FOX-ESS ECS2900 Energy Cube Battery Installation Guide

June 12, 2024
FOX-ESS

FOX-ESS ECS2900 Energy Cube Battery

FOX-ESS ECS2900 Energy Cube Battery

Tools Required

The following tools will be required to install CM (Cube Master) and CS (Cube Slave).

  • Screw Driver

  • Crimping Modular

  • Safety Shoes

  • Multimeter

  • Safety Gloves

  • Safety Goggles

  • Plier

  • Ribbon

  • Electric Drill

  • Track Level Bar

  • Tape

  • Marker

Packing List

For CS :

No. Items
A Mounting screw pack
B installation guide & User manual

For CM :

Packing List

No. Items
A Mounting screw pack
B Fixing bracket
C Foot stand
D Communication cable (BMS-inverter) (1.2m)
E Grounding cable (1.2ml
F DC positive output cable (1.2ml
G DC negative output cable (1.2m)
H Installation guide & User manual
I Expansion tube2 & Expansion screw2
J Waterproof cover

Terminals

For CS :

Terminals

For CM :

Installation Steps

Step 1

Install a CS with four feet stand (Item C) and place it on the ground and adjust it to the level. After installing the feet stand, use a track level bar to confirm the level. Insert the waterproof cover (Item J) into the bottom of the battery and lock it in place with the clip.

Step 2

Place the battery 20mm against the wall.

Note: Please make sure the Operating Status LED is on your left hand side when you facing the battery model.

Step 3

Stack the batteries one by one.

Step 4

Place the two fixing brackets (Item B) close to the wall and install them on both sides of the battery.

Step 5

Mark the wall through the bracket hole.

Step 6

Punch after removing the CM. Drill holes with electric drill, make sure the holes are at least 50mm deep, and then tighten the expansion tubes (Item I).

Step 7

After stacking CM again, fix the battery on the wall.

Step 8

Fix the mounting screw packs on both sides of the battery, the installation is over.

Note: Please make sure each system including 1 CM and 1 CS. CS less than 6 pieces:

Wiring Steps

A: Connect the inverter and make sure the wiring position is correct, as shown in the figure below.

Note: Inverter wiring refer to the inverter user manual.

PIN ASSIGNMENTS FRONT VIEW

CONN.1 PIN CONN.2 PIN
1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8

Note: Default wire harness PIN to PIN

PIN Function Definitions
1 GND
2 GND
3 RS485-B
4 BMS-CANL
5 BMS-CANH
6 BMS-CANH
7 BMS-CANL
8 RS485-A

B: Connect the grounding cable. The figure is shown in below.

System Start Up

CM operation:

  1. Before starting, please dial DIP to the correct position. DIP represents the number of CS in the system. Please refer to the following table for details:
    DIP position| CS
    ---|---
    0| 1
    1| 2
    2| 3
    3| 4
    4| 5
    5| 6
  2. Normal mode: When there is PV and grid access, turn on DC switch first, then press “POWER” button.
  3. Black start: When there is no PV and grid access, turn on DC switch first, then press “POWER” button, then press and hold “B-Start” button and release it after 10s.

Startup steps:

Turn on DC switch and press the POWER switch. Alarm display and Alarm LED on CS/CM will light up at the same time for ls to prove that the system is powered on successfully. The control panel is shown in below.
System Start Up

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals