Specifications

  • Product Name: BOXED ATS System
  • Function: Automatically starts generator for emergency power supply
  • Charge Current: 1A
  • Operation Modes: Automatic and Manual

Product Usage Instructions

Operation Steps

  1. Connect the ATS box to the generator control panel using the provided cable.
  2. Switch the position to AUTO.

Automatic Position Setup
Press the AUTO button to activate automatic mode. The AUTO indicator light will turn on, indicating that the ATS system is working automatically.

ATS System Working
When the mains power supply is off, the ATS system will open the air damper control and start the generator within 2 seconds. After the generator runs for 5 seconds, the system will switch the load to the generator power supply.

ATS System Start 3 Times
If the generator fails to start initially, the ATS system will attempt to start it three times before indicating a fault.

Generator Stop
When the mains power supply is restored, the ATS system will transfer the load back to the mains power and stop the generator after running for 5 seconds without a load.

Manual Start
To manually control the generator, switch the position to MANUAL.

Automatic Air Damper Control
If your generator has air damper control, the ATS system will automatically open and close it when starting and stopping the generator.

PRODUCT INSTRUCTION

ATS system is designed for the main power supply off and start the generator for emergency power supply.
When the mains power supply is off, the generator will start in 2-6 seconds and then supply power to load. When the main power supply is on, the ATS system will automatically transfer the switch to the main power supply, and then stop the generator in 2-6 seconds.

  • This system uses SCM core and digital techniques to control and manage the automatic working system.
  • Easy installation and operation
  • Automatic working without people inspection. When the transfer is broken the system will remain an error record and indicate engineer to inspect and re-setup. Don’t worry about the mains power supply and generator power supply action same time.
  • There is a battery charger inside, and the battery of the generator automatically.

OPERATION STEPS

Use the cable to connect the ATS box to the generator control panel, and switch the “AUTO” position.

Automatic postion setup
Press the AUTO button, the indicator light AUTO will be on, ATS system will work automatically.

ATS system working
When the ATS system works automatically, if the main power supply is off, the ATS system will automatically open the air damper control start the generator in 2 seconds, and wait for the generator to run 5 seconds, the system will switch the load to the generator power supply.

The ATS system starts 3 times
When the generator can not start well, the ATS system will start the generator circularly 3 times as below Mains power supply off→ generator starts 3 seconds first time→ start unsuccessfully and wait for 5 seconds→ generator starts 4 seconds second time→start unsuccessfully and wait seconds→ generator start 5 seconds third time

NOTICE: When the generator can not start successfully in 3 times, the indicator light “FAULT” will be on.

Generator stop
When the mains power supply is on again, the ATS system will transfer the load to the mains power supply, and the generator will stop after running 5 seconds without load.

Manual start
If you don’t need the ATS system to work automatically, please put the switch to the “MANUAL” position.

Automatic air damper control
If the generator has air damper control, when the generator starts, the ATS system will automatically open it and close it after the generator start successfully.

OPERATION INSTRUCTION

BOXED-Ats-System-FIG-1

Battery maintenance

ATS system will charge the battery automatically,the charge current is 1A.

ATS access to power system diagram

BOXED-Ats-System-FIG-2

Access ATS system

BOXED-Ats-System-FIG-3

Wiring diagram

Single-phase. single voltage wiring diagram:

BOXED-Ats-System-FIG-4

Three-phase. Double voltage wiring diagram:

BOXED-Ats-System-FIG-5

Notice

  1. ATS power must be bigger than load power.
  2. Must add an AIR-BREAKER to protect the ATS system, when you connect the main power cable to the ATS box.
  3. Please run the generator successfully at the “OFF” position first, then you can use “AUTO” to work automatically.
  4. Please turn the air-breaker switch to the “ON” position when using the ATS system.
  5. Only electrician can open the box for inspection and repair, there is high voltage danger,

Frequently Asked Questions

  • Q: What should I do if the generator fails to start after three attempts?
    • A: If the generator fails to start successfully after three attempts, the indicator light FAULT will illuminate.
  • Q: Can I manually start the generator?
    • A: Yes, you can switch the ATS system to MANUAL position for manual control of the generator.

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

Related Manuals