Vibrasystems SMSR-A-AF-AT Spring Vibration Isolator Seismic Restrained Instruction Manual
- June 9, 2024
- Vibrasystems
Table of Contents
SMSR-A/AF/AT
Installation Instructions
SMSR-A-AF-AT Spring Vibration Isolator Seismic Restrained
- Check each isolator’s model number against the information on the packing slip, before beginning installation.
- Secure the isolatorʼs base plate (BP) to the equipment support structure – concrete foundation or metal frame, according to the equipment base’s drawings for the locations of the mounting holes. All bolts and anchor hardware must be a minimum of grade 2. If recommended by the manufacturer or installation engineer a higher grade, then follow their recommendation. All anchors must be installed according to the installation drawings and instructions.
- Use a forklift, crane, or any other certified lifting machine to raise the equipment to be installed. Slowly lower the equipment on top of the isolators and make sure that the equipment’s base is perfectly aligned with the isolator’s top plate (BTP or WTP).
SMSR-AT
4a) When the equipment, which must be at the full operating weight, is placed
onto the isolator, the isolator’s spring will be compressed according to the
load vs. deflection chart for this model.
5a) Loose the restraint nuts (RN) to allow leveling of the top plate (BTP).
6a) Level each isolator in sequence by turning the leveling bolt (LB) a full
clockwise turn at a time.
7a) After the leveling is done, run down the lock nut (N) to the equipmentʼs
base.
8a) Adjust the vertical restraint nuts (RN) to allow a free movement of the
installed equipment with an allowed gap from 1/8” to 3/16”.
SMSR-A & SMSR-AF
4b) Make sure that the top plates (WTP) are properly attached or welded to the
equipment’s base. Welding to steel base is permitted provided the weld
achieves the required strength.
5b) When the equipment, which must be at the full operating weight, is placed
onto the isolator, the isolator’s spring will be compressed according to the
load vs. deflection chart for this model.
6b) Loose the restraint nuts (RN) to allow leveling of the top plate (WTP).
7b) Level each isolator in sequence by turning the leveling nut (LN) a full
clockwise turn at a time.
8b) Adjust the vertical restraint nuts (RN) to allow a free movement of the
installed equipment with an allowed gap from 1/8” to 3/16”.