DEWALT CCU+TM Critical Connection Undercut Anchoring System Instruction Manual
- June 1, 2024
- Dewalt
Table of Contents
- CCU+™ Critical Connection Undercut Anchoring System
- THE CRITICAL CONNECTION UNDERCUT SYSTEM (CCU+™)
- COMPLIANCE
- SPECIFICATION OF THE ANCHOR
- INSTALLATION
- GENERAL / GETTING PREPARED
- PRIMARY HOLE DRILLING
- UNDERCUTTING
- CONVENTIONAL BITS
- ANCHOR SETTING
- REPLACING WEAR PARTS
- TROUBLE SHOOTING
- Read User Manual Online (PDF format)
- Download This Manual (PDF format)
DEWALT CCU+TM Critical Connection Undercut Anchoring System Instruction
Manual
CCU+™ Critical Connection Undercut Anchoring System
The DeWALT Critical Connection Undercut (CCU+TM) Anchoring system is a specified anchor system incorporating an undercut anchor and various installation accessories and specific power tools. The contents of this manual will help guide the installer through proper preparation, installation, maintenance and troubleshooting of the CCU+TM anchoring system.
This manual is not a substitute for construction drawings or specifications. CCU+TM anchors may be part of an engineered structure. Proper anchor placement and installation are critical to the performance of the structure.
The installer should make sure they have the correct anchors, bits, hammers, vacs and accessories to install CCU+TM anchors as per any construction drawings.
THE CRITICAL CONNECTION UNDERCUT SYSTEM (CCU+™)
A. Anchor
B. Primary bit
HSDB: Hollow stop drill bit for specific drilling depth, primarily used
for drilling until collar touches the concrete surface in case of preset
installation
HDB: Hollow drill bit for variable drilling depth, primarily used for
drilling through the fixture in case of thru bolt installation
C. Undercut bit
HUCB: Hollow undercut bit for dust-free undercutting
UCB: Undercut bit for economic undercutting
D. Setting tool
Setting tool for power tool installation with SDS connector
Setting tool for manual installation with hand held hammer
COMPLIANCE
A. ICC-ES
Steel grades A36 and A193, Gr. B7 and SS316 qualified according to ACI 355.2
for design according to ACI 318: ESR-4810 Download Anchor Design Software DDA™
at: DEWALT.COM/DDA
B. OSHA
Part of an OSHA Table 1 compliant system.
Dust Extractor System with HEPA Filtration and /Auto Cleaning Hollow Bit
System: HDB, HSDB, HUCB (see above) Use hood, shroud, etc. to control dust
when using conventional bits.
**C. Anchors Made In The USA***
We can certify CCU+™ anchors for Trade Agreements Act (TAA), Buy American Act
(BAA), American Iron and Steel (AIS), Build America, Buy America Act (BABA),
and Buy America (FHWA, FAA, FRA, FTA).
Please email anchors@dewalt.com for certification information.
*As of the date of this Instruction Manual, DeWALT Critical Connection Undercut Anchors meet the requirements of the Trade Agreements Act (TAA), Buy American Act (BAA), American Iron and Steel (AIS), Build America, Buy America Act (BABA), and Buy America (FHWA, FAA, FRA, FTA).
SPECIFICATION OF THE ANCHOR
A. Material
- Rod
- Sleeve
- Cone
- Nut
- Washer
Component No. | Description | Specifications |
---|---|---|
Carbon Steel Version (A36 or B7) | High Strength Stainless Steel |
(316 SS)
1| Rod| ASTM A36 or ASTM A193 Grade B7,Zinc Plated ASTM B633, SC1 (Fe/Zn 5)|
ASTM A193, Grade 8BM, Class 2 (316 SS)
2| Sleeve| Carbon Steel, Zinc Plated ASTM B633, SC1 (Fe/Zn 5)| AISI 316 SS
3| Cone| Carbon Steel, Zinc Plated ASTM B633, SC1 (Fe/Zn 5)| AISI 316 SS
4| Nut| 3/8″ DIA A36: SAE J955 Grade 23/8″ DIA B7: SAE J955 Grade 81/2″, 5/8″,
3/4″ DIA: ASTM A563, Grade C| 3/8″ DIA SS2: ASTM F594SS 316 Alloy Group 21/2″,
5/8″, 3/4″ DIA: ASTM A194, Grade 8M (316 SS)
5| Washer| ASTM F844; Meets ANSI/ASMEB18.22.1, Type A plain (wide)| AISI 316
SS; meets ANSI/ASMEB18.22.1, Type A plain (wide)
Material Identification Code | A36 | B7 | SS2 |
---|---|---|---|
Length Identification Code | Refer to Installation Parameter |
Section
Head of Anchor Rod
Anchor Size| Symbol| Unit| 3/8″| 1/2″| 5/8″|
3/4″
---|---|---|---|---|---|---
Nominal anchor diameter [equals rod diameter]| da| in. (mm)| 3/8 = 0.375(9.5)|
1/2 = 0.5(12.7)| 5/8 = 0.625(15.9)| 3/4 = 0.75(19.1)
Outside anchor diameter [equals drill bit diameter]| dnom = dbit| in. (mm)|
11/16 = 0.688(17.5)| 13/16 = 0.813(20.6)| 1 = 1.000(25.4)| 1-1/4 = 1.250(31.8)
Nominal demented depth [equals drill hole depth]| hnom| in. (mm)| 4-1/4 (108)|
5-3/8 (137)| 8(203)| 10-5/8 (270)
Effective demented depth [the anchor is designed for]| hef| in. (mm)|
4.0(102)| 5.0(127)| 7.5(191)| 10.0(254)
Minimum concrete member thickness| hmin| in. (mm)| 6.0(152)| 7.0(178)|
9.75(248)| 12.0(305)
Minimum edge distance| cmin| in. (mm)| 2.5(64)| 3.0(76)| 4.5(114)| 6.0(152)
Minimum spacing distance| smin| in. (mm)| 3.0(76)| 3.75(95)| 5.625(143)|
7.5(191)
Installation torque| A36| Tinst| ft.-lbf. (Nm)| 11(15)| 29(38)| 70(95)|
118(160)
B7 and SS2| 37(50)| 70(95)| 118(160)| 221(300)
Torque wrench / socket size| –| in.| 9/16| 7/8| 11/16| 1-1/4
B. Installation parameter
In case of the Preset (PS), installation, the anchor is installed first, and
then the attachment (fixture or base plate) is put in place
Preset Anchor Installation System Components
Rod Dia.| in. (mm)| 3/8″| 1/2″| 5/8″|
3/4″
---|---|---|---|---|---
Max. Fixture Thickness| 0.875 (22)| 1.25 (32)|
2 (51)| 1.625 (41)| 2.375 (60)| 2.0 (51)|
4.0 (102)
Steel Grade| PS A36| 3/8 X 6| 1/2 X 7-1/2| 1/2 X 8-1/4| 5/8 X 10-3/4| 5/8 X
11-1/2| 3/4 X 14| 3/4 X 16
DFM1311050| DFM1311100| DFM1311150| DFM1311200| DFM1311250| DFM1311300|
DFM1311350
PS B7| 3/8 X 6| 1/2 X 7-1/2| 1/2 X 8-1/4| 5/8 X 10-3/4| 5/8 X 11-1/2| 3/4 X
14| 3/4 X 16
DFM1371050| DFM1371100| DFM1371150| DFM1371200| DFM1371250| DFM1371300|
DFM1371350
PS SS2| 3/8 X 6| 1/2 X 7-1/2| 1/2 X 8-1/4| 5/8 X 10-3/4| 5/8 X 11-1/2| 3/4 X
14| 3/4 X 16
DFM1361050| DFM1361100| DFM1361150| DFM1361200| DFM1361250| DFM1361300|
DFM1361350
In case of the Thrubolt (TB) installation, the anchor is installed through the
attachment (fixture or baseplate).
Thrubolt Anchor Installation System Components
Rod Dia.| in. (mm)| 3/8″| 1/2″| 5/8″|
3/4″
---|---|---|---|---|---
Max. Fixture Thickness| 0.875 (22)| 1.25 (32)|
2 (51)| 1.625 (41)| 2.375 (60)| 2.0 (51)|
4.0 (102)
Steel Grade| TB A36| 3/8 X 6| 1/2 X 7-1/2| 1/2 X 8-1/4| 5/8 X 10-3/4| 5/8 X
11-1/2| 3/4 X 14| 3/4 X 16
DFM1311550| DFM1311600| DFM1311650| DFM1311700| DFM1311750| DFM1311800|
DFM1311850
TB B7| 3/8 X 6| 1/2 X 7-1/2| 1/2 X 8-1/4| 5/8 X 10-3/4| 5/8 X 11-1/2| 3/4 X
14| 3/4 X 16
DFM1371550| DFM1371600| DFM1371650| DFM1371700| DFM1371750| DFM1371800|
DFM1371850
TB SS2| 3/8 X 6| 1/2 X 7-1/2| 1/2 X 8-1/4| 5/8 X 10-3/4| 5/8 X 11-1/2| 3/4 X
14| 3/4 X 16
DFM1361550| DFM1361600| DFM1361650| DFM1361700| DFM1361750| DFM1361800|
DFM1361850
INSTALLATION
A. Power Tools Vacuums
DCV585
DWV010
DWV012 or DWV015
SDS+ Hammers
DCH416 Cordless / Battery / DC Tool
D25416 Corded / AC tool
SDSMAX Hammers
DCH614 Cordless / Battery / DC Tool
D25614 Corded / AC tool
Anchor Size| Hole Diameter| Hole Depth|
Hammer| Vacuum| Primary Bit| Undercut Bit|
Setting Tool
---|---|---|---|---|---|---|---
Version| HSDB| HDB| Conventional| HUCB| UCB|
Manual| Power
3/8″| 11/16″| 4-1/4″| SDS+DCH416or D25416| DWV010or DWV012or DCV585| Preset|
DFX11380| DWA54116| DW58081| DFX21380| DFX213811| DFX313805| DFX313825
Thrubolt| –
1/2″| 13/16″| 5-3/8″| SDS+DCH416or D25416| Preset| DFX11120| DWA54316|
DW58141| DFX21120| DFX211211| DFX311210| DFX311230
Thrubolt| –
5/8″| 1″| 8″| SDSMAXDCH614or D25614| Preset| DFX11580| DWA58001| DW58521|
DFX215802| DFX215811,2| DFX315815| DFX315835
Thrubolt| –
3/4″| 1-1/4″| 10-5/8″| SDSMAXDCH614or D25614| Preset| DFX11340| DWA58115|
DW58551| DFX21340| DFX213411| DFX313420| DFX313440
Thrubolt
|
–
DWH050K 1
The hood allows dust free drilling if conventional primary bits or UCB are
used; use of hollow bits is suggested
DW5891 2
SDSMAX to SDS+ adapter, allowing to use a SDSMAX hammer for a bit with a SDS+
shank; alternatively, use a SDS+ hammer tool
B. Installation instructions
GENERAL / GETTING PREPARED
**Power Tool: Hammer and Vacuum
** Connect the bit to the proper hammer and, in case of a hollow bit, to the proper vacuum using the DEWALT AirLock™ connector system.
**Hollow Bits
** Make sure that air flows freely, clean if required.
**Undercut Bits
** Make sure the cutter blades slides easily over the bow jaw and the gap can be fully closed.
PRIMARY HOLE DRILLING
HOLLOW BITS
Preset Installation
1a. Before drilling, ensure hollow drill bit holes are not clogged.
Using a HSDB of proper size, drill a hole into the base material to the
required depth, i.e. until the collar of the bit touches the concrete surface.
Continue with Step 3.
Thrubolt Installation
1b. Before drilling, ensure hollow drill bit holes are not clogged.
Using a HDB of proper size drill a hole into the base material to the required
depth. For this, mark the depth on the bit shank taking the fixture thickness
into account. Continue with Step 3.
CONVENTIONAL BITS
Preset Installation
-
c. Using the proper drill bit size, drill a hole into the base material to the required depth. The tolerances of the drill bit used should meet the requirements of ANSI Standard B 212.15. Mark the depth on the bit. Continue with Step 2.
-
Remove dust and debris from the hole following drilling (e.g. suction, forced air). Continue with Step 3.
Thru bolt Installation
-
c. Using the proper drill bit size, drill a hole into the base material to the required depth. The tolerances of the drill bit used should meet the requirements of ANSI Standard B212.15. Mark the depth on the bit taking the fixture thickness into account. Continue with Step 2.
-
Remove dust and debris from the hole following drilling (e.g. suction, forced air). Continue with Step 3.
UNDERCUTTING
HOLLOW BITS
Preset Installation
3a. Insert a HUCB of proper size until it hits the bottom of the hole.
Start the hammer at low speed and undercut. Undercutting is complete when the
stopper sleeve is fully compressed, i.e. the gap is closed. Continue with Step
5.
Thrubolt Installation
3b. Insert a HUCB of proper size until it hits the bottom of the hole.
Start the hammer at low speed and undercut. Undercutting is complete when the
stopper sleeve is fully compressed, i.e. the gap is closed. Continue with Step
5.
CONVENTIONAL BITS
Preset Installation
3c. Insert a UCB of proper size until it hits the bottom of the hole.
Start the hammer at low speed and undercut. Undercutting is complete when the
stopper sleeve is fully compressed, i.e. the gap is closed. Continue with Step
5.
4. Remove dust and debris from the hole following drilling (e.g. suction,
forced air).
Thrubolt Installation
3c. Insert a UCB of proper size until it hits the bottom of the hole.
Start the hammer at low speed and undercut. Undercutting is complete when the
stopper sleeve is fully compressed, i.e. the gap is closed. Continue with Step
5.
4. Remove dust and debris from the hole following drilling (e.g. suction,
forced air).
ANCHOR SETTING
Preset Installation
Insert the anchor into hole. Place setting sleeve over anchor and drive the
sleeve over the cone. For this, use either a setting tool for manual
installation or a setting tool for power tool installation. Take care that the
thread does not get damaged during installation
Verify that the red setting mark is visible on the the add rod at or above the
sleeve.
Apply proper torque; Do not exceed maximum torque.
Thrubolt Installation
Insert the anchor into hole. Place setting sleeve over anchor and drive the
sleeve over the cone. For this, use either a setting tool for manual
installation or a setting tool for power tool installation. Take care that the
thread does not get damaged during installation.
Verify that the red setting mark is visible on the headed rod at or above the
sleeve.
Apply proper torque; Do not exceed maximum torque.
REPLACING WEAR PARTS
A. Bow jaw
B. Cutter blade
C. Instructions
The cutter blade wears and has to be replaced, depending on the condition of
the concrete. Also the bow jaw experience wear at its head over time and needs
to be replaced occasionally. The following procedure explains how the cutter
blade and the bow jaw, if required, can be changed.
Anchors | Bow Jaw | Cutter Blade |
---|---|---|
HUCB | UCB | HUCB & UCB |
3/8″ | DFX213807 | DFX213805 |
1/2″ | DFX211212 | DFX211210 |
5/8″ | DFX215817 | DFX215815 |
3/4″ | DFX213422 | DFX213420 |
-
Press the pin on the undercutter using a screwdriver
-
Pull out the bow jaw
-
Change the cutter blade
-
Insert the bow jaw
Note: The bow jaw used for the HUCB has an air exhaust on one side. Therefore it is important to ensure that the bow jaw is oriented correctly to match the air inlet in the bit chassis! -
Align the pin and pinhole and reinsert
TROUBLE SHOOTING
A. Cleaning of primary hollow bit
Hollow bits work best in dry concrete. Take care when drilling in wet
concrete. The internal hollow channel of
smaller diameter HSDB can clog with concrete dust. It is recommended to
occasionally blow through the small hole at the rear of the bit using dry
compressed air in case of SDS+ bits. The SDSMAX bits can be cleaned from the
inlets at the front using a thin gauge wire to dislodge material build up..
B. Un-jamming of undercut bit
When the cutter blade of the UCB is stuck while undercutting and it cannot be
pulled out from the hole, use
wrenches as shown in below picture to relieve the cutter blade closed and
remove the under cutter from the hole.
After removal, re tighten the loosened screw and continue undercutting. This
feature is not available for HUCB as these do not tend to jam because of the
dust constantly removed during undercutting
FOR TECHNICAL ASSISTANCE PLEASE CONTACT:
anchors@DEWALT.com
1-800-524-3244
The information contained herein is accurate to the best of DEWALT’s knowledge
as of the date of publication and is provided for guidance and informational
purposes only. Refer to website for most up to date version of this document.
To obtain a project specific certification contact DEWALT engineering at
anchors@DEWALT.com.
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>