Current AHG Series Heavy Industrial High Bay Lighting Installation Guide

June 12, 2024
current

Current AHG Series Heavy Industrial High Bay Lighting

Product Information

Product Name Heavy Industrial High Bay Lighting (ALR2/AHG Series)
Model ALB071
Electrical Requirements The LED driver must be supplied with 120-480 VAC,

50/60 Hz per
product label and connected to an individual properly grounded
branch circuit, protected by a 15 or 20 ampere circuit
breaker.
Grounding Instructions| The grounding and bonding of the overall system shall be done
in accordance with National Electric Code (NEC) Article 600 and
local codes.

BEFORE YOU BEGIN

Read these instructions completely and carefully.

WARNING

RISK OF ELECTRIC SHOCK

  • Turn power off before inspection, installation or removal.

  • Properly ground electrical enclosure.
    RISK OF FIRE

  • Follow all NEC and local codes.

  • Use only UL or IEC approved wire for input/output connections. Minimum size 18 AWG.

This device complies with Part 15 of the FCC Rules. Operation is subject to the following two conditions:

  1. This device may not cause harmful interference,
  2. This device must accept any interference received, including interference that may cause undesired operation. CAN ICES-005 (A) / NMB-005 (A)

Note: This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference when the equipment is operated in a commercial environment. This equipment generates, uses, and can radiate radio frequency energy and, if not installed and used in accordance with the instruction manual, may cause harmful interference to radio communications. Operation of this equipment in a residential area is likely to cause harmful interference in which case the user will be required to correct the interference at his own expense.

Save These Instructions
Use only in the manner intended by the manufacturer. If you have any questions, contact the manufacturer.

Prepare Electrical Wiring

Electrical Requirements
The LED driver must be supplied with 120-480 VAC, 50/60 Hz per product label and connected to an individual properly grounded branch circuit, protected by a 15 or 20 ampere circuit breaker.

Grounding Instructions
The grounding and bonding of the overall system shall be done in accordance with National Electric Code (NEC) Article 600 and local codes.

Features

  • 5 year warranty
  • Wet location rated

Installation

Current-AHG-Series-Heavy-Industrial-High-Bay-Lighting-
FIG-1

  1. Turn off power to the fixture and make the appropriate wiring connections.Current-AHG-Series-Heavy-Industrial-High-Bay-Lighting-FIG-2
  2. Connect a rigid conduit or flexible conduit or strain relief and feed the AC line wire through the fitting.

Mounting Instructions

Standard Mount

Current-AHG-Series-Heavy-Industrial-High-Bay-Lighting-
FIG-3

Mount the wrap-around brackets on the ceiling or support rail using appropriate hardware. After brackets are secured in place, install one side of the housing in the bracket, then rotate up and snap the other side of the housing into bracket. Chain and “S” hook (not included) can also be used to support the brackets.

Cable Mount

Current-AHG-Series-Heavy-Industrial-High-Bay-Lighting-
FIG-4

Snap the cable attachment bracket to the standard wrap-around brackets. Use appropriate cables to hang the fixture.

3/8-inch Rod Mount

Current-AHG-Series-Heavy-Industrial-High-Bay-Lighting-
FIG-5

Mount the wrap-around brackets on the housing and then attach to the 3/8 inch rods using appropriate hardware.

45 Degree Wall Mount

Current-AHG-Series-Heavy-Industrial-High-Bay-Lighting-
FIG-6

Mount the wrap-around brackets on the wall or support rail using appropriate hardware. After brackets are secured in place, install one side of the housing in the bracket, then rotate up and snap the other side of the housing into the bracket.

Troubleshooting

Symptom/Solution

  • Luminaire will not turn on
    • Check that the color of the supply side wires match the color of the wires they are connected to.
    • Check that all wire connectors are properly connected.
    • Verify that your input voltage is within specs.
    • If using any additional controls (i.e. wireless controls or motion sensors), please also verify that those are working properly and that the unit is setup to interface with the controllers.

LED.com
© 2023 Current Lighting Solutions, LLC. All rights reserved. Information and specifications subject to change without notice. All values are design or typical values when measured under laboratory conditions.

Page 4 of 4 (Rev 04/18/23)
ALB071-ALR2-AHG_Install_R02

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

current User Manuals

Related Manuals