Foundations BAYECON320 Packaged Rooftop Units Installation Guide
- September 16, 2024
- Foundations
Table of Contents
Foundations BAYECON320 Packaged Rooftop Units
Product Information
Specifications:
- Product Name: Foundation Packaged Rooftop Units 3 to 5 Tons
- Model Number: BAYECON320*
- Compatible With: E/GB036-060, E/GD036-060
Product Usage Instructions
Installation Instructions:
Only qualified personnel should install and service the equipment.
Installation, starting up, and servicing of heating,ventilating, and air-
conditioning equipment can be hazardous and requires specific knowledge and
training.
Important Safety Warnings:
When working on the equipment, observe all precautions in the literature and
on the tags, stickers, and labels that are attached to the equipment to avoid
death or serious injury.
Environmental Concerns:
Proper field wiring and grounding are required to avoid fire and electrocution
hazards. All field wiring must be performed by qualified personnel following
the requirements for field wiring installation and grounding as described in
NEC and local electrical codes.
Responsible Refrigerant Practices:
Technicians must wear proper Personal Protective Equipment (PPE) to protect
themselves from potential hazards. Follow precautions in the manual and on the
tags, stickers, and labels.
R-454B Flammable A2L Refrigerant:
Use ONLY R-454B rated service equipment and components. Contact your local
representative for specific handling concerns with R-454B refrigerant.
Copyright:
This document and the information in it are the property of Trane. Any
reproduction without written permission is prohibited.
FAQ:
Q: Who should install and service the equipment?
A: Only qualified personnel should install and service the equipment due
to the potential hazards involved.
Q: What should technicians do to protect themselves?
A: Technicians must wear proper Personal Protective Equipment (PPE) for
the job being undertaken to prevent potential hazards.
SAFETY WARNING
Only qualified personnel should install and service the equipment. The installation, starting up, and servicing of heating, ventilating, and air- conditioning equipment can be hazardous and requires specific knowledge and training. Improperly installed, adjusted or altered equipment by an unqualified person could result in death or serious injury. When working on the equipment, observe all precautions in the literature and on the tags, stickers, and labels that are attached to the equipment.
Introduction
Read this manual thoroughly before operating or servicing this unit.
Warnings, Cautions, and Notices
Safety advisories appear throughout this manual as required. Your personal
safety and the proper operation of this machine depend upon the strict
observance of these precautions.
The three types of advisories are defined as follows:
WARNING Indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury.
CAUTIONs Indicates a potentially hazardous situation which, if not avoided, could result in minor or moderate injury. It could also be used to alert against unsafe practices.
NOTICE Indicates a situation that could resu lt in equipment or property- damage only accidents.
Important Environmental Concerns
Scientific research has shown that certain man-made chemicals can affect the
earth’s naturally occurring stratospheric ozone layer when released to the
atmosphere. In particular, several of the identified chemicals that may affect
the ozone layer are refrigerants that contain Chlorine, Fluorine and Carbon
(CFCs) and those containing Hydrogen, Chlorine, Fluorine and Carbon (HCFCs).
Not all refrigerants containing these compounds have the same potential impact
to the environment. Trane advocates the responsible handling of all
refrigerants.
Important Responsible Refrigerant
Practices
Trane believes that responsible refrigerant practices are important to the
environment, our customers, and the air conditioning industry. All technicians
who handle refrigerants must be certified according to local rules. For the
USA, the Federal Clean Air Act (Section 608) sets forth the requirements for
handling, reclaiming, recovering and recycling of certain refrigerants and the
equipment that is used in these service procedures. In addition, some states
or municipalities may have additional requirements that must also be adhered
to for responsible management of refrigerants. Know the applicable laws and
follow them.
WARNING
Proper Field Wiring and Grounding Required!
Failure to follow code could result in death or serious injury. All field wiring MUST be performed by qualified personnel. Improperly installed and grounded field wiring poses FIRE and ELECTROCUTION hazards. To avoid these hazards, you MUST follow requirements for field wiring installation and grounding as described in NEC and your local/state/national electrical codes.
Personal Protective Equipment (PPE) Required!
Failure to wear proper PPE for the job being undertaken could result in death
or serious injury. Technicians, in order to protect themselves from potential
electrical, mechanical, and chemical hazards, MUST follow precautions in this
manual and on the tags, stickers, and labels, as well as the instructions
below:
- Before installing/servicing this unit, technicians MUST put on all PPE required for the work being undertaken (Examples; cut resistant gloves/sleeves, butyl gloves, safety glasses, hard hat/bump cap, fall protection, electrical PPE and arc flash clothing). ALWAYS refer to appropriate Safety Data Sheets (SDS) and OSHA guidelines for proper PPE.
- When working with or around hazardous chemicals, ALWAYS refer to the appropriate SDS and OSHA/GHS (Global Harmonized System of Classification and Labeling of Chemicals) guidelines for information on allowable personal exposure levels, proper respiratory protection and handling instructions.
- If there is a risk of energized electrical contact, arc, or flash, technicians MUST put on all PPE in accordance with OSHA, NFPA 70E, or other country-specific requirements for arc flash protection, PRIOR to servicing the unit. NEVER PERFORM ANY SWITCHING, DISCONNECTING, OR VOLTAGE TESTING WITHOUT PROPER ELECTRICAL PPE AND ARC FLASH CLOTHING. ENSURE ELECTRICAL METERS AND EQUIPMENT ARE PROPERLY RATED FOR INTENDED VOLTAGE.
Follow EHS Policies!
Failure to follow instructions below could result in death or serious injury.
- All Trane personnel must follow the company’s Environmental, Health and Safety (EHS) policies when performing work such as hot work, electrical, fall protection, lockout/tagout, refrigerant handling, etc. Where local regulations are more stringent than these policies, those regulations supersede these policies.
- Non-Trane personnel should always follow local regulations.
R-454B Flammable A2L Refrigerant!
Failure to use proper equipment or components as described below could result
in equipment failure, and possibly fire, which could result in death, serious
injury, or equipment damage.
The equipment described in this manual uses R-454B refrigerant which is
flammable (A2L). Use ONLY R-454B rated service equipment and components. For
specific handling concerns with R-454B, contact your local representative.
Copyright
This document and the information in it are the property of Trane, and may not
be used or reproduced in whole or in part without written permission. Trane
reserves the right to revise this publication at any time, and to make changes
to its content without obligation to notify any person of such revision or
change.
Trademarks
All trademarks referenced in this document are the trademarks of their
respective owners.
General Information
Inspection
- Check carefully for shipping damage. If any damage is found, report it immediately, and file a claim against the transportation company. Replace damaged parts with authorized parts only.
- Compare the order number on the shipping label with the accessory identification information on the ordering and shipping documents to verify that the correct accessory has been received.
Parts List
Each economizer ships partially assembled. The steps for installation are illustrated throughout this guide. Refer to the figures as the steps are performed. Figure 1, illustrates the major components of the economizer when shipped for field installation. Uncrate the economizer and check for the following parts.
Table 1. Economizer component parts list
Item | Description | Qty |
---|---|---|
1 | Rain block-off | 1 |
2 | Duct block-off | 1 |
3 | Horizontal return air bracket | 1 |
4 | Horizontal return air bracket | 1 |
5 | Horizontal return air bracket | 1 |
6 | Duct block-off | 1 |
7 | Duct block-off | 1 |
8 | Horizontal linkage rod assembly secured in plastic damper(a) | 1 |
9 | Plastic bag of miscellaneous parts: | 1 |
--- | --- | --- |
Screws | — | |
Outdoor air temperature sensor | 1 | |
Installation and operation manual | 1 | |
Rubber grommet | 1 | |
Pop-in wire ties | 1 | |
10 | 1 | |
Economizer assembly (with wire harness) | 1 |
Field supplied parts list
Tube Sealant – Trane recommends Sikaflex 221 (SEL00439)| 1
(a) For downflow installation, remove this rod from assembly and discard.
Note: Confirm there are no missing parts before starting installation.
Field Supplied Part
NOTICE
Corrosion Damage!
Failure to use recommended caulking/sealant could cause corrosion related
failures to refrigerant components.
Note: While installing and servicing economizer, avoid manual adjustments of damper blade as much as possible. Refer to Figure 2, p. 6. If only required conditions, decouple actuator and shaft connection before manual adjustments of damper blade. Confirm the coupler properly engaged after installation and service. Refer to Figure 2.
Figure 2. Economizer damper blade
Installation
Reconfigure the Damper
(Horizontal Configuration Only)
The economizer damper is shipped from the factory in downflow configuration.
Follow steps below to reconfigure it for horizontal installation.
- Remove two screws from 11. See Figure 3 .
- Remove nut and disassemble 12. See Figure 3,.
- Remove six screws from 13 (three on each side) and attach to horizontal hinge mounting brackets as shown in Figure 4.
- Connect 8. Do not allow more than 0.25 in. (6.25 mm) of rod to protrude through ball joint at 14.
- Tape areas shown in Figure 4.
Install Optional Sensors
If optional sensors for humidity and temperature monitoring will be used (BAYENTH320 and BAYENTH321), install using instructions provided in kits.
Install Duct Block-off Plate
Install duct block-off plate as shown in Figure 5, p. 7 and Figure 6.
Important: On downflow units, if power exhaust or barometric relief accessory kits are installed along with an economizer, do not install the duct block-off plate item 6 and 7 shown in Figure 5.
Economizer Installation
WARNING
Hazardous Service Procedures!
Failure to follow all precautions in this manual and on the tags, stickers,
and labels could result in death or serious injury.
Technicians, in order to protect themselves from potential electrical,
mechanical, and chemical hazards, MUST follow precautions in this manual and
on the tags, stickers, and labels, as well as the following instructions:
Unless specified otherwise, disconnect all electrical power including remote
disconnect and discharge all energy storing devices such as capacitors before
servicing. Follow proper lockout/tagout procedures to ensure the power can not
be inadvertently energized.When necessary to work with live electrical
components, have a qualified licensed electrician or other individual who has
been trained in handling live electrical components perform these tasks.
-
Remove unit end panel from the unit.
-
Apply gasket on the left hand and right hand posts as shown in Figure 8.
-
Remove approximately 3-inch of gasket material from the bottom of each corner post to expose the holes used to attach the economizer assembly to the unit. Make marks on LH and RH post engagement holes (through gasket) for shooting screws during economizer assembly onto unit.
Note: There are 12 holes on LH and RH post for installation; six large clearance holes and six small engagement holes. The following steps will describe how to use them. -
Install block-off onto unit base rail as shown in Figure 9 using four screws.
-
Install the economizer assembly onto the unit and secure it by inserting six screws (three on each side) through the clearance holes in the economizer end panel and into the engagement holes on the LH and RH post. Refer to Figure 10.
-
Install the end panel onto the economizer assembly. Use four screws at the top, six screws (three on each side) along the sides, and three screws at the bottom. Refer to Figure 11 and Figure 12.
-
Using field supplied silicone, apply sealant around economizer hood.
Install Mixed Air Sensor
- Install MAS sensor as shown in Figure 13 and connect wires 121A and 122A to it.
- Confirm wires 121A and 122A are connected to MAS terminals on RTEM. See Figure 14.
Factory Installed Economizer Setup
This section covers setup of economizer units factory-installed in the unit.
Downflow Configuration
- Remove horizontal return duct cover.
- Remove two filters inside the economizer section and set aside for later installation.
- Remove items 2, 3, 4, 5, and 8 from the economizer section as shown in Figure 15 and discard. These parts are required only for horizontal economizer configuration.
- Remove rain block-off out from inside the indoor section.
- Pull the economizer assembly out into operating position. Using the screws provided, secure each side of the economizer assembly by inserting two screws on each side through the clearance holes in the corner post and into the engagement holes in the economizer assembly.
- Install filters taken out in Step 2 in the bottom filter rack as shown in Figure 17.
- Install the block-off angle underneath the economizer. The block off angle is designed to close the opening created between the economizer and the unit base refer Figure 18.
- Using field supplied silicone, seal around the economizer hood. Refer to Figure 12.
- Reinstall horizontal return duct cover.
Horizontal Configuration
- Follow Step 1 to Step 8 from “Downflow Configuration
- Install the horizontal block-off parts 2, 3, 4, and 5 shown in Figure 6, p. 7.
- Apply gasket around block-off as shown in Figure 19
- Reconfigure the damper for horizontal operation as economizer can not be taken off from unit. See “Reconfigure the Damper (Horizontal Configuration Only),” for instructions.
- If optional sensors for humidity and temperature monitoring are to be used (BAYENTH320 and BAYENTH321), install them. Use the instructions provided in the kits.
- Remove return duct cover from the horizontal opening and install over the downflow opening.
- Using field supplied silicone apply sealant around economizer hood as shown in Figure 12.
Mist Eliminator Servicing
- Remove screws securing end panel to the unit and the economizer and set panel aside.
- Remove mist eliminator brackets.
- Remove mist eliminator and clean.
- Reinstall mist eliminator and secure with brackets.
- Reinstall end panel and secure it to the unit and the economizer using the screws removed in Step 1.
Minimum Position Setting
To adjust the minimum position setting and check out the economizer, the power
must be connected.
-
Close the unit disconnect and place the zone sensor fan selector in the fan ON position and the heat/cool selector in the OFF position. This will place the damper in the minimum ventilation position.
-
To adjust the minimum position setting for the required ventilation air, turn the potentiometer (on the ECA) clockwise to open (to increase the amount of ventilation) or counterclockwise to close (to decrease the amount of ventilation). The damper will open to this setting each time the blower circuit is energized.
Note: When adjusting minimum position, the damper may move to the new setting in several small steps. Once the damper has remained in position for 10 to 15 seconds without movement, it can be assumed it is at the new position. -
Replace the filter access panel. The damper will close when the blower circuit is de-energized.
Dry Bulb Settings
Standard economizer dry bulb changeover is field selectable to 5 outdoor
temperatures. See Table 2, p. 12 for potentiometer settings. The selection is
made on the ECA.
Reference Enthalpy Settings
Economizer enthalpy changeover is field selectable to 5 points. See Table 2,
p. 12 for potentiometer settings. The selection is made on the ECA.
Table 2. Potentiometer settings
Potentiometer Setting | Dry Bulb | Enthalpy |
---|---|---|
A | 73ºF (22.8ºC) | 27 Btu/lb (63 kJ/kg) |
B | 70ºF (21.1ºC) | 25 Btu/lb (58 kJ/kg) |
C(a) | 67ºF (19.4ºC) | 23 Btu/lb (53 kJ/kg) |
D | 63ºF (17.2ºC) | 22 Btu/lb (51 kJ/kg) |
E | 55ºF (12.8ºC) | 19 Btu/lb (44 KJ/Kg) |
(a) Factory setting.
Table 3. Economizer control options
Control Option| Enable Conditions (a)| Optional Sensors
Required (b)
---|---|---
Dry Bulb (standard)| See Table 2.| Outdoor Air Temp. (OAT)
Reference Enthalpy| See Table 2.| Outdoor Humidity (BAYENTH320*)
Comparative Enthalpy| Outdoor Air Enthalpy 3.0 BTU/lb. less than Return Air
Enthalpy| Outdoor Humidity Return Humidity Return Temperature
- Economizing is enabled when these conditions are met.
- Conditions level will be self configured when optional sensors are connected.
Trane and American Standard create comfortable, energy efficient indoor environments for commercial and residential applications. For more information, please visit trane.com or americanstandardair.com.
Trane and American Standard have a policy of continuous product and product data improvement and reserve the right to change design and specifications without notice. We are committed to using environmentally conscious print practices.
ACC-SVN208G-EN 23 Aug 2024 Supersedes ACC-SVN208F-EN (Jul 2024)
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>