LP Smart Side 38 series Carrara Stucco Finish
Application instructions
precision series 38 series, 76 series, 190 series primed panel siding Including SilverSide & SmartFinish (smooth square edge panel siding is approved for use with Carrara Stucco Finish ONLY)
General
- At the time of manufacture, LP’s Precision Series primed panel siding meets or exceeds the performance standards set forth in
- ICC-ES acceptance criteria ACC321 and has achieved code recognition under the ICC-ES Report ESR-1301, and HUD recognition under HUD-MR-1318. For copies of ESR-1301, call LP Customer
- Support at 1-800-648-6893 or go on-line at http://www.icc-es.org/reports/pdf_files/ICC-ES/ESR-1301.pdf
- Minimum 6 in. clearance must be maintained between siding and finish grade.
- Siding applied adjacent to porches, patios, walks, etc. must have a clearance of at least 1 in. above any surface.
- Minimum 1″ clearance at intersection with roof line
- Apply siding in a manner that prevents moisture intrusion and water buildup.
- All exposed wood substrate must be primed and painted in a manner that prevents moisture intrusion and water buildup.
- In non-traditional ICF and SIP assemblies, the ICF or SIP manufacturer must prescribe the fastening specifications. Note: LP does not recommend LP SmartSide for use in these non-traditional assemblies. If used, LP will not warrant for Buckling and Shrinkage. However, balance of warranty does remain intact.
- When using wet blown cellulose insulation, the insulation must not be in direct contact with the siding and it must be allowed to dry a minimum of 24 hours or longer if specified by the insulation manufacturer.
- DO NOT USE STAPLES
Storage
- Store off the ground well supported, on a flat surface, under aroof or separate waterproof covering
- Keep siding clean and dry. Inspect prior to application.
- Allow siding to adjust to atmospheric conditions before application
Stud Spacing
Precision Series 38 Series and 76 Series panel siding must be installed on 16 in. OC framing only. When installing on 24 in. OC framing, Precision Series 190 Series panel siding is required.
Moisture
- Moisture control and moisture vapor control are critical elements of proper housing design. Check your local building codes for application procedures for handling moisture and moisture vapor in your area.
- As with all wood products, do not apply engineered wood siding to a structure having excessive moisture conditions such as drying concrete or plaster. If such conditions exist, the building should be well ventilated to allow it to dry prior to the application of the siding.
- Siding must not be applied to green or crooked structural framing members. Do not apply siding over rain-soaked or buckled sheathing materials.
- Gutters are recommended for control of roof water run off.
Vapor Retarder/Weather Barrier
- A properly installed breathable water-resistive barrier is required behind the siding.
- Consult your local building code for details.
- LP will assume no responsibility for water penetration
Gaps & Sealants
Seal all gaps with a high-quality, non-hardening, paintable sealant with a minimum stated service life of 30 years. Follow the sealant manufacturer’s instructions for application.
Flashing, Windows, Doors & Openings
All openings must be properly sealed or flashed in a manner that prevents moisture intrusion or buildup. Several examples that accomplish this are shown on the following pages.
Trim
- Trim should be thick enough so the siding does not extend beyond the face of the trim.
- Trim and fascia must be applied in a manner that will not allow moisture intrusion or water buildup.
- LP® SmartSide® siding is not designed and/or manufactured to be used as trim or fascia. LP SmartSide trim and fascia are available in a variety of dimensions.
Finishing Instructions
- Priming all exposed wood substrates before painting is highly recommended.
- Paint all exposed siding surfaces including drip edges.
- Thoroughly paint the bottom edges of siding especially all cut ends next to the roof line.
- Apply paint as soon as possible and within 180 days of application.
- Follow the coating manufacturer’s application and maintenance instructions.
- High-quality acrylic latex paint, specially formulated for use on wood and engineered wood substrates, is highly recommended.
- Semi-gloss or satin finish oil or alkyd paints are acceptable.
- For flat alkyd paint, please check with the coating manufacturers for their recommendations for use on composite wood siding.
Nailing Instructions
- Use minimum 6d, corrosion resistant according to ASTM 641, box style nails for 38 Series and 76 Series panels and minimum 8d for 190 Series panels. . Do not use electroplated fasteners.
- Penetrate studs or studs and wood sheathing a combined minimum of 1 1/2 in.
- For 38 Series panels, double nailing procedure meets wall bracing requirements and 5/16 in. shear wall design values.
- For 76 Series and 190 Series panels, single nailing meets wall bracing requirements. To meet the equivalent 3/8″ shear wall design values, double nailing procedures must be used. It may be necessary to angle drive the second nail in order to penetrate the framing. Seal nails driven below the surface.
- Shear values for panels applied directly to studs shall be no greater than noted in Table 1 of the ICC-ES report ESR-1301.
- Not warranted for application on SIP and ICF assemblies.
CAUTION
- 38 Series and 76 Series panels must be installed on 16 in. OC framing only. When installing on 24 in. OC framing, 190 Series panels are required.
- Backside of panel must not come in contact with masonry foundation.
- Do not force siding into place. Maintain the illustrated 1/8 in. space behind the joint to allow for expansion while the panel equilibrates with the local environment.
- LP® SmartSide® Panel siding must not be attached by stapling.
- DO NOT INSTALL OVER ALIGNMENT BEAD. Install panels in light contact to the edge of alignment bead. (see above drawing)
4 ft. x 8 ft. Ungrooved Shiplap Panel
LP SmartSide Panel Siding Joint Details
HORIZONTAL beltline
For multi-story buildings, make provisions at horizontal joints for “setting” shrinkage of framing, especially when applying siding directly to studs
Siding Must Not Contact Masonry
1 in. Roof & Chimney Clearance
Gap, Flash Doors & Windows
The Louisiana-Pacific Corporation (“LP”) LP SmartSide Siding (the “Products”)
limited warranty (the “Warranty”) applies only to structures on which the
Products have been applied, finished and maintained in accordance with the
published application, finishing and maintenance instructions in effect at the
time of application. The failure to follow such application, finishing or
maintenance instructions will void the Warranty as to the portion of the
Products affected by the variance (the “Affected Products”).
LP assumes no liability for any loss or damage sustained by the Affected
Products and is expressly released by the purchaser or owner from any such
loss or liability.
Any modification of the Warranty’s application, finishing or maintenance
requirements is void and unenforceable unless approved in writing prior to
application by the Siding General Manager or his designee and a member of the
LP Legal Department.
Warranty
For a copy of the warranty or for installation and technical support, visit the LP SmartSide product support Web site at: www.lpcorp/smartside.com or for additional support call 800.450.6106.
ALTERNATE INSIDE CORNER DETAILS
NEED HELP
© 2011 Louisiana-Pacific Corporation. All rights reserved. LP and SmartSide are registered trademarks of Louisiana-Pacific Corporation. Printed in U.S.A.
NOTE : Louisiana-Pacific Corporation periodically updates and revises its product information. To verify that this version is current, call 800-450-6106.
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>