The product is a portable load bank with a case, specifically designed for load testing and verification of power sources or generators. It is referred to as “Model 2500” in the general reference outline drawing. The load bank offers load steps and voltage selection options, allowing users to simulate different load conditions.

Key Features

  • Load Steps: The load bank provides load steps of 12.5 kW and 25 kW.
  • Voltage Selection: The voltage can be set to either 480V or 240V/208V.
  • Fuse: There is an option to turn off the fuse.
  • Control Power: The control power can be turned on or off.
  • Protective Plug: A protective plug must be installed in Phase C when operating in single phase.

Warnings

  • Load Cables: Before connecting the load bank to a generator or power source, ensure that the load cables are installed and locked in place.
  • Protective Plug: When operating in single phase, it is essential to install the protective plug in Phase C.

Dimensions

AVTRON 2500 Portable Load Bank fig-1

  1. WEIGHT: 78 LBS [35.5 kg)

  2. CONNECTION CABLES AND 115V POWER CABLE.
    ALL DIMENSIONS ARE APPROX. IN INCHES mm

  3. UNIT IS SUPPLIED WITH 10″ [3m) LONG LOAD CONNECTION CABLES AND 115V POWER CABLE.

AVTRON 2500 Portable Load Bank fig-2

  1. ALL DIMENSIONS ARE APPROX. IN INCHES [mm
  2. WEIGHT: APPROX (CASE) 37 LBS [17 kg).

Product Usage Instructions

  1. Ensure that the load cables are properly installed and locked in place.
  2. Set the desired load steps using the provided controls. Choose between 12.5 kW and 25 kW load steps.
  3. If needed, select the desired voltage by using the voltage selection option. You can choose between 480V and 240V/208V.
  4. If required, turn off the fuse using the provided switch.
  5. Turn on the control power if needed.
  6. If operating in single phase, make sure to install the protective plug in Phase C.
  7. Once all the necessary settings are configured, connect the load bank to the generator or power source.
  8. To turn off the load bank, follow these steps:
  9. Turn off the control power.
  10. If applicable, turn off the fuse.
  11. Disconnect the load bank from the generator or power source.