  • Product Name: Modulo Group 1
  • Recommended Radius for Curving: Greater than 500mm
  • Recommended Ceiling Installation Process: Furring channel, starter bead
  • Recommended Wall Installation Process: Top hat, furring channel, battens

Product Usage Instructions

Ceiling Application
Follow these steps for ceiling installation:

  1. Install furring channel at both end positions where panels will be installed.
  2. Ensure the variation in fixing furring channel is not greater than 3mm per meter.
  3. Install remaining furring channel at a maximum of 600mm centers.
  4. Install the starter bead to the furring channel ensuring it is square.

Wall Application
Follow these steps for wall installation:

  1. Ensure the prepared wall surface is true and plumb.
  2. Fix top hat, furring channel, or battens at the top and bottom of the wall at the heights where panels are to be installed.
  3. In addition to top and bottom furring channel, install additional…

Cutting Instructions
Use a batten that slides into position along with 8G countersunk screws and polyurethane adhesive for installation.

FAQ

  • Q: Can Modulo Group 1 be installed on both internal and external curves?
    A: Yes, Modulo Group 1 can be installed on both internal and external curves when the radius is greater than 500mm.

  • Q: What is the recommended process for ceiling application?
    A: The recommended process includes installing furring channels, ensuring square installation of the starter bead, and maintaining proper spacing.

  • Q: How should I prepare the wall for installation?
    A: Ensure the wall surface is true and plumb before fixing top hat, furring channel, or battens at appropriate heights for panel installation.

Installation Guides
MODULO® Group 1

Installation guide
MODULO® Group 1

Suitable Applications for MODULO® Group 1
MODULO® Group 1 is manufactured from aluminium and is designed for both internal ceiling, curves and wall applications. It is not warranted for use in external areas.
MODULO® Group 1 is designed to be used in areas where a fire rating of Group 1 or Group 2 is required. For all other applications, our Group 3 may be a more suitable solution.

About MODULO® Group 1

  • The MODULO® Group 1 sections are designed to be screw fixed through each tongue where they intersect the furring channel or battens on the prepared ceiling.
  • MODULO® Group 1 is designed to take self drilling screws however pre-drilling may be required depending on the specific fastener.
  • For MODULO® Group 1 profile weights, please refer to the Technical data sheet available on our website when calculating load capacities found screenwood.com.au/range/modulo or contact our team for information.

Curving
Modulo Group 1 can be installed on a both internal and external curves when the radius is greater than 500mm.
For radii tighter than 500mm, we recommend clamping and creasing the profiles using the specified crease rebates on the profiles where required.

Ceiling Application

Recommended Installation Process
Follow these simple steps for ceiling installation:

  1. Install furring channel at either end position where the panels are to be installed.
    If fixing furring channel directly to the ceiling or via a suspended system, ensure the variation is no greater than 3mm per metre.

  2. Install the remaining furring channel at a maximum of 600mm centers.

  3. Install the starter bead to the furring channel ensuring it is square.

Wall Application
Recommended Installation Process
Follow these simple steps for wall installation:

  1. Ensure the prepared wall surface is true and plumb.
  2. Fix top hat, furring channel or battens at the top and bottom of the wall at the heights where the panels are to be installed.
  3. In addition to top and bottom furring channel, install additional furring channel parralel to the top and bottom channels at a maximum distance of 600mm.
  4. If installing top and bottom aluminum trims, install the bottom trim allowing for the desired shadow line spacing (if applicable).
  5. Install the starter bead to the furring channel ensuring it is plumb.
  6. At the end of the run, the last panel may need to be cut at a specific width using a panel saw or track saw with an appropriate aluminum blade and safety measures in place. Flats have been designed into the extrusion for the use of high bond tapes (such as 3M VHB 4910) & silicone adhesives.

Installation guide for MODULO® Group 3

Suitable Applications
MODULO® Group 3 is a tongue and groove lining board made from Moisture Resistant (MR) Fibreboard. It is designed for ceiling, walls, curves and joinery applications in both vertical and horizontal orientations. It is not suitable for use in wet areas or for external use. For resistance to wear and UV please see our technical data sheet.

Installation Recommendations

  • Screenwood recommends that MODULO® Group 3 should be screw fixed to timber battens or furring channel spaced at a maximum of 600mm centres (see installation diagram).

  • The M2 weights are provided in the profile specification sheets and on the website. Installers must check to make sure that the framing system or battens and the structure they are fixed to is suitable for the load of the specific MODULO® Group 3 profile.

  • An 8-gauge countersunk screw should be used for fixing, and located on the panels using the centering groove on the tongue. A polyurethane adhesive is to be applied to the batten/furring channel prior to MODULO® Group 3 being fitted.
    Although MODULO® Group 3 is manufactured from moisture resistant (MR) MDF, the end grain of MODULO® Group 3 cannot get wet. Section ends should be sealed in installations where accidental ingress of water or moisture may occur.

  • MODULO® Group 3 used for walls should be kept at least 20mm above a floor surface and care must be taken when floors are being mopped/cleaned. The warranty does not cover damage from water ingress.

  • MODULO® Group 3 may be butt jointed where required, however alignment of the adjoining panel must be perfect for a seamless joint. Butt joints should be staggered to avoid straight unsightly join lines. If a straight joint is desired, we recommend an expressed joint of 5mm.

  • Expansion joints for MODULO® Group 3 must be considered on all installations where the runs exceed 5.4m in either direction. Consideration of the suitability of MODULO® must be taken prior to purchase.

Cutting
Cutting of MODULO® Group 3 should be done by qualified trades using a drop saw or panel saw with carbide tipped blades and can be created beautifully with the use of routers, trimmers and other joinery tools typically used when fabricating MDF.

Detailing and Trims
MODULO® Group 3 can be finished in a variety of ways including return mitres, rebated corners, abs edge tapes, aluminium trims, matching timber trims or sealing ends with paint.

Curves

  • MODULO® Group 3 can accommodate curves by cutting a 3mm wide relief into the back of the panels, to a depth 1.5mm from the panel face.
  • The relief cut panels can be manipulated during installation to adhere to concave or convex surfaces, keeping within the maximum radius. Profile depth and maximum radius are provided in the individual profile detailing spec sheets.

Corners
MODULO® Group 3 can be mitred for a seamless corner finish with both vertical and horizontal applications.

Horizontal mitre

Relief cut panels

Vertical mitre

References

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

Related Manuals