Danfoss 084H5001 Intelligent Purging System IPS 8 Ammonia User Guide
- June 1, 2024
- Danfoss
Table of Contents
Danfoss 084H5001 Intelligent Purging System IPS 8 Ammonia
Mechanical / Refrigeration check
-
Verify that IPS 8 purger is installed, wired, and piped as per Danfoss instructions
-
Horizontal alignment requirements must be within 2 degrees to IPS top cover. See Fig. 1
-
The purger unit should be always kept in an upright position – from receipt to final installation, including possible lift to a high final location. See Fig. 2
-
Leave space around IPS for air circulation flow. Do not install it right up to a wall. See Fig. 3
-
Inspection of possible dirt in gas lines. See Fig. 4
- For purge point connect gas line a slope towards the IPS8 purger, must be observed.
- No liquid traps
-
Remember to remove rubber plug. See Fig. 5.
-
Carry out proper vacuum on the purge point connect gas line and R717 side of IPS 8 purger. The R717 side of IPS 8 purger must be pressurized prior to the IPS 8 being put into operation.
-
Before connecting power supply to IPS let it stand upright for min. 6 hours after it has been placed at its final location
-
After mechanical installation, but before connecting power supply IPS, please check:
- If Danfoss drain valve used (Type SV or ICF with ICFD), then check:
- SV: See Fig. 6a
- Check throttle valve A is opened, and SV is properly assembled.
- Check that port B is closed by bolt.
- ICFD: See Fig. 6b
- Check stop valves
- Check coil is installed on solenoids (Solenoid for ICF w/ICFD (DO6) – if used)
-
Open stop valves D, as we have vacuumized the pipes before. Open manually one of purge point solenoids E. See Fig. 6a and 6b
For general mechanical installation guidance/practice. See Fig. 6c
Electrical check -
Check Main power supply. See Fig. 7
- 084H5001, IPS 8: 230 V, AC 50 Hz
- 084H5002, IPS 8: 230 V, AC 60 Hz
- Power to be connected to Main switch: QS1 and Terminal: XT0
- Terminals on QS1
- 3, L2 – Line phase
- 1, L1 – Neutral
- Terminal XT0
- PE – Earth
-
Check connections to field connected Purge point solenoids and ICFD solenoid (if used) See Fig. 8a and 8b
- Coils voltage. Same as Main power supply. No further action needed.
- At different voltage for field connected solenoids coils. See Fig. 9
IPS controller (MCX15B2) setup
After Mechanical / Refrigeration check, the conditions for startup must be checked. See Fig. 10 for overview of Electrical Panel and location of Thermal magnetic miniature circuit breakers
-
Switch ON:
- QS1, QM2 and QM4. See Fig. 10
-
Before start of compressor, temperatures needs to be checked. Should all be within: +/-1 K˝ (OK) – if OK then go to 15)If Temperatures are not within: +/-1 K˝ then check cables and connections of pressure and temperature sensors. (NOK)
-
Preparation for start compressor
- Switch ON – See Fig. 10
- QM1 and QM3
Below (E10, System is OFF and the icon ) inform that MainSwitch is OFF
-
Navigation to Main Switch parameter
-
- Select “Start”
- Select “Main Switch ON” and
-
Go to Main Screen and watch compressor in operation and pressure/temperature
changing.
As compressor is in operation, pressure and temperature is changing, after
about 15-25 minutes we should observe changes as re°ected on below screens.
See development below from left to right
If the compressor is running for 15-25 minutes, without pressure and temperature really changing (example below) and compressor then becomes very hot [90 ˙C-110 ˙C] on its surface, – then STOP IPS and call Danfoss.
IPS MCX controller – Quick start
Basically, the IPS with the built-in MCX controller, only need one setting, How many Purge points?See steps below for how to navigate to the parameter for entering how many Purge points which is connected.
- Navigate from the Main Menu to Start by
- Select “Main Switch OFF”
- Go to Main Menu
- Navigate from the Main Menu to “Login”
- Enter password “200”
- Choose “Parameters”
- Choose “Unit Conÿg”
- Choose “Valve Settings”
- Enter the number of purge solenoid valves connected to the IPS (factory setting is:8)
- Go back to Start and chose ‘Main Switch ON’, and go back to main screen
See development below from left to right
IPS MCX controller – Quick start
It can be useful during commissioning to quickly move the next Purge point,
in order not to wait to IPS internal time cycle between purge points.
See steps below for how to navigate to the parameter in question.
- Navigate from the Main Menu to Start by
- Enter password “200”
- Choose “Start”
- Choose “Next Purge Point” and
- Press
, to go back to main screen - Check that Purge Point has been changed to the next one. (below example from Purge Point 3 to Purge Point 4)
See development below from left to right
Lifting Procedure
Connection points
Installation
Fig. 6C
DanfossA/5
Climate Solutions• danfoss.com • +45 7488 2222
Any information, including, but not limited to information on selection of
product, its application or use, product design, weight, dimensions, capacity
or any other technical data in product manuals, catalogues descriptions,
advertisements, etc. and whether made available in writing, orally,
electronically, online or via download, shall be considered informative, and
is only binding if and to the extent, explicit reference is made in a
quotation or order confirmation. Danfoss cannot accept any responsibility for
possible errors in catalogues, brochures, videos and other material. Danfoss
reserves the right to alter its products without notice. This also applies to
products ordered but not delivered provided that such alterations can be made
without changes to form, fit or function of the product.
All trademarks in this material are property of Danfoss A/Sor Danfoss group
companies. Danfoss and the Danfoss logo are trademarks of Danfoss A/S. All
rights reserved.
© Danfoss | Climate Solutions | 2023.07
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>