Mounting and Operating Instructions
Target group: Skilled electricians
Intended Application: Emergency Lighting, not suitable for private use
DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITY
The information, recommendations, descriptions, and safety notations in this
document are based on Eaton Corporation’s (“Eaton”) experience and judgment
and may not cover all contingencies. If further information is required, an
Eaton sales office should be consulted. The sale of the product shown in this
literature is subject to the terms and conditions outlined in appropriate
Eaton selling policies or other contractual agreements between Eaton and the
purchaser.
THERE ARE NO UNDERSTANDINGS, AGREEMENTS, WARRANTIES, EXPRESSED OR IMPLIED,
INCLUDING WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MERCHANTABILITY,
OTHER THAN THOSE SPECIFICALLY SET OUT IN ANY EXISTING CONTRACT BETWEEN THE
PARTIES. ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON. THE CONTENTS
OF THIS DOCUMENT SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE
PARTIES.
In no event will Eaton be responsible to the purchaser or user in contract, in
tort (including negligence), strict liability or otherwise for any special,
indirect, incidental or consequential damage or loss whatsoever, including but
not limited to damage or loss of use of equipment, plant or power system, cost
of capital, loss of power, additional expenses in the use of existing power
facilities, or claims against the purchaser or user by its customers resulting
from the use of the information, recommendations and descriptions contained
herein. The information contained in this manual is subject to change without
notice.
**** SAFETY INSTRUCTIONS
- The device shall only be used for its intended purpose and in undamaged and flawless condition
- Only genuine Eaton spare parts may be used for replacement and repair
- Prior to its initial operation, the luminaire will have to be checked in line with the instructions (see installation sector)
- Carry out the marking of the emergency luminaire: Assign the circuit and the luminaire No. and enter them.
- Recording in the minutes shall be performed in compliance with the national regulations (is deleted in case of automatic recording).
- Any foreign object shall be removed from the luminaire prior to its initial operation!
- Observe the national safety rules and regulations to prevent accidents as well as the safety instructions included in these operating instructions marked with
1 Conformity with standards
Conforms to: EN 60 598-1, EN 60 598-2-22, and DIN EN 1838.
Developed, manufactured, and tested in accordance with DIN EN ISO 9001.
Brief description Scope of application
As a self-contained luminaire, the Atlantic LED and Outdoor Wall CGLine+ safety luminaires are suitable for installations acc. to EN 50 172, DIN VDE 0100-718, and DIN V VDE V 0108-100. With a CGLine+ web controller, the self- contained luminaires can be monitored centrally via a bus cable.
2.1 Use in food processing areas
This luminaire range complies with the requirements of food law in line with
regulation (EC) No 852/2004 (HACCP) annex II chapter I paragraph 2a, b chapter
II paragraph 1c in the field of lighting products.
Please note:
The HACCP Certification does not include the resistance of the luminaire
against aggressive cleaning compounds. This must be clarified on a case-by-
case basis.
3 General notes for connection and operation of the luminaires
The Mains cable should be connected to the terminals L1, L2, N, and PE on the printed circuit board, where L is an unswitched permanent connection for the electronics and L2 is used for switching the lamp on and off with a light switch as and when required. For maintained light switching the supplied wire jumper must be inserted in the L1 and L2 terminals.
a battery connection
b mode switch (see chapter 5.4)
c bus connection (see chapter 5.4)
d connection for battery heating (optional – type „H“
e battery holder
Bus connection
With central monitoring via the CGLine+ bus, a bus connection is via the D1
and D2 terminals, whereby the terminals each exist twice and are bypassed on
the device side to enable through-wiring.
LED-connection
The integrated supply electronics are suitable for the operation of various
LED circuit boards. When switching on for the first time or after the network
and battery have been disconnected or after a reset (test button pressed > 10
s) the electronics detect the circuit board used and set the correct
parameters for operation. This initialization process requires approx. 5 s.
LEDs are sensitive to ESD, which means against electrostatic discharge. This
can already happen by touching connections. Please take suitable electronic
protection measures!! Only connect in dead-voltage condition!
Battery connection
Commissioning should only be carried out at temperatures within the specified
range. Charging of the batteries at excessive or insufficient temperatures may
damage batteries and is therefore prevented by the electronics. To fathom
battery life please note the startup date on the battery in the given data
field!
Battery heating (optional – type „H“)
Atlantic LED and Outdoor Wall CGLine+ with the extension „H“ are equipped with
a battery heater. The battery heater allows the operation of this luminaire at
low ambient
temperatures up to -20°C. The heater switches on at low temperature
automatically and switches off at sufficient temperature.
Mounting
4.1 Atlantic LED CGLine+
Prepare the required cable entry and fit a cable gland. Fix the gallery to the ceiling or wall using the stainless steel screws (included).
Note: Atlantic LED R escape route lighting mainly emits light from the short sides, contrary to conventional fluorescent lighting.
Pictograms not included, for order numbers see page 15
The cable jacket must be removed just behind the gland. Because of the limited space, the wires must be kept as short as possible and should only be placed within the indicated space. Keep the square area in the center of the luminaire free. (see chapter 2 for details)
Atlantic LED S and D versions: Fix one (S) or two (D) pictograms in the
diffuser.
Atlantic LED S: When applying a pictogram please note the difference between
the top and bottom sides of the diffuser.
Put the pictogram(s) carefully in place and verify if they are locked behind the right edges.
The diffuser and the reflector unit can be snapped together. Please note the diffuser fits only one way to the reflector unit.
Connect the battery to the circuit board. The combined diffuser and reflector unit can be placed in the enclosure. Check beforehand whether the position of the connectors on the reflector unit and the enclosure correspond and then insert the unit in the gallery.
Tighten the 4 bolts carefully and securely.
Torque: 1 Nm
Dimensional drawings
4.2 Outdoor Wall CGLine+
Insert mains and bus cable and attach the wall plate to the wall. Remove cable jacket with the exception of the last 8 cm. Make a hole in the grommet in the base, insert the wires and then put the box on the wall plate. Attach the box to the wall plate by fast tightening of the four pre-mounted screws. Torque: 1 Nm
The cable jacket must be removed just behind the gland. Because of the limited
space, the wires must be kept as short as possible and should only be placed
within the indicated
space. Keep the square area in the center of the luminaire free.
Connect the battery to the circuit board (see chapter 4.1)
Dimensional drawings
Installation / Operation
5.1 Operation mode
a. Duration of emergency lighting
Display | Encoding | Description |
---|---|---|
00x | Duration of emergency lighting 1h. | |
10x | Duration of emergency lighting 3h. (Default) | |
01x | Duration of emergency lighting 8h. |
**IMPORTANT**
b. Automatic operation – time of function test and duration test
Function / Duration test
Without the connection of the luminaire to a CGLine+ monitoring system, the
function test is performed weekly at the time of the first commissioning or
last reset.
The time of the curation test should always be specified so that the following
phase of battery charging is not implemented during active times in the
building. The factory setting for the continuous operation test intends that
the first duration test is carried out automatically 6 months + 12 hours after
the first commissioning or last reset. Following that, the next test occurs
precisely 6 months after the last duration test.
Note:
as commissioning is usually carried out during the day and the duration test
therefore occurs (following 6 months + 12 hours) during the night, this should
avoid the duration of the duration test falling within the operating time of
the building.
| xx0| AUTO DT Function OFF
Duration test (DT) has to be started manually if about 12 months no DT was
made, the display changes from green to yellow
---|---|---
| xx1| AUTO DT Function ON (Default)
The duration test will be started automatically twice a year.
A modifi cation of operating mode must be confi armed by pressing the test button < 1 s. After a reset (Disconnecting the mains supply and battery or via the test button (press and hold for > 10 s )) the new parameter will also be set.
If the time cannot be set to occur during idle operating times in this way, the automatic duration test can be deactivated with CGLine+ luminaires. To implement this, switch the DIP switch 3 to ‚Off‘. The duration test can then be started manually at a suitable time with the test button (press and hold for 5 – 10 s).
If this test is not started within 12 months, a yellow LED on the luminaire
lights up to signal a due test.
When the LED at the test button blinks yellow after a DT this test failed. The
battery has to be replaced (Order no. 400 71 353 399). Please note the date of
the first commissioning of the new battery.
5.2 Dim-Level
Setting the brightness in mains mode by using the test button:
– Push the test button for t < 1 s
– After the first flash of the LED the brightness can be altered by pushing
the button again in 3 steps (100% / 30% / 10%). Every push of the button
raises the brightness by 1 step. If the highest step is reached it begins
again with the lowest.
5.3 TEST button and display
a. Magnet switch
Duration pressing
button [s]| Function
---|---
< 1| Display of emergency operating time Display of luminaire address Setting
the dim-level
5-Jan| start function test
10-May| Start / stop duration test
20-Oct| Reset of the luminaire
The functions can be started by using the provided magnet. Position the magnet for the time specified on the luminaire as illustrated in the picture.
5.3 TEST button and display
b. Status display
| Status| | LED
---|---|---|---
Operation mode| No failure| | lights up green
Emergency mode| | LED is off
Delay on mains return| | blinks 1 s green, yellow in rotation
Function test| | blinks green
Duration test| | blinks green
Luminaire is blocked| | blinks 0.5 s green, yellow in rotation
Failure indication| Charging failure| | blinks yellow slow 0.5 Hz|
Function test failed| | blinks yellow slow 0.5 Hz
Duration test failed| | blinks yellow slow 0.5 Hz
Lamp failure| | yellow blinks fast 2 Hz
Other| 1-h Emergency operation| | red| After pushing the test button for (t <
1s)
3-h Emergency operation| | yellow
8-h Emergency operation| | grün / green
2-h Emergency operation|
ast (f )alternation
| red / yellow
Display of luminaire address| [100er]| | green
[10er]| | yellow
[1er]| | red
Duration not possible because battery partly charged| | red for 1 s after
button was pushed
Reset of luminaire| | 0,5 s green, 0,5 s red
No duration test during the last 12 month| | yellow
Important displays with the test- button
OK
TEST
Charge failure / Ladefehler
LED-Fehler
erforderlich
If the ambient temperature is too low, see specification 5.
Exchange battery Order No. 400 71 353 667 see also chapter 8
Colour yellow: a mixed colour from green and red
Legend
LED Lighting
LED is off
blinks slow 0,5 Hz / 1 Hz
blinks fast 2 Hz
5.4 Luminaire monitoring CGLine+
The Atlantic and Outdoor LED CGLine+ luminaires are prepared for connection to
a central CGLine+ luminaire monitoring. An individual, distinct identification
number (6 characters) is assigned to every luminaire in the CGLine+ luminaire
series.
This ID number must be transferred to the installation plan for subsequent
configuration work. The removable ID sticker in the luminaire can be used for
this.
To the central CGLine+ monitoring system maximum 4 bus cables (2-core) with up
to 100 luminaires each can be connected. The max. data line length per line is
0.5 mm2 : 330 m / 1.0 mm2
: 660 m 1.5 mm2 : 1000m
Bus voltage: | 22,5 VDC |
---|---|
Max. voltage drop: | 13 VDC |
Bus Current | 400 mA |
An unscreened, 2-core cable with free bus topology can be used as a data cable. Each of the luminaires connected to the data bus cable is automatically recognized by the CG-Controller. The CG-Controller can assign a short address to the connected luminaires, which can be polled via the three LEDs on the luminaire. For more information regarding addressing please see the operating instructions of a central CGLine+ monitoring system.
Servicing / Maintenance
Observe the relevant national regulations applying to the maintenance, servicing, and checking of electrical apparatus! In case of returns, you need an RMA – number from us. For further information see www.ceag.de. The light source of this luminaire is not replaceable; when the light source reaches its end of life the whole luminaire shall be replaced.
Disposal / Recycling
When disposing of defective devices, comply with valid regulations for recycling and waste disposal. Plastic parts are marked with corresponding symbols. The LiIon battery integrated in the luminaire must be returned to the seller or an approved disposal location and must not be disposed of by the customer, in accordance with the 2006/66/EC directive.
Technical Data
Power input | 230 V AC, 50/60 Hz |
---|---|
Housing material | Luminaire: polycarbonat, aluminium |
Housing colour | grey |
Luminous flux phiE/phiNenn at the end of rated operating time | 1 h |
100%
| 3 h
65%
| 8 h
25%
Light source| HighPower LEDs 2 x 1.6 W
Power consumption mains operation (apparent/effective power)| Ohne Heizung
Mit Heizung without heating with heating| 7.2 VA / 7.0 W
9.4 VA / 9.3 W
Insulation class| I
Protection category acc. to EN 60529| IP65
Permissible ambient temperature without heating| +5 °C .. +35 °C
Permissible ambient temperature with heating| -20 °C .. +35 °C
Terminals (doubled for through wiring)| plug-in terminal mains, L,L´, PE up
to 2.5 mm2 (max 6 A) CGLine+ bus up to 1.5 mm2
Battery| Lithium-Ion 3.7 V / 4000 mAh with multiple protection circuits
Weight| Atlantic D: 1,74 kg
Outdoor Wall: 3,0 kg
We reserve the right to make technical alterations without notice!
Eaton is dedicated to ensuring that reliable, efficient, and safe power is
available when it’s needed most. With unparalleled knowledge of electrical
power management across industries, experts at Eaton deliver customized,
integrated solutions to solve our customers’ most critical challenges.
Our focus is on delivering the right solution for the application. But,
decision-makers demand more than just innovative products. They turn to Eaton
for an unwavering commitment to personal support that makes customer success a
top priority. For more information, visit
www.eaton.com/electrical.
Eaton Industries Manufacturing GmbH
Electrical Sector EMEA
Route de la Longeraie 7
1110 Morges, Switzerland
Eaton.eu
CEAG Notlichtsysteme GmbH
Senator-Schwartz-Ring 26
59494 Soest, Germany
Tel.: +49 (0) 2921 69-870
Fax: +49 (0) 2921 69-617
E-Mail: info-n@ceag.de
Web: www.ceag.de
© 2022 Eaton All Rights Reserved
Printed in Germany
Order No. 40071860262_E
Publication No. IB451053ML
Juli 2022
Eaton is a registered trademark.
All trademarks are property of their respective owners.
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>