DATREND Systems MN-150x Automated ESU Analyzer Instruction Manual
- June 10, 2024
- Datrend Systems
Table of Contents
vPad-ESU™
Automated ESU Analyzer
App Version 5.00.X
Operating Manual
MN-150a
To order this manual, use Part Number 6100-205
Revision | Revision History Description | Date |
---|---|---|
A | Initial release | 2024-Apr-18 |
MN-150x Automated ESU Analyzer
Copyright
Datrend Systems Inc. (“DSI”) agrees to a limited copyright release that allows
you to reproduce manuals and other printed materials for use in service
training programs and other technical publications. If you would like other
reproductions or distributions, submit a written request to Datrend Systems
Inc.
Unpacking and Inspection
Follow standard receiving practices upon receipt of the instrument. Check the
shipping carton for damage. If damage is found, stop unpacking the instrument.
Notify the freight carrier and ask for an agent to be present while the
instrument is unpacked. There are no special unpacking instructions, but be
careful not to damage the instrument when unpacking it. Inspect the instrument
for physical damage such as bent or broken parts, dents, or scratches.
Claims
Our routine method of shipment is via common carrier. Upon delivery, if
physical damage is found, retain all packing materials in their original
condition and contact the carrier immediately to file a claim.
If the instrument is delivered in good physical condition but does not operate
within specifications, or if there are any other problems not caused by
shipping damage, please contact your local sales representative or DSI
immediately.
Standard Terms and Conditions
Refunds & Credits
Please note only serialized products (products labelled with a distinct serial
number) and accessories are eligible for partial refund and/or credit. Non-
serialized parts and accessory items (cables, carrying cases, auxiliary
modules, etc.) are not eligible for return or refund. In order to receive a
partial refund/credit, the product must not have been damaged, and must be
returned complete (meaning all manuals, cables, accessories, etc.) within 90
days of original purchase and in “as new” and resalable condition. The Return
Procedure must be followed.
Return Procedure
Every product returned for refund/credit must be accompanied by a Return
Material Authorization (RMA) number, obtained from Datrend Customer Service.
All items being returned must be sent prepaid (freight, duty, brokerage, and
taxes) to our factory location.
Restocking Charges
Products returned within 30 days of original purchase are subject to a minimum
restocking fee of 15%. Products returned in excess of 30 days after purchase,
but prior to 90 days, are subject to a minimum restocking fee of 20%.
Additional charges for damage and/or missing parts and accessories will be
applied to all returns. Products which are not in “as new” and resalable
condition, are not eligible for credit return and will be returned to the
customer at their expense.
Certification
This instrument was thoroughly tested and inspected and found to meet DSI’s
manufacturing specifications when it was shipped from the factory. Calibration
m easurements are traceable to the National Research Council of Canada (NRC)
and/or the National Institute of Standards and Technology (NIST). Devices for
which there are no NRC/NIST calibration standards are measured against in-
house performance standards using accepted test procedures.
Warranty
Warranty and Product Support
Datrend Systems Inc. (“DSI”) warrants the Analyzer Base Unit of vPad-ESU (the “Datrend product”) to be free from defects in materials and workmanship under normal use and service for one (1) year from the date of original purchase. This warranty will be automatically extended to two (2) years from the date of original purchase, provided that calibration is performed on an annual basis by a Datrend Authorized Service Center*. During the warranty period DSI will, at our option, either repair or replace defects in materials and workmanship at no charge; provided the Datrend product is returned (shipping, duty, brokerage and taxes prepaid) to DSI. Any and all transportation charges incurred are the responsibility of the purchaser and are not included within this warranty. This warranty extends only to the original purchaser and does not cover damage from abuse, neglect, accident or misuse or as the result of service or modification by other than DSI. IN NO EVENT SHALL DATREND SYSTEMS INC. BE LIABLE FOR CONSEQUENTIAL DAMAGES.
This warranty is subject to the following limitations:
- Tablet PC: per tablet manufacturer’s original warranty
- Standard Accessories: 90 day limited warranty
- Damage to instrument due to activation of an electrosurgical generator connected to FOOTSW ITCH; REM; ACTIVE; DISPERSIVE; MA; and/or HF LEAKAGE terminals is not covered under the warranty
- Damage to tablet PC due to contact with an activated electrosurgical generator is not covered under warranty
- Re-calibration of the instrument, which has a recommended annual calibration frequency, is not covered under the warranty.
No warranty shall apply when damage is caused by any of the following:
- Power failure, surges, or spikes,
- Damage in transit or when moving the instrument,
- Improper power supply such as low voltage, incorrect voltage, defective wiring or inadequate fuses,
- Accident, alteration, abuse or misuse of the instrument,
- Fire, water damage, theft, war, riot, hostility, acts of God, such as hurricanes, floods, etc.
Only serialized products (those items bearing a distinct serial number tag)
and their accessory items are covered under this warranty. PHYSICAL DAMAGE
CAUSED BY MISUSE OR PHYSICAL ABUSE IS NOT COVERED UNDER THE W ARRANTY. Items
such as cables and non-serialized modules are not covered under this warranty.
This warranty gives you specific legal rights and you may have other rights,
which vary from province to province, state to state, or country to country.
This warranty is limited to repairing the instrument to DSI’s specifications.
W hen you return an instrument to DSI for service, repair or calibration, we
recommend shipment using the original shipping foam and container. If the
original packing materials are not available, we recommend the following guide
for repackaging:
- Use a double-walled carton of sufficient strength for the weight being shipped.
- Use heavy paper or cardboard to protect all instrument surfaces. Use non-abrasive material around all projecting parts.
- Use at least four inches of tightly packed, industrial-approved, shock-absorbent material all around the instrument.
DSI will not be responsible for lost shipments or instruments received in damaged condition due to improper packaging or handling. All warranty claim shipments must be made on a prepaid basis (freight, duty, brokerage, and taxes). No returns will be accepted without a Return Materials Authorization (“RMA”) number. Please contact Datrend (refer toChapter 5 of this manual) to obtain an RMA number and receive help with shipping/customs documentation.
- Subject to some exclusions, based on sales territory. Contact Datrend for details.
Warranty Disclaimer
Should you elect to have your instrument serviced and/or calibrated by someone other than Datrend Systems or an Authorized Service Centre, please be advised that the original warranty covering your product becomes void when the tamper- resistant Quality Seal is removed or broken without proper factory authorization. W e strongly recommend, therefore, that you send your instrument to Datrend Systems or an Authorized Service Centre for service and calibration, especially during the original warranty period.
In all cases, breaking the tamper-resistant Quality Seal should be avoided at all cost, as this seal is the key to your original instrument warranty. In the event that the seal must be broken to gain internal access to the instrument (e.g., in the case of a customer-installed firmware upgrade), you must first contact Datrend Systems at 1-604-291-7747. You will be required to provide us with the serial number for your instrument as well as a valid reason for breaking the Quality Seal. You should break this seal only after you have received factory authorization. Do not break the Quality Seal before you have contacted us! Following these steps will help ensure that you will retain the original warranty on your instrument without interruption.
WARNING
Unauthorized user modifications or application beyond the published specifications may result in electrical shock hazards or improper operation. Datrend Systems will not be responsible for any injuries sustained due to unauthorized equipment modifications.
DSI DISCLAIM S ALL OTHER WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING ANY WARRANTY OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE OR APPLICATION.
THIS PRODUCT CONTAINS NO USER-SERVICEABLE COMPONENTS.
UNAUTHORIZED REMOVAL OF THE INSTRUMENT COVER SHALL VOID THIS AND ALL OTHER EXPRESSED OR IMPLIED WARRANTIES.
Note: Calibration of Datrend products typically involves adjustment of parameters stored in firmware by proprietary software. Parties other than Datrend and its Authorized Service Centers are limited to verification of the status of the accuracy of the instrument. Do not confuse verification with calibration.
vPad™, vPad-ESU™, vPad-ES™, vPad-353™, vPad-AS™, vPad-A3™, vPad Record Manager™, vPad-RM™, vPad-EQM™, vPad-mT™, vPad-Check™, vPad-Cal™, vPad-XPORT™, vPad-AIMS™, Datrend Docs™ and CMX™ are trademarks of Datrend Systems Inc.
Android™ is trademark of Google Inc.
Valleylab™, Force FX™, Force EZ™ and ForceTriad™ are trademarks of Medtronic – Covidien Ltd.
System 5000™ is a trademark of CONMED Corporation
Abbreviations and Definitions
The following abbreviations, terms and acronyms are used throughout this manual:
A | Ampere |
---|---|
AAMI | American Association of Medical Instrumentation |
App | Application software that causes a computer to perform tasks for computer |
users.
CQM| Contact Quality Monitor. A monitoring system in an ESU which continuously
tests for reliable and safe contact between a monopolar
return electrode and the patient. A CQM system measures the impedance across a
split or dual-pad return electrode and will alarm
and disable the generator in case of fault.
DSP| Digital Signal Processor. A specialized microprocessor with architecture
optimized for the operational needs of digital signal processing, for example,
filtering or analyzing electrical signals represented as sampled data.
DUT| Device Under Test. The electrosurgical generator being tested.
Earth| See GND
ESU| Electrosurgical Unit. A high-frequency (HF) electrical generator used to
cut or coagulate tissue in surgical procedures.
ESU Standard| A standard established by a national or international agency
which specifies safety and performance requirements for high- frequency
medical equipment such as ESUs. Recognized Standards
Organizations include: AAMI – Association for Advancement of Medical
Instrumentation
IEC – International Electrotechnical Commission
GND or Ground| The line (conductor) connected to a place that is maintained at
“Ground” or “Earth” voltage. Same as Protective Earth.
HF| High Frequency; according to the ITU definition, a portion of the radio
frequency spectrum occupying 3 to 30 Megahertz (MHz). W hen referring to ESUs
or electrosurgical generators, “HF” implies a frequency of operation somewhat
below the ITU HF band, typically in the range of 0.2 to 2 MHz depending on
generator make and model.
Hz| Hertz
IEC| International Electrotechnical Commission
IME| Android input method (e.g. keyboard)
kHz| kilohertz
Measurement Category (CAT)| A method of classifying electrical connections
used in measurement and testing, taking into account the total continuous
energy available in the circuit. Categories range from CAT I (not for direct
connection to AC mains) through CAT IV (continuous energy may exceed 110 kVA).
MHz| Megahertz
PE| Protective Earth. The line (conductor) connected to a place that is
maintained at “Ground” or “Earth” voltage.
REM| Return Electrode Monitor. A monitoring system in an ESU which
continuously tests for reliable and safe contact between a monopolar return
electrode and the patient. A REM system measures the impedance across a split
or dual-pad return electrode and will alarm and disable the generator in case
of fault.
RMS| Root-Mean-Square measurement of a parameter (eg. Vrms , A rms….)
V| Volt
Vrms| Volts rms
W| W att
Symbol Definitions
The following symbols may be found on vPad-ESU:
CONSULT MANUAL FOR PROPER OPERATION
The operating manual provides valuable information on the proper use of vPad-
ESU. It is highly recommended the operator read the instructions thoroughly
before operating the device. It is possible to damage the Equipment Under Test
(EUT) and/or cause harm to the operator if vPad-ESU is used incorrectly.
****10KV MAX
This warning label appears between ACTIVE and DISPERSIVE terminals of the
variable resistive load. The maximum peak instantaneous voltage which may be
applied between ACTIVE and DISPERSIVE terminals is 10,000V when the load is
set for maximum resistance, or 5115 ohms. As the load is reduced from 5115 to
3000 ohms, the maximum input must be reduced in proportion, for example, at
3000 ohms the input voltage must not exceed 6000V. For loads less than 3000
ohms, refer to voltage ratings specified in the table below.
Load | Maximum peak input |
---|---|
700 – 2995 ohms | 5000V |
150 – 655 ohms | 4000V |
40 – 145 ohms | 2000V |
5 – 35 ohms | 1000V |
**** REFER TO USER MANUAL FOR LOAD RATINGS
This warning label appears below and to the right of the ACTIVE and DISPERSIVE
terminals of the variable resistive load. Maximum power input to ACTIVE and
DISPERSIVE terminals depends on the resistance of the load and the duty cycle
of the input. Refer to the specifications of section 1.1.8 in this manual.
CAUTION: Electrical Shock Hazard, Refer Servicing to Qualified Personnel
CAUTION: Consult Accompanying Documents
These warnings appear on the serial number label of vPad-ESU. vPad-ESU
contains hazardous electrical voltages internally which W ILL BE present when
the covers are removed. The operator should read the Operating Manual to
determine what actions to take in the event of failure of vPad-ESU. Refer to
the Troubleshooting and Maintenance Section of the Operating Manual.
WARNING: OPENING THE vPad-ESU MAY COMPROMISE USER SAFETY.
REFER SERVICING TO DATREND AUTHORIZED AGENT.
vPad-ESU is a complex instrument which contains internally distributed line
voltages. Failure to observe appropriate measures when the instrument has been
opened, or failure to reassemble correctly may compromise the safety of the
user.
WARNING: GROUNDING CIRCUIT CONTINUITY IS VITAL FOR SAFE OPERATION. NEVER
OPERATE THE vPad-ESU W ITH GROUNDING CONDUCTOR DISCONNECTED.
Proper grounding is essential to ensure operator safety. Do not bypass the
grounding provisions inherent in the design of vPad-ESU, otherwise, the
operator may be subjected to an electrical shock risk.
WARNING: HAZARDOUS VOLTAGES OR CONDITIONS MAY EXIST DURING TESTS. CONSULT
THE ACCOMPANYING DOCUMENTS FOR APPROPRIATE PRECAUTIONS.
While testing an electrosurgical generator, high voltage may be present at the
generator’s output terminals which will thus be applied to test leads and
terminals of vPad-ESU. In particular, the user may be exposed to a potential
hazard of burns or electric shock from unterminated test leads which are
required in testing of HF leakage. Follow testing instructions in this manual
and as displayed by vPad-ESU, and exercise due care in operation of the
generator under test. Refer to accompanying documents of the electrosurgical
generator and follow all manufacturer’s instructions, cautions and warnings in
use and testing of the generator.
Specifications
Equipment Performance Specifications
1.1 Instrument Specifications
1.1.1 Power Measurement
Range…………………………………………….. 0 – 999.9 W (derived from current)
Accuracy ………………………………………. ±(3 % of reading + 0.5W)
1.1.2 RMS Current Measurement
Range…………………………………………….. 0 to 5000 mA (internal load bank) 0 to 8500 mA
(externally-connected load)
Accuracy ………………………………………. ±(1 % of reading + 5 mA)
1.1.3 RMS Voltage Measurement
Range……………………………………………. 0 – 999.9 V (derived from current)
Accuracy ……………………………………… ±(1 % of reading + 1V)
1.1.4 Peak Voltage Measurement
Range……………………………………………. 0 – 9999 V
Accuracy ……………………………………… ±(1 % of reading + 10V)
1.1.5 Crest Factor Measurement
Range……………………………………………. 1.0 – 999.9
Method…………………………………………. Peak/RMS ratio, calculated using the larger of +/-
peak values
1.1.6 Instrument Bandwidth (-3dB)
250 Hz – 12 MHz
1.1.7 Isolation, Earth to Measuring Device
10 kV
1.1.8 Variable Load
Range…………………………………………….. 0 – 5115 ohms
Resolution……………………………………… 5 ohms
Accuracy ……………………………………….. ±1 % +0.5, -0 ohms
Power, 50% duty cycle…………………… 200W @ 5 ohms
(20 sec on; 20 sec off)
400W @ 10 ohms
600W @ 20 ohms
600W @ 40 ohms
600W @ 80 ohms
600W @ 160 ohms
600W @ 320 ohms
600W @ 640 ohms
530W @ 1280 ohms
260W @ 2560 ohms
1.1.9 RF Leakage Loads
Resistance……………………………………. 2 x 200 ohms
Accuracy …………………………………….. ±1 %
Power, 100% duty cycle………………. 16W
1.1.10 REM/CQM Test Resistance
Range………………………………………….. 0 – 1023 ohms
Resolution…………………………………… 1 ohm
Accuracy …………………………………….. ±1 % +1, -0 ohms
1.1.11 Footswitch Control
Outputs………………………………………. CUT, COAG and BIPOLAR
Contacts……………………………………… N.O. SPST, 125VAC 0.5A
1.1.12 Operational Duty Cycle
Up to 100% in manually activated tests, 50% in automated footswitch
activation, from 1 to 20 seconds
1.1.13 HF Digital Oscilloscope
Vertical ranges…………………………….. 0.125, 0.25, 0.75, 1.5, or 3A / division
Vertical range relection……………….. Manual or Automatic
Horizontal ranges……………………….. 1.25, 2.5, 5, 10, 20 or 40 ìsec / division
Trigger level………………………………… Adjustable, +/- edge
1.1.14 HF Spectrum Analyzer
Vertical ranges……………………………. Normalized dB or linear
Horizontal ranges……………………….. 62.5, 125, 250, 500, 1000, 2000 kHz / division
Frequency resolution…………………… 1.22, 2.44, 4.88, 9.77, 19.5, 39.1 kHz
1.1.15 Current Monitor Output
Sensitivity…………………………………….. 0.1V/A into 1 Megohm
Bandwidth (-3dB)………………………… 250 Hz – 12 MHz
Accuracy………………………………………. ±2%
1.2 Measurement Terminals
All measurement terminals are rated Measurement Category I (CAT I): not
suitable for direct connection to AC mains supply
1.2.1 ACTIVE and DISPERSIVE
Maximum Voltage………………………… Flashover voltage depends on load resistance
setting, as follows:
10 kV peak instantaneous at 5115 ohm
5 kV for loads of 700 to 2995 ohms
4 kV for loads of 150 to 655 ohms
2 kV for loads of 40 to 145 ohms
1 kV for loads of 5 to 35 ohms
Maximum Current……………………….. 5 A RMS
1.2.2 mA
Maximum Voltage……………………….. N/A (terminals short-circuited)
Maximum Current……………………….. 8.5 A RMS
1.2.3 HF LEAKAGE
Maximum Voltage……………………….. 56 V RMS
Maximum Current……………………….. 0.28 A RMS
1.2.4 REM (CQM)
Maximum Voltage……………………….. 16 V
Maximum Current……………………….. 0.03 A
1.2.5 FOOTSWITCH OUTPUT
Maximum Voltage……………………….. 125 VAC
Maximum Current……………………….. 0.5 A
Connect measurement terminals ONLY as instructed in this manual. See Chapter
4, Operation
1.3 User Interface
Display …………………………………………………… 10.1″ colour LCD (minimum 1280 x 800 resolution)
User Controls …………………………………………. Capacitive touchscreen
Wired Connectivity …………………………………. μUSB 2.0 Device (shared with base unit)
μ USB 2.0 Host
XBUS Interface (RJ11-6)
Wireless Connectivity …………………………….. 802.11 b/g/n
Bluetooth 2.1+ EDR
Memory, Internal …………………………………….. 16GB Maximum†
Memory, Expansion ………………………………… 16GB to 32GB Micro SD Card (optional)
Modes of Operation ………………………………… Manual (standard)
Automatic (accessory option)
† 16 GB is the maximum amount of internal memory installed in the tablet. The
internal memory is formatted similar to a hard disk to facilitate storage and
access to data including the Operating System, Programs, and Data. The
formatting process reduces that amount of storage available for use by the
tablet. Additionally, the Operating System can consume up to 4 GB of storage.
The nominal internal storage available for users is approximately 12 GB as
shipped from Datrend.
If additional storage is required, an SD card can be installed in the tablet.
Upon initial installation of an SD card, check for proper operation and that
the correct size is reported. It may be necessary to format your SD card. If
so, ensure that the card is formatted for the FAT32 file system, and that the
long format mode is used (do NOT use “quick format”).
Equipment Technical Specification s
1.4 Electrical Ratings
120 Volt power outlet ……………………………… 90 to 132 V ac rms, 47 to 63 Hz, 0.6 A max.
230 Volt power outlet ……………………………… 180 to 264 V ac rms, 47 to 63 Hz, 0.4 A
max.
1.5 Fuses
Internal, not replaceable by user
1.6 Environment for Use
15 to 40 EC
10% to 90% RH
Altitude: 2000m max.
Indoor use only
Pollution Degree 2
1.7 Dimensions
Base unit ………………………………………………… 8.5 x 11 x 13 in. (22 x 28 x 33 cm)
Tablet PC (detachable) …………………………… 10.5 x 6.7 x 0.5 in. (27 x 17 x 1.3 cm)
1.8 Weight
18 lb (8.2 kg)
1.9 Standard Accessories
Power Cord (country specific)
North America………………………………………….. P/N 3000-471
Continental Europe…………………………………… P/N 3000-006
United Kingdom……………………………………….. P/N 3000-004
Australia…………………………………………………….. P/N 3000-005
Shorting Jumper (3 supplied)………………………………. P/N 3220-600
ESU REM Test Cable, with pin…………………………….. P/N 7200-570
Dispersive HF Test Lead, 30″, without pin…………. P/N 7200-572
Test lead, 30″, Red, with 2 retractable sleeves………. P/N 7200-574
Test lead, 30″, Black, with 2 retractable sleeves……. P/N 7200-575
HF Leakage Jumper……………………………………………….. P/N 7200-582
Kit, Banana Test Lead (green) w. Crocodile Clip….. P/N 7500-430
1.10 Optional Accessories
For a complete list of available accessories, visit
www.datrend.com or contact Datrend Customer Service
(see Chapter 5 for contact details)
1.11 Compliance With Standards
vPad-ESU is in compliance with these safety standards:
CAN/CSA-C22.2 No. 61010-1-(2 Edition) – Safety Requirements for Electrical
Equipment for 2nd Measurement, Control, and Laboratory Use, Part 1: General
Requirements UL Std. No. 61010-1 (2 Edition) – Safety Requirements for
Electrical Equipment for 2nd Measurement, Control, and Laboratory Use – Part
1: General Requirements Following manufacture, all units are subjected to, and
have passed the requirements of the ‘Routine Tests’ defined in Annex F of the
above Standard(s).
Overview
vPad-ESU is a test instrument intended for measuring the output of
electrosurgical generators, also known as electrosurgical units or “ESU’s”.
Tests performed by vPad-ESU are based on measurement of high-frequency current
delivered by the ESU to a preset load resistance.
vPad-ESU comprises an RF Analyzer unit (right), and an Android tablet which
provides a user interface by means of the vPad-ESU™ software or “app”
installed on the tablet.
2.1 RF Analyzer
The RF Analyzer unit incorporates a high-powered load which is comprised of
banks of ceramic power resistors. High-voltage RF relays are used to switch
the resistor banks in and out, allowing the load to be varied from zero to
5115 ohms in 5 ohm steps. Two 90mm fans provide forced-air cooling of the
load, enabling it to withstand inputs of 400W at 100% duty cycle for standard
test loads of 100, 300 or 500 ohms. In addition to the variable test load, the
RF Analyzer provides two low-powered, fixed loads which are used in measuring
high-frequency leakage from the ESU under test. A variable resistance which
can be set from zero to 1023 ohms in one-ohm steps is used in testing the
Return Electrode Monitor (REM) or Contact Quality Monitor (CQM) of the ESU. A
footswitch control output provides relay contacts to independently activate
“cut”, “coag” and “bipolar” control inputs of the ESU, enabling various tests
to be performed automatically under the control of the Android tablet.
In HF testing, a toroidal current transformer in the RF Analyzer senses high-
frequency current in the load and produces a proportional signal which is
conveyed to the Analyzer electronics. The electronics include a digital signal
processor (DSP) which captures and analyzes the ESU signal in realtime.
Periodically, the DSP sends data to the Android tablet where measurements of
current, voltage and power are displayed by the vPad-ESU app.
2.2 vPad-ESU™ App
The vPad-ESU application software or “app” on the tablet enables biomedical
engineering technicians to perform tests of ESU power output, HF leakage and
REM/CQM alarm operation. Measurements obtained during manual testing may be
saved ad-hoc, leading to creation of a test report document which may then be
saved on the tablet. Alternatively, the vPad-ESU app provides automated
testing of ESU’s in the form of Power Curves and AutoSequences.
A Power Curve or “power distribution” is a test in which the ESU power is
measured over a range of specified loads. A power distribution may by measured
automatically, in which case the ESU under test is switched on and off by
vPad-ESU via a footswitch control cable. A power distribution can also be
measured semi-automatically, in which case the technician is prompted by vPad-
ESU to activate the ESU by means of a footpedal or handswitch. During the
test, results are tabulated and plotted on a graph of power versus resistance.
Users may configure loads used in a test and timing associated with each power
measurement. The setup for a Power Curve can also include pass/fail criteria
in the form of upper limit and lower limit curves provided by the manufacturer
or created by the user. Several examples of Power Curve setups are installed
with the vPad-ESU app.
AutoSequences are automated sequences of measurements which can be integrated
with user instructions, diagrams and an inspection checklist. vPad-ESU
AutoSequences are ideally suited to preventive maintenance (“PM”) inspection
of ESUs in accordance with manufacturer specifications. An AutoSequence can
guide a technician step-by-step through a PM inspection while automatically
recording results to obtain a PM record or test report document on completion
of the sequence. Automation of the PM procedure enables a PM to be completed
more quickly and accurately, and with less prior experience or specific
training on the part of the technician. Example AutoSequences installed with
the vPad-ESU app enable technicians to perform PM inspections of major makes
and models. vPad-ESU enables users to program their own AutoSequences to
incorporate instructions, schematics, performance and safety measurements as
specified in a manufacturer’s service manual or in a PM procedure developed by
their organization.
This manual provides instructions for setup and operation of vPad-ESU.
Additional instructions may be found in “Help” menus and schematic diagrams of
the vPad-ESU app. Further information on operation, setup and programming may
be obtained by contacting Datrend Customer Service; see Chapter 5 in this
manual for contact information.
Setup
Place the RF Analyzer unit on a strong, stable bench or table. To release the
Android tablet from the RF Analyzer, push the top edge of the tablet straight
down to compress the retaining tray which is below the tablet. Once the tablet
has cleared the retaining arms at the top of the RF Analyzer, rotate the
tablet toward you and remove it.
Extend the stand on the rear of the tablet “boot” and place the tablet beside
the Analyzer, either on its left or right side according to convenience.
As HF test leads must not be allowed to drape over the tablet screen, the
tablet is usually placed to the side of the RF Analyzer which is opposite the
electrosurgical generator under test.
Use the micro-USB cable (P/N 3140-478) provided with vPad-ESU to connect the
port labelled “USB” on the tablet to the USB jack on the RF Analyzer. Do not
connect the USB cable to the tablet port labelled “HOST”; this port is for
connection of optional external devices such as USB flash drive, barcode
scanner, keyboard and so on. The micro-USB to USB Type A adaptor provided with
the tablet connects to the “HOST” port when needed for interface with an
external device. Note that tablets are constantly evolving and the power and
USB location(s) may change over time. If in doubt, consult your local Datrend
representative or contact technical service on the Datrend website
www.datrend.com .
Use the 5V power cable (P/N 3140-477) provided with vPad-ESU to connect the
power jack on the tablet to the power jack on the RF Analyzer. Note there are
different plugs on each end of this cable; the smaller plug connects to the
tablet and the larger to the RF Analyzer.
Use the line cord provided with vPad-ESU to connect the RF Analyzer to the AC
mains supply. The receptacle for the line cord is located on the right side of
the Analyzer.
Use the ON/OFF switch located beside the line cord receptacle to power up the
RF Analyzer. The power indicator on the front of the Analyzer should
illuminate green, and the fans located on the left of the unit should begin to
run at relatively low speed.
Power up the tablet by pressing and holding the tablet’s ON/OFF button, which
is located immediately to the right of the power jack. Hold the button down
until the tablet starts up, then release. After startup, the tablet should
display the manufacturer logo and then, after a few seconds, the Android HOME
screen.
Switch the tablet OFF when vPad-ESU is not in use. Press and hold the ON/OFF
button until a confirmation message appears on the tablet screen. Select the
appropriate response to complete the Power Off sequence.
Note: Pressing and releasing the Power ON/OFF button momentarily will put
the tablet in a ‘sleep’ mode. Press the ON/OFF button momentarily again to
‘wake’ the tablet. This is NOT the same as OFF.
To store or transport vPad-ESU, reverse the setup procedure. Note that the
unit is moved or shipped with the tablet placed in the retaining tray at the
front of the RF Analyzer such that the screen faces inward to the Analyzer.
Operation
This chapter explains how to use vPad-ESU to perform ESU testing. Test Record management is also covered in this chapter.
4.1 HOME Screen
The Android HOME screen is displayed approximately 20 seconds after switching
the tablet ON.
Initiate actions on the tablet by pressing the corresponding icon or button. For example:
| Press to launch the vPad-ESU application software, or “ap p “. Use this app
to perform ESU testing.
---|---
| Press to launch the vPad Record Manager app. Use this app to copy, print,
convert or delete Test Records saved by vPad-ESU. This app can be launched
from the HOME screen, or from within vPad-ESU by pressing the “Test Records”
button.
| Press to access Settings. Use this menu to configure sound, display,
touchscreen, and wireless setup.
By default, vPad-ESU is supplied with both WiFi and Bluetooth connectivity d
is ab le d . Use the Settings menu to enable wireless connectivity, in
accordance with policies of your institution or organization.
| At bottom center on the screen, press the Apps button to access more apps
which are installed on the tablet. (Note: Android OS icons may change over
time as the OS evolves)
| At bottom left on the screen, press the Home button to return from an app to
the Home screen. (Note: Android OS icons may change over time as the OS
evolves)
| At bottom left, press the Back button to navigate back one step, from the
app or screen currently being displayed, to a previous one. For some apps,
this button’s function may be disabled. (Note: Android OS icons may change
over time as the OS evolves)
| At bottom left, press the Recents button to jump from the current app to a
different app that was started earlier, but is currently on pause. (Note:
Android OS icons may change over time as the OS evolves)
For more information on how to use the Android tablet, refer to the tablet
operator manual supplied with vPad-ESU.
4.2 Startup
Press the vPad-ESU icon on the Android HOME screen to start the app. A splash
screen will display the product name and the software version. The app will
then connect to the RF Analyzer via USB, or alternatively by Bluetooth if
wireless operation has been enabled under the app’s Setup menu.
If the app is unable to connect to the RF Analyzer, a pop up menu is displayed with alternative connection options. You may attempt to retry connecting by the same or a different method.
If a connection is successfully made, the app will command the RF Analyzer to
perform self-tests of the Digital Signal Processor (DSP) and fans. If a test
fails, an alarm message is displayed and the app exits. If all self-tests
pass, the main menu of the app is shown.
4.3 Main Menu
The main menu of the app is the starting point for navigation to manual tests
(HF Output; HF Leakage; and REM (CQM) Test), automated tests (AutoSequences
and Power Curves), and app settings.
The “Operator’s Manual” button launches Acrobat Reader, passing the operator
manual PDF to the Reader.
If Acrobat Reader or this operator manual (MN-110) is not installed on the
tablet, an error dialog is displayed.
The “Test Records” button launches vPad Record Manager, passing the file
folder path for vPad-ESU to the manager. See section 4.13 for more information
on Record Manager.
4.4 Setup Menu
Application settings and user preferences are configured via the “Setup” menu.
To view or change the application settings, press the “Setup” button on the
main menu of the app.
4.4.1 Report Title
The “Test Report Title” on the Setup menu is inserted, center-justified, at
the start of each Test Record file.
Change this title to the name of your hospital or organization, if desired.
4.4.2 List Editor
The “Edit List” button of the Setup menu displays a pop-up that allows the
user to select one of the list files for editing. A “list” is a list of items
which the user may select from to streamline input of certain types of
information during a test, for example, ESU make and model, hospital
locations, ESU waveforms and resistance values which are used in testing the
REM/CQM function of the ESU.
To edit the list of ESU manufacturers and models, press “Edit List” and then select “Makes/Models”. This will display the ESU manufacturer and model list in an editor dialog. As noted at the top of this dialog, when editing or adding new ESU’s you must place a semicolon between the make and model on each line. During a test, the ESU pick list is presented in the order shown; therefore, you may prefer to delete irrelevant models from the list and reorganize it with most frequently-selected items first.
Select one of the other radio buttons to view or modify one of the other lists. For example, the figure below shows the ESU waveform list in the editor dialog. During a test, the list of waveforms is presented in the order shown; therefore, you may prefer to delete irrelevant waveforms from the list and reorganize it with most frequently-selected items first.
Press the “Exit” button to close the list editor without making changes to the
file. Press the “Save and Exit” button to update and then return to the Setup
menu.
4.4.3 AutoSequence Editor
To make changes to an AutoSequence, press the “Edit AutoSequences” button on
the Setup menu. This will display the AutoSequence selector menu.
Press a row of the list to select the corresponding AutoSequence file and pass it to a text editor app. When this is done for the first time, you will be prompted to select an app to open the file with. The user can choose to use the selected editor one time only or always.
AutoSequences are script-based programs which are written in the vPad “RFA”
language. Refer to the RFA Programmer’s Guide for vPad-ESU for information on
creating automated test sequences and preventive maintenance inspection
procedures for vPad-
4.4.4 Power Curve Test Editor
To modify a Power Curve test or create a new one, press the “Edit Power Curve”
button on the Setup menu. This will display a selector for Power Curve tests.
Choose the test you wish to view or change to open it in an editor UI.ESU.
When a row of the selector is pressed, the corresponding “.pc” file for the test is passed to the power curve editor UI. The UI provides controls for editing the parameters of the power curve test setup.
The name of the power curve test, which is the same as its filename on the
tablet, is displayed as the “Test Title” at the top of the editor UI. This
field cannot be edited. To create a new power curve test, press the “Save As
New” button of the editor. You will then be prompted to enter a filename for
the new power curve file.
Except for the loads used during the test, the power curve settings are self-
explanatory. The setup includes choices for ESU output under test (CUT; COAG;
or Bipolar), method of ESU activation (automatic via footswitch control, or
semi-automatic based on prompting the user to activate the ESU by footpedal or
handswitch); and the ESU on/off duty cycle. Waveform and power settings are
used when displaying setup instructions to the user on initiation of the test.
Test loads of the power curve setup are specified with a CSV format. Loads may
be specified individually as a simple list, for example: 50,100,200,500,1000
(ohms). Loads may be specified as a range with an implicit step interval equal
to one-tenth of the range, for example: 100-1000 means 100 to 1000 ohms in
steps of 100 ohms (10 readings). Loads may be specified as a range with an
explicit step interval, for example, 200-1000/200 means 200 to 1000 ohms in
steps of 200 ohms (5 readings). Loads may also be specified using any
combination of these methods, and do not need to be listed in ascending order.
For example: 50,1500-5000/500,100-1000,10 will cause power measurements to be
acquired for loads of 10, 50, 100, 200, 300… 900, 1000, 1500, 2000… 4500 and
5000 ohms (20 readings). When the test is executed, the load list is read,
parsed and sorted in ascending order. The loads are quantized down to the
nearest 5 ohms to suit the resolution of the variable load in the RF Analyzer.
A power curve test can optionally provide for automatic pass/fail of results
based on a list of upper and lower power limits in a CSV-formatted text file.
The limits filename is arbitrary but is typically chosen to describe the power
curve. As a convention, the filename should be given a CSV extension. Each
line in the CSV file specifies a load and the minimum and maximum power levels
which are acceptable for this load. An example of a power curve limits file
follows:
50,35.2,52.8
100,97.6,146.4
200,168.8,253.2
300,240,360
400,227.2,340.8
500,166.4,249.6
600,129.6,194.4
700,103.2,154.8
800,72.8,109.2
900,62.4,93.6
1000,55.2,82.8
In the above example, for a 50 ohm load the output of the ESU must fall
between 35.2 and 52.8 watts for the power measurement to be assigned a “pass”.
Pass/fail specifications for loads of 100, 200, 300… ohms are expressed
similarly, up to the highest load of the test (1000 ohms) for which the
measured power must range from 55.2 to 82.8 watts to be assigned a “pass”.
Such limits may be derived from power curve diagrams which are provided in the
operator manual of a ESU. This can be done by assigning a tolerance (e.g.
±20%) to the nominal power read from the curve for a given load.
Alternatively, a manufacturer may provide power curve specifications which
include tolerance information.
If limits have been specified in a power curve test, the limits are referenced
at the end of the test after all measurements have been completed. The list of
limits is searched to find loads which match the loads in the acquired test
data. If a match is found, the measured power for that load is compared to the
specified limits.
If all such comparisons are within range, the test is automatically assigned a
“PASS” or otherwise a “FAIL”. Specification of limits in a power curve test is
optional. If no limits have been specified in the setup, the user will assign
the final test result manually, by means of PASS/FAIL buttons which are
displayed below the results on completion of the test.
4.5 HF Output Test
The HF Output test is used primarily for measurement of RMS current and power
delivered to a set load by the ESU under test.
4.5.1 HF Test Setup
Start a HF Output test by pressing the “HF Output” button on the main menu of
the app.
The HF Output test begins by displaying the test setup.
The displayed schematic shows how to connect the device under test or “DUT” to
the RF Analyzer. Different schematics are shown depending on the buttons
selected (monopolar or bipolar ESU output; and internal load, external load,
or combination internal plus external load). Prior to starting the test,
connect the ESU to the RF Analyzer as shown in the schematic. Test leads shown
are included with vPad-ESU. Note the dispersive HF test lead without pin (P/N
7200-572) is used to connect the neutral or return port of the DUT to the
current monitor of vPad-ESU. The shorting jumper shown in the schematic is P/N
3220-600, and the red jumper lead is P/N 7200-574.
Optionally, vPad-ESU may be set up to activate and deactivate the ESU remotely
from the tablet. To do so, connect the appropriate footswitch control cable
between the FOOTSWITCH OUTPUT jack of the RF Analyzer and the footswitch
control inputs of the ESU. Available as accessories for vPad-ESU, footswitch
control cables can be obtained for Covidien/Valleylab ForceTriad (P/N
7200-557), Covidien/Valleylab Force FX (P/N 7200-559), ConMed System 5000 (P/N
7200-558) as well as other makes and models.
Press the “Help” button on the menu to view instructions on setup and
operation of the HF Output test. Press the “Footswitch Setup” button to
configure automatic control of the ESU via a footswitch cable such as the one
illustrated in the schematic above. More details on footswitch setup and
control are provided in a discussion of the HF Output menu to follow.
To change the load resistance for the test, press the “HF Load” text box and
input the value via the Android soft keyboard. To make the entered value a
startup default, check the “Save as default” box. The new default will then be
stored when the “Start Test” button is pressed.
4.5.2 Test Warning
Once all required connections to the DUT have been made, press the “Start
Test” button on the HF Test Setup menu to begin testing. The first time this
button is pressed, you will see a “KEEP LEADS AWAY…” warning.
Once shown, this warning is never displayed again as long as the app is not
exited. The warning is displayed one time only, each time the app is run.
Regardless of whether or not you see this warning at the start of a test,
always follow this instruction when using vPad-ESU. Test leads which are
conducting high-power, high-frequency energy can cause the touchscreen to
behave erratically if such leads are draped over the tablet, or brought close
to it.
4.5.3 Continuous Monitoring of HF Output
On starting a HF Output test, readouts of power, current and voltage are
displayed. Provided no ESU signal is present when the test is started, the
load will then be set to the resistance specified on the HF Test Setup screen.
If an ESU signal is present when the HF Output menu is entered, the app will not set the load. This is a protective measure to prevent damage or unnecessary wear of the control relays in the load array. If ESU activity is detected at test startup, an alarm message will be displayed instructing you to switch the ESU off. Deactivate the ESU, then press “Continue” on the alarm dialog to dismiss it and proceed with the test. When the app is in the state shown above, the RF Analyzer is continuously monitoring for an ESU signal. Measurements of power, current, voltage and crest factor are displayed when a signal is detected. In this mode, vPad-ESU acts similarly to a True RMS instrument which provides continuous monitoring of ESU output as long as the input signal is detected. Forced air cooling of the load is automatic and self-adjusts according to the power measured. At higher power levels, operational duty cycle restrictions should be observed (see section 1.1.8 for load power ratings).
While measurements are being displayed, they can be saved to a test data
buffer and thereby a record of the measurements can be created. This may be
done by pressing the “Save Data” button while readouts are active. Data
recording may also be accomplished automatically by having vPad-ESU control
the ESU, or semi-automatically when activating the ESU by means of a footpedal
or handswitched “test pencil”. Refer to sections 4.5.8, 4.5.9 and 4.5.10 which
follow for more details.
4.5.4 Changing the Load
Press the “Test Setup” button on the HF Output menu to display the HF Test
Setup menu, described earlier. Reasons for entering the setup menu are to
refer to the schematic, and to change the load resistance.
Note the current setting of the load is displayed above the “Test Setup”
button. The ESU must be deactivated when leaving the Setup menu to return to
HF Output measurement; if it is not, the load will not be set and an alarm
dialog will be displayed as described in the previous section.
4.5.5 Analyzer Setup
Press the “Analyzer Setup” button to display a menu for configuring the
Digital Signal Processor (DSP) of the RF Analyzer.
“Measurement Range” of the
Analyzer may be set to ±0.5, 1, 3, 6 or 12 amperes full scale, or to
“Autoranging”. The factory default is Auto-ranging and should be left at this
setting unless greater stability of the measurement is desired, which can be
achieved through appropriate selection of one of the fixed ranges.
“Signal averaging” is the amount of time the DSP spends accumulating and
analyzing signal data for calculation of RMS and peak values. Options for this
setting are:
-
Normal
RMS value is calculated by the DSP over 560 milliseconds; in this mode, vPad- ESU emulates the response of an analog test instrument such as a RF millivoltmeter -
Slow
RMS value is calculated over 1680 milliseconds; in this mode, vPad-ESU emulates the response of a thermal power meter such as a RF bolometer
The factory default setting for “Signal Averaging” is “Normal”, and this
should be used in most test situations. The “Slow” setting may be helpful for
improving stability of measurements for ESU signals that are amplitude-
modulated at frequencies in the 100 to 1000 Hz range.
Referring to Fig u re 22, “Trigger level” is the signal threshold above/below
which the DSP is triggered and begins to capture data for analysis. It is
represented as a percentage of the full-scale of the selected range.
The factory default is 5%. If set higher than 5%, vPad-ESU may not measure if
the ESU power output is small.
“Trigger edge” sets the triggering polarity to rising or falling edge of the
ESU signal. The factory default is rising edge. This feature is provided
mostly for the benefit of the HF digital oscilloscope, described in the
following section.
Analyzer settings may be changed and then applied via the “Apply” button.
These changes will be temporary and will be reset to previously-set defaults
if the HF Output test is exited. To save current settings as the defaults,
check the “Save as default setup” box then press the “Apply” button.
4.5.6 HF Digital Oscilloscope
The HF Output test includes an HF digital oscilloscope function which is
entered by means of the “Scope” button on the menu.
In oscilloscope mode, each time the RF Analyzer is triggered by an ESU signal,
a waveform is recorded by the Digital Signal Processor (DSP) for a duration of
0.0125 to 0.4 milliseconds, depending on the choice of horizontal scale.
Concurrently with and subsequent to acquisition of the waveform sample, the
DSP accumulates and analyzes ESU signal data for RMS and peak value
measurements over a much longer interval, nominally equal to 560 milliseconds
when the Analyzer’s signal averaging is set to “Normal”.
The waveform sample captured by the DSP is shown on the scope with vertical
scale set according to the measurement range in use (0.5, 1, 3, 6 or 12 amps).
The waveform is plotted in a chart at the left of the screen, with
corresponding “meter” values (power, RMS current and voltage) indicated to the
right of the chart.
The horizontal span of the scope depends on the range chosen by the user under
“Analyzer Setup”. This may be set to 1.25, 2.5, 5, 10, 20 or 40 microseconds
per division respectively. The choice of horizontal scale corresponds to a
sampling rate used by the DSP to record the waveform. This variable sampling
rate is used for waveform capture only; measurement of RMS and peak value over
the “Signal averaging” time is always performed at the maximum sampling rate
of the Analyzer.
A “Scope: TRIGGERED” message is used to represent presence of an input signal. Failure to receive a trigger within a set timeout causes the “Scope: TRIGGERED” message to change to “Scope: on hold” and the last recorded waveform to be redrawn in a different colour. In this way, the app emulates a normally-triggered oscilloscope.
When the oscilloscope is placed “on hold”, power, current and voltage
measurements are blanked as interruption of the input signal during the RMS
averaging time usually results in readings that do not correspond to the
waveform seen within the first 0.0125 to 0.4 msec following the trigger.
In oscilloscope mode, button functions at the bottom of the HF Output menu
remain the same as when meters are being displayed. An exception is the
“Scope” button which is re-labelled “Meter”, which if pressed hides the
oscilloscope and restores the RMS current and power meters.
Oscilloscope displays may be saved on the tablet as PNG image files and then
tied to a Test Record of the corresponding test results. Refer to section
4.5.9 for further details.
4.5.7 HF Spectrum Analyzer
In oscilloscope mode, the frequency spectrum of the input signal may be
observed by checking the “Spectrum” box.
In “spectrum mode”, each time waveform data is received from the DSP it is
further processed by the app and the result is plotted on the chart.
Therefore, the spectrum follows the input signal in realtime. When the ESU is
deactivated, the spectrum display is placed “on hold” as previously described
for the oscilloscope.
vPad-ESU derives the spectrum by Fast Fourier Transform (FFT) of the captured
waveform. The magnitude of the spectrum is obtained and then normalized to the
peak value before plotting on a linear or “dB” vertical scale. The resulting
display is useful for checking harmonic distortion in the ESU output as well
as relative levels of sidebands and spurious signals.
The horizontal span of the spectrum and the frequency resolution are directly
related to the horizontal scale of the oscilloscope as selected under
“Analyzer Setup”. These relationships are described by TABLE 4.5.7-1
following.
TABLE 4.5.7-1: Scope and Spectrum Analyzer Settings
Scope horizontal (ssec/div)| Scope time span (ptsec)| Spectrum
horizontal (MHz/div)| Spectral range (MHz)| Spectral resolution
(kHz)
---|---|---|---|---
1.25| 12.5| 2| 20| 39.1
2.5| 25| 1| 10| 19.5
5| 50| 0.5| 5| 9.77
10| 100| 0.25| 2.5| 4.88
20| 200| 0.125| 1.25| 2.44
40| 400| 0.0625| 0.625| 1.22
Similar to oscilloscope displays, spectra may be saved on the tablet as PNG
image files and then tied to a Test Record of the corresponding test results.
Refer to section 4.5.9 for details.
4.5.8 Footswitch Setup
Press the “Footswitch Setup” button to display a menu for configuring
automatic or semi-automatic footswitch control of the ESU under test.
Radio buttons at the top of
the menu select which of three ESU outputs will be activated when the
“Footswitch ON” button of the HF Output test is pressed. As shown, CUT, COAG
or Bipolar output of the ESU may be remotely activated by vPad-ESU.
“Footswitch ON-time” is the length of time the ESU is activated, in seconds.
It may be set between 1 and 20 seconds. The factory default setting for ON-
time is 3 seconds.
“Measurement delay” is a trigger hold-off delay between activating the ESU and
enabling the DSP of the RF Analyzer to start measuring. This delay is intended
to allow the ESU to stabilize before measurement of its output commences. Note
the measurement delay is restricted to the following range:
0 <= Measurement delay <= (Footswitch ON-time – 500 msec)
The factory default setting for measurement delay is 300 msec.
The “Manually-operated foot/handswitch” checkbox enables an alternative method
of testing where, as opposed to being automatically controlled by the
FOOTSWITCH OUTPUT port of vPad-ESU, the ESU is manually controlled by the
technician using a footpedal, or alternatively a hand-operated switch such as
a “test pencil”.
Settings on the “Footswitch setup” menu may be changed and then applied via
the “Apply” button. These changes will be temporary and will be reset if the
HF Output test is exited. To save current settings as the defaults, check the
“Save as default setup” box then press the “Apply” button.
Note that on return to the HF Output test, if the “Manually-operated…”
checkbox is not checked, the ESU output under control and the ON-time are
displayed above the “Footswitch Setup” button. If the “Manually-operated…”
checkbox is checked, only the ON-time will appear above the “Footswitch Setup”
button.
4.5.9 Automated Measurement with Data Recording
To measure HF output automatically, press the “Footswitch ON” button to
activate ESU CUT, COAG or Bipolar as indicated above the “Footswitch Setup”
button. Provided an ESU is connected to vPad-ESU, measurements of power,
current and voltage will be displayed during the footswitch “ON” time. While
in progress, the measurement may be optionally aborted by pressing the
“Footswitch OFF” button.
After the ESU has been activated, a timer above the “Footswitch ON/OFF” button counts down in seconds. When the timer reaches zero, the ESU is deactivated and the measurement results are forwarded to the “Save HF Test Result” dialog. After ESU deactivation, the “Footswitch ON/OFF” button will be locked out for duration equal to the ON-time, thereby maintaining a 50% operational duty cycle.
The “Save HF Test Result” dialog enables you to save the measurement results
and thereby create a record of tests performed on the ESU. However, saving
measurements while testing in this way is optional. If you do not wish to save
the displayed measurements, simply press the “Cancel” button to dismiss the
“Save…” dialog and return to testing.
Optionally, measurement results can be saved with a corresponding description
of the ESU waveform that produced them. To include a waveform description with
the result, press the “Waveform” selector and choose an item from the
displayed pick list.
For the “Test Result”, select PASS, FAIL or INFO ONLY as appropriate, which
will then enable the “Save” button on the dialog. Enter “Notes” if desired,
then press “Save”. Results saved to the test data buffer may be viewed using
the “View Data” button on the HF Output menu.
If the HF Output test is set to oscilloscope mode, when the “Save HF Test
Result” dialog appears the menu will include a “Save scope screenshot”
checkbox. If this box is checked and the “Save” button then pressed, a PNG
image of the oscilloscope screen is saved to a file with an auto-generated
filename:
wfm_ YYYYmmDDhhMMss.png for waveforms
**fft YYYYmmDD_hhMMss.png for spectra
The resulting PNG file is saved in a temporary folder on the tablet. If a Test
Record is eventually saved, the temporary folder is renamed with the equipment
ID or control number of the ESU under test. Images saved during tests of HF
Output and other tests may be found in the vPad-ESU file folder on the tablet.
Test results saved to the data buffer may be viewed with the “View Data”
button on the HF Output menu. A Test Record file of the results may be saved
from the “View Data” menu if a control number has been entered via the
“Equipment Information” menu. For further details, refer to sections 4.8 and
4.9 respectively.
4.5.10 Semi-Automated Measurement with Data Recording
** Automated measurement and data recording requires a footswitch control
cable to interface the FOOTSWITCH OUTPUT of vPad-ESU to footswitch control
inputs of the ESU.
As an alternative, the ESU may be activated manually but the measurement
result is recorded automatically after a predetermined ON-time. This
alternative mode is enabled by selecting the “Manually-operated…” checkbox on
the “Footswitch Setup” menu. With this option, the “Footswitch ON/OFF” button
of the HF Output test will be greyed out.
When “Manually-operated…” of the “Footswitch Setup” is enabled and the HF
Output menu restored, a pop-up message is displayed for a few seconds. The
pop-up message displays “Activate CUT”, “Activate COAG” or “Activate BIPOLAR”,
depending on the radio button selected on the “Footswitch Setup” menu. The
first time this prompt appears, it is accompanied by a bell tone. On
subsequent appearances, the popup is displayed silently.
When you see this prompt, activate the corresponding output of the ESU
manually, using the ESU’s footpedal control or a handswitched device such as a
“test pencil”. If and when an ESU signal is detected, a timer posted above the
disabled “Footswitch ON” button is initialized with the ON-time specified on
the “Footswitch Setup” menu. The timer then starts counting down to zero. When
the timer reaches zero, a pop-up is displayed which says “Switch RF off!”. The
“off” message is always accompanied by an alert tone. As instructed, switch
the ESU off immediately.
As the “Switch RF off” prompt is being displayed, the measurement results are
forwarded to the “Save HF Test Result” dialog as described in the previous
section. Select a “Test Result” and save the measurement, or alternatively
discard the data by pressing the “Cancel” button on the dialog.
4.6 HF Leakage Test
The HF Leakage test is used to measure high-frequency current or power from
specific ESU output terminals to protective earth or “ground”. Leakage
measurements are compared to a maximum limit defined in a standard or by the
ESU manufacturer.
4.6.1 HF Leakage Setup
Start an HF Leakage test by pressing the “HF Leakage” button on the main menu
of the app.
The HF Leakage test begins by displaying the test setup.
Use the “Previous Test” / “Next Test” buttons to select one of seven possible
test configurations. Choose the test to suit the ESU characteristics (isolated
or ground-referenced) and the generator output to be tested (monopolar or
bipolar). ESU, test and load descriptions are shown on the left and a
corresponding wiring diagram for the test is shown on the right. Below the
wiring diagram is a reference to the 60601-2-2 standard which provides the
testing specifications.
As selected by “Previous / Next Test” buttons, the leakage tests are as
follows:
Test #1: for isolated monopolar output, measuring HF current from the active
terminal of the generator to earth through a 200-ohm load. Note jumper P/N
7200-582 is used in this test.
Test #2: for isolated monopolar output, measuring HF current from the
dispersive or neutral terminal of the generator to earth through a 200-ohm
load (rated 16 watts).
Test #3: for earth-referenced monopolar output, measuring HF current from the
dispersive terminal of the generator to the earth while the generator drives a
specified load connected between active and dispersive terminals.
Test #4: for earth-referenced monopolar output, measuring HF current from the
dispersive terminal of the generator to the earth while the generator drives a
specified load connected between the active terminal and earth.
Test #5: for isolated bipolar output, measuring HF current from bipolar output
terminal #1 to the earth through a 200-ohm test load. In this test, the
monopolar dispersive terminal of the generator is also connected to the earth
through a load.
Test #6: for isolated bipolar output, measuring HF current from bipolar output
terminal #2 to the earth through a 200-ohm test load. In this test, the
monopolar dispersive terminal of the generator is also connected to the earth
through a load.
Test #7: cross-coupling test, measuring HF current from an unused output of
the ESU while a different, independent output is activated to deliver power to
a specified load resistance.
Note this test does not appear in the IEC60601-2-2 standard, but is
required by certain manufacturers for specific ESU models.
WARNING: HIGH VOLTAGE
Some HF leakage tests may require connection of an unterminated lead to the
DUT. Place the free end of the unterminated lead safely out of harm’s way for
the test. To avoid RF burns, exercise caution while testing is in progress.
The use of automated footswitch control and data recording per section 4.5.9
is recommended for performance of HF leakage tests, unless the manufacturer’s
test instructions specify otherwise.
Tests #2 through #7 require a load to be specified. Enter the required value
into the “DUT Load” box beneath the test description. The default load is 200
ohms, as specified in the IEC standard. A manufacturer may specify a different
load depending on the model; consult ESU accompanying documents or the
manufacturer’s service manual for the generator if necessary.
Enter the pass/fail limit for leakage into the “Leakage Limit” box below the
schematic. Initially, a default limit of 150 mA is set, which is the value
specified in the IEC standard. You may choose either milliamps (mA) or watts
(W) as the units of measure by means of radio buttons below the wiring
diagram. Initially, the default units of measure is “mA” per the IEC standard.
Alternatively, a manufacturer may specify the limit in watts; consult the
service manual of the ESU for test specifications.
The “Help” button displays detailed instructions for setup and use of the
leakage test. These instructions should be consulted before and during the
test. The “Footswitch Setup” configures footswitch control of the DUT; refer
to section 4.5.8 for instructions.
Once the appropriate test has been selected and the generator connected as
shown in the diagram, press the “Start Test” button to run the test.
4.6.2 HF Leakage Measurement
When the HF Leakage menu is entered, a meter which measures in milliamps or
watts is shown, depending on the units of measure selected on the test setup
menu. The HF load will be set to the specified resistance, if a DUT load is
required to perform the test. If a load is used, fans are set to maximum
accordingly. If a DUT load is not used, fans operate at a lower RPM.
If an ESU signal is detected when the HF Leakage test is entered, the app will
not be able to set the load. In this case, an alarm dialog is displayed.
Switch the ESU off, then press “Continue” to dismiss the dialog and proceed
with the test.
The “Analyzer Setup” button displays a menu for configuring the DSP of the RF
Analyzer. This is the same menu as used in the HF Output test; see section
4.5.5 for instructions.
The “Test Setup” button of the HF Leakage test displays the HF Leakage setup
menu, described in the previous section. Return to the setup menu to refer to
the schematic or to choose a different test configuration. On exiting the
setup menu, the HF load will not be set if the ESU is running.
The “Footswitch Setup” button displays a menu for configuring the footswitch
control relays of the RF Analyzer. This is the same menu as used in the HF
Output test; see section 4.5.8 for instructions.
The “Footswitch ON” button activates the ESU output shown above the
“Footswitch Setup” button. The operation of this button is the same as the
“Footswitch ON/OFF” button of the HF Output test. Refer to sections 4.5.9 and
4.5.10 for details.
When HF leakage is detected, the value is displayed in the readout and is
compared to the maximum limit specified in the test setup. Depending on the
result, “PASS” or “FAIL” is then shown below the readout accordingly.
According to standards, the leakage value should never exceed 150 mA or 4.5W.
The rating of the leakage test load is 16W, which corresponds to 283 mA. If a
leakage measurement exceeds 245 mA or 12W, the test is stopped, an alarm
dialog is displayed, and a repeating alarm tone is emitted. If this alarm is
seen, switch the ESU off immediately and check the test connections. Once the
problem has been corrected, press the “Continue” button on the alarm dialog to
dismiss it and return to testing.
Provided there is no leakage alarm, the user may press the “Save Data” button
to copy the leakage reading to the “Save HF Leakage” menu. As described in
section 4.5.9, optionally select the ESU waveform in use from the pick list,
enter “Notes” if desired, and press the “Save” button to copy the leakage
measurement to the test data buffer. There is no need to manually choose a
pass or fail result since it is automatically assigned based on the limit.
If the “Save Data” button is pressed before a reading has been seen, the “Save
HF Leakage” menu is displayed but the “HF Leakage” value is set to zero. This
enables a user to record a specific case where the ESU under test produces
little or no detectable leakage, thereby resulting in a test “PASS”. This
type of result may be encountered when testing cross-coupled leakage between
ESU outputs (leakage test #7).
If CUT, COAG or BIPOLAR footswitch control is in use, the leakage is captured
and the “Save HF Leakage” dialog is shown automatically when the footswitch
timer reaches zero count. This is similar to automated measurement and data
recording in the HF Output test (see section 4.5.9). If no leakage has been
detected by the time the footswitch timer reaches zero, the “Save HF Leakage”
dialog is still displayed but the “HF Leakage” result is set to zero and the
test result is assigned a “PASS”. Similarly, if measuring semiautomatically as
described in section 4.5.10, when the “Switch RF off” prompt appears there may
be no detectable leakage and thus the “Save HF Leakage” dialog will show a
measurement of zero and test result of “PASS”. Accept the result by pressing
the “Save” button on the dialog, or press “Cancel” to discard and then retest.
Leakage results saved to the test data buffer may be viewed with the “View
Data” button. A Test Record file of the results may be saved from the “View
Data” menu if a control number has been entered via the “Equipment
Information” menu. For further details,
refer to sections 4.8 and 4.9 respectively.
4.7 REM (CQM) Test
The REM (CQM) test is used to verify the Return Electrode Monitor (REM) or
Contact Quality Monitor (CQM) function of the ESU. The test is performed by
varying a resistance which is connected to the REM or CQM port of the ESU. The
test procedure involves setting the resistance to specified values and
observing the corresponding response of the ESU’s REM or CQM alarm indicator.
Typically, you will need to follow a specific test procedure provided by the
manufacturer of the ESU.
4.7.1 REM Test Setup
Start a REM (CQM) test by pressing the “REM (CQM) Test” button on the main
menu of the app.
Set up the test as shown in the following diagram.
As shown, use a REM test cable to connect the REM (CQM) jacks of vPad-ESU to
the REM or CQM port of the device under test (DUT). For the majority of ESU
models, to connect vPad-ESU and the ESU you will use a REM test cable with a
pin on the rectangular plug (P/N 7200-570). This cable is provided with vPad-
ESU as a standard accessory. With some ESUs, for example Olympus ESG-400, a
REM test cable without pin must be used. This cable is available as an
optional accessory (P/N 7200-571). Some
manufacturers specify a test procedure in which both cables will be needed to
completed all steps of the test (e.g. Covidien or Valleylab Force FX).
4.7.2 REM Test Procedure
The REM test menu provides a user interface for varying the resistance across
the REM (CQM) jacks. The resistance can be varied between zero and 1023 ohms
with a precision of one ohm.
Use any of the following methods to vary the resistance:
- Drag the slider control below the resistance readout.
- Increment or decrement the resistance in one ohm steps by pressing the or button.
- Increase the resistance continuously by pressing and holding the button, or by pressing the “Sweep Up” button. Discontinue the automatic sweep by pressing the “Stop Sweep” button.
- Decrease the resistance continuously by pressing and holding the button, or by pressing the “Sweep Down” button. Discontinue the automatic sweep by pressing the “Stop Sweep” button.
- Press the “Set” button and input a specific resistance value using the keyboard, or choose a resistance from a list of favourites.
On the “Set Resistance” dialog, press the “Choose” button to display a pick
list of preset resistance values.
The list of presets can be modified by the user; see section 4.4.2 for editing
instructions.
The resistance is set to a default value when the REM test is started. To
change the default, press the “Set” button then enable the “Save as default”
checkbox on the “Set Resistance” dialog. Enter the desired startup value then
press “Done” on the keyboard.
When testing the REM or CQM alarm function of the DUT, follow the test
procedure of the ESU manufacturer. Set or sweep the test resistance and
confirm the ESU produces a REM alarm, or clears the alarm, at the specified
values of resistance.
4.7.3 Saving REM Test Results
The “Save Data” button on the REM test menu may be pressed at any time to
record a test result.
Select alarm “ON” or “OFF” according to the current status of the DUT for the
resistance value displayed.
Then, choose a “Test Result” depending on how the DUT should be responding to
the resistance according to the manufacturer’s specifications. Choose “INFO
ONLY” if there is no specified DUT response for the set resistance but the
value is being recorded to show compliance with the testing procedure. Once a
“Test Result” is selected, press the “Save” button to copy the result to the
test data buffer.
REM test results saved to the data buffer may be viewed with the “View Data”
button. A Test Record file of the results may be saved from the “View Data”
menu if a control number has been entered via the “Equipment Information”
menu. For further details, refer to sections 4.8 and 4.9 respectively.
4.8 Viewing Test Results
The “View Data” button may be pressed to view the current contents of the Test
Record data buffer.
On this menu, “Clear Last” erases the most recently-recorded measurement from
the buffer. “Clear All” clears the entire buffer. A confirmation prompt is
displayed if “Clear All” is pressed.
“Enter Equipment Information” opens the equipment information menu, which is
described in section 4.9. Once an equipment ID or control number has been
entered via the “Equipment Information” menu, the “Create Record” button will
be enabled which allows results in the data buffer to be permanently saved as
a Test Record file on the tablet. Refer to section 4.10 for details on
creating a Test Record.
4.9 Entering Equipment Information
The Equipment Information menu is used to enter details about the ESU under
test. This menu can be entered from the “View Data” menu (see section 4.8).
The menu is also displayed when an automated test is started.
As shown above, the menu provides fields for manual input of control number,
serial number, description, manufacturer, model, location, facility and
technician. Of these, only the Control Number m u s t be entered to enable
saving of a Test Record file. To enter information, press the corresponding
field to display the Android soft keyboard.
Buttons are provided on the menu for erasing selected fields of the
information: control and serial number only; make and model only; or all
fields on the menu. Facility and technician fields are “sticky” and are
maintained in a file on the tablet.
If the description field is blank when the menu is opened, it is auto-
populated with “Electrosurgical generator” by default. The “Choose Device”
button displays a pick list of ESU makes and models; use the pick list to
streamline input of manufacturer and model fields of the information.
Similarly, use the “Choose” (location) button to select from a list of hospital locations. The lists of ESU models and hospital locations may be modified by the user; see section 4.4.2 for editing instructions.
Pressing the control number “Search” button causes the app to search for an
equipment.csv file on the tablet, and if such a file is found, the file is
then searched for a match to the ID in the control number field.
If a match is found, the information fields on the menu are then automatically
populated from the CSV file.
There are several ways a user may create or obtain a CSV file of ESU
equipment. The most direct but perhaps least efficient way is to create the
file with a spreadsheet program, entering the equipment information manually
and then saving the spreadsheet in CSV format. Alternatively, it may be
possible to create an equipment.csv file as an export from your Computerized
Maintenance Management System (CMMS). With these approaches, the resulting
equipment.csv file should be copied to the Datrend/vPad-ESU folder on the
tablet so that the vPad-ESU app can find it.
Alternatively, an equipment.csv file can be created by the vPad-EQM™ Equipment
Manager app, or imported to the tablet from a CMMS by the vPad-mT™ medTester
Emulator app. If vPad-ESU does not find an equipment.csv file in its own
folder, it will try to find it in folders used by the vPad-EQM and vPad-mT
apps. If an equipment.csv file cannot be found when the “Search” button is
pressed, the error is reported by means of a dialog.
The first line of the equipment.csv file specifies the data columns and
subsequent lines contain the equipment data. Below is an example showing how
to format the equipment.csv file:
ControlNumber,SerialNumber,Description,Manufacturer,Model,Location,Facility,NextDate
CN11705,13DGP121,Electrosurgery Unit,CONMED,System 5000,OR 6,Anytown General
Hospital,2016-Jul-14
CN13041,V312-006-2,Electrosurgery Unit,VALLEYLAB,Force FX,OR 2,Anytown General
Hospital,2016-Sep-8
CN13042,V318-011-2,Electrosurgery Unit,VALLEYLAB,Force FX,OR 3,Anytown General
Hospital,2016-Sep-8
…
CN200452,4953001498,Electrosurgery Unit,OLYMPUS,ESG-400,OR 9,Anytown General
Hospital,2016-Dec-4
4.10 Creating a Test Record
Once measurement data has been recorded and a control number has been input
via the “Equipment Information” menu (section 4.9), it becomes possible to
create a Test Record of the measurements. To do so, press the “Create Record”
button on the “View Data” menu (see section 4.8). The Test Record filename is
auto-generated based on the control number as shown in the example below.
Optionally, enter technician labour time in minutes or hours and a due date
for the next test of the ESU. To streamline input of a due date, press “1
year” to generate a default equal to today plus 12 months.
To view Test Records which have been saved by vPad-ESU, press the “Test
Records” button on the main menu of the app. This will launch the vPad Record
Manager app which will allow such Records to be converted from the native
format to PDF, printed, transmitted to a PC by Bluetooth or through the
internet, or copied to a USB flash drive connected to the tablet. Refer to
section 4.13 for details on the Record Manager.
4.11 Automated Testing
Automated test sequences or “AutoSequences” are based on manual tests
described in the preceding sections. In addition to test measurements,
AutoSequences can be programmed to include procedural instructions, drawings
or schematics, and inspection checkpoints. AutoSequences are ideal for
performing preventive maintenance (PM) inspections of electrosurgical
equipment in accordance with manufacturer’s specifications.
4.11.1 Selecting and Starting a Test
An automated test or PM procedure is selected by pressing the “AutoSequences”
button on the main menu of the app.
Each automated test corresponds to a “.rfa” file in the vPad-ESU file folder on the tablet. The AutoSequence selector menu displays the filenames in ascending alphabetical order, but without the “.rfa” file extension.
Select the desired test by pressing a row of the “Select Autosequence” menu.
If the “KEEP LEADS AWAY…” warning has not yet been displayed, it is shown now.
See section 4.5.2 for further information on this important warning.
As a first step, you are prompted to input information about the ESU under
test. Fill in the information then press “Next Step” to proceed. For more
details on the “Equipment Information” menu and the equipment “Search”
function, refer to section 4.9.
Entering equipment information at this stage is optional. To skip the
information input, simply press “Next Step” to begin the test immediately. At
the end of the test, you will be prompted to enter an equipment control number
as this is the minimum information required to create and save a Test Record
file.
4.11.2 Test Execution
After inputting or skipping the equipment information, the automated test is
executed as a series of steps which are performed sequentially, one after the
other.
Press the “Next Step” button to increment to the next step of the sequence.
Press the “Previous Step” button to review prior instructions or results. To
abort the test and discard acquired results, press the “Quit Test” button. You
will be prompted to confirm the abort in this case.
During a PM inspection, a fault in the equipment may be encountered which
cannot be corrected at time of test. In this case, press “Finish Test” to
create a Test Record of results acquired up that point in the procedure¹ .
Repair the fault then repeat the AutoSequence/PM from the beginning.
Follow instructions as these are displayed during the procedure. Certain steps
may require you to examine a schematic or photograph. Press the “Show Picture”
button when such steps are encountered. If necessary, pinch-zoom and drag
gestures may be used to expand specific areas of displayed images.
Since the PM is incomplete, the Test Record will be assigned a “FAIL”. A record of failed equipment may not seem particularly helpful, however, provided faulty equipment is identified and quarantined for repair, the Test Record provides evidence that the PM completion requirement of the equipment management system has been addressed.
To exit the image viewer, press the BACK button , then press “Next Step” to
continue with the procedure.
Inspection steps or “checks” will require you to examine the ESU and select
“PASS”, or otherwise an alternative result such as “FAIL”, “SERVICE”, “INFO”
or “N/A” (not applicable). If you choose “PASS”, the sequence advances to the
next step automatically. If you choose a result other than “PASS”, the app
will prompt you for a rationale for that result and will display the keyboard
so you can enter it. For results other than “PASS”, you must enter a reason
after which the sequence will be permitted to move on with the next step. For
these inspection steps, the results can be entered automatically by using a
barcode scanner to scan preprinted “PASS”, “FAIL” or “SVC” (service) barcodes.
Test steps will measure HF Output, HF Leakage or REM (CQM) alarm response. These steps operate similarly to their manual counterparts as described in preceding sections of this manual. Each test step includes pass/fail limits for the measurement result. If the measurement falls within the specified limits, the sequence advances to the next step automatically after a short delay.
If instead of “PASS” the measurement is a “FAIL”, the sequence stops at the
current step which enables you to correct the problem and repeat the
measurement.
At the end of the sequence, you are shown a summary of the results and you are
then prompted to create a Test Record. The Test Record filename is auto-
generated based on the control number as shown in the example below.
If you did not enter a control number at the start of the test, you will be
prompted to enter it now by means of a dialog. Press “Continue” to dismiss the
dialog and view the “Equipment Information” menu. Input the required control
number which will then enable you to save the Test Record.
On “Create Record” dialog, optionally enter the technician labour time in
minutes or hours and a due date for the next test of the ESU. To streamline
input of a due date, press “1 year” to generate a default equal to today plus
12 months. When the Record is saved, you will be returned to the main menu of
the app.
To view Test Records which have been saved by vPad-ESU, press the “Test
Records” button on the main menu of the app. This will launch the vPad Record
Manager app which will allow such Records to be converted from the native
format to PDF, printed, transmitted to a PC by Bluetooth or through the
internet, or copied to a USB flash drive connected to the tablet. Refer to
section 4.13 for details on the Record Manager.
4.11.3 AutoSequence Programming
Example AutoSequences are provided with the vPad-ESU app. The example
AutoSequences include PM inspection procedures for ConMed, Covidien, Olympus
and Valleylab ESU models. The PM procedures provided with vPad-ESU may be
copied and used as templates to write new PM procedures for other ESU models.
Note that AutoSequences provided with vPad-ESU are based on manufacturer’s
information available at the time the sequences were created and are subject
to change without notice. Datrend provides the procedures as examples only
and they should be reviewed and approved before use.
AutoSequences are script-based programs which are written in the vPad “RFA”
language. Minor changes and updates to RFA scripts can be accomplished on the
tablet using an editor app (see section 4.4.3). Programming of RFA scripts
from scratch is more easily accomplished on a desktop or laptop computer,
using a chroma-coded editor intended for writing program code or alternatively
by using the Datrend v Pad IDE™ software for MS Windows™.
Refer to manual MN-151 RFA Programmer’s Guide for vPad -ESU for more
information on creating automated test sequences and preventive maintenance
inspection procedures for vPad-ESU.
4.12 Power Curves
A power curve test is a special kind of automated test sequence in which ESU
output power is measured while the load is varied over a range of preset
resistance values. The test may be completely automated, in which vPad-ESU
switches the ESU on and off by means of a footswitch control cable.
Alternatively, the test may be semi-automated in which case the technician is
prompted by vPad-ESU to activate the generator by means of a footpedal or
handswitch device.
4.12.1 Selecting and Starting a Test
A power curve test is selected by pressing the “Power Curves” button on the
main menu of the app.
The selector menu displays the power curve tests which are currently stored on the tablet.
Select the desired test by pressing a row of the “Select Power Curve Test”
menu. If the “KEEP LEADS AWAY…” warning has not yet been displayed, it is
shown now. See section 4.5.2 for further information on this important
warning.
4.12.2 Test Execution
A Power Curve test begins by displaying the test setup instructions. The
instructions are derived from settings which are contained in the power curve
setup.
Connect the ESU to be tested to vPad-ESU as shown in the diagram. Set the ESU power, mode and waveform to the settings specified in the instructions. If the test is fully automated, you will be required to connect a footswitch control cable from the FOOTSWITCH OUTPUT of vPad-ESU to corresponding footswitch inputs of the DUT. Available as accessories for vPad-ESU, footswitch control cables can be obtained for Covidien/Valleylab ForceTriad (P/N 7200-557), Covidien/Valleylab Force FX (P/N 7200559), ConMed System 5000 (P/N 7200-558) as well as other makes and models.
Once the ESU has been set up and connected to vPad-ESU as required, press the “Start Test” button to run the test sequence.
Status of the test sequence is displayed near the top of the screen. For tests where the generator is activated manually (footswitch control not is use), obey the prompts which are displayed at the top of the screen and switch the ESU on or off when instructed to do so.
According to the test setup, at each step of the test sequence:
a. The resistance of the HF load is set.
b. For fully-automated tests, the specified footswitch control is activated;
for manual tests, the user is prompted to activate the generator.
c. The power is measured and is displayed in the status area near the top of
the screen. For manual tests, a “Save Data” button is shown below the data
table on the right and becomes enabled when the ESU signal is detected. Press
the “Save Data” button to save the power measurement to the data table.
e. The data table scrolls down automatically as power measurements are added
to it, and the power graph is updated.
f. For a manual test, the user is prompted to switch off the ESU once the data
table and graph have been updated. vPad-ESU waits until the ESU signal
disappears, then clears the prompt from the status area.
g. Once the ESU has been de-activated, vPad-ESU delays for a period of time
that is determined from the duty cycle specified in the test setup. During the
delay, a countdown timer is shown in the status area. After the “off” delay,
the next load is read from the test setup and the process repeats, beginning
with step (a.) above.
The test sequence stops when all loads have been tested. A “Save Test” button then appears at far right, below the data table. Test result buttons appear on the left. To save the test, select a result and press the “Save Test” button.
If a “limits” CSV file has been specified in the test setup, upper and lower limit curves as read from the file will be shown in red on the chart. At the end of the test sequence, the acquired power measurements are compared to the limits from the CSV file. A “PASS” or “FAIL” result is automatically assigned based on the limit comparisons. To save the results, simply press the “Save Test” button.
A “Save graph” checkbox is displayed on completion of the test sequence. If
this box is checked and the “Save Test” button then pressed, a PNG image of
the power graph is saved to a file with an auto-generated filename:
pwr_YYYYmmDD_hhMMss.png
The PNG image is saved to a temporary folder on the tablet. If a Test Record
is eventually saved, the temporary folder is renamed with the equipment ID of
the Test Record. Images saved during power curve and other tests may be found
in the vPad-ESU file folder on the tablet. Refer to section 4.10 for details
on saving a Test Record.
4.12.3 Power Curve Programming
Example Power Curve tests are provided with the vPad-ESU app. These may be
used as templates to create new tests. Refer to section 4.4.4 for programming
instructions.
4.13 Record Manager App
vPad Record Manager is an app which is installed on the Android tablet and
which may be run independently of, or simultaneously with, the vPad-ESU app.
Record Manager may be used to copy, print, and/or delete Test Record files
saved by vPad-ESU. Record Manager can also be used to convert Test Records to
Adobe PDF documents. Note that PDF is a format which enables vPad Record
compatibility with other Android apps, for example, e-book readers and
document printing apps.
Press on the Android HOME screen to launch the Record Manager app.
Refer to MN-087a 6100-081 v Pad -RM O p e rato rs Man u al for further information on use of the Record Manager.
Calibration and Maintenance
Calibration of vPad-ESU by a Datrend Authorized Service facility is
recommended on an an nual basis, and is required to extend the product
warranty. The basic one (1) year warranty on the RF Analyzer can be extended
to a maximum of two (2) years provided that annual calibration is performed by
a Datrend Authorized Service Center on an annual basis. Refer to the
Calibration Decal applied to the rear panel of the unit to determine
calibration status of your vPad-ESU.
vPad-ESU contains no user serviceable parts. Failure of vPad-ESU will require
return of the unit to an authorized service facility for repair. Opening the
case of vPad -ESU for any reason will void the warranty and may compromise
user safety .
Service must be performed by a factory trained, authorized service agent.
This unit contains hazardous voltages which may cause injury if correct
service procedures are not followed.
For calibration or service assistance, contact Datrend for a Return Materials Authorization (RMA) number and the location of the nearest Service Facility.
Datrend Systems Inc.
Unit 130 – 4020 Viking Way
Richmond, BC • CANADA • V6V 2L4
Tel: 800.667.6557 (North America only) or
+1.604.291.7747 • Fax +1.604.294.2355
e-mail: customerservice@datrend.com
www.datrend.com
vPad-ESU may be cleaned with a soft, lint free, damp cloth using a mild
detergent. Use of other cleaning agents on the touchscreen may result in
scratching, discolouration, streaking or even failure.
Electrical safety protection of the operator may be compromised if the
instructions in this manual are not followed, or if vPad-ESU is used for a
purpose not specified in this manual.
APPENDIX A. Sample Test Record
This appendix provides an example of a vPad-ESU Test Record, illustrating the data representation for HF output, HF leakage and REM (CQM) tests as well as equipment inspection tasks. The following was obtained by running the “ConMed System 5000 PM Inspection” AutoSequence provided with vPad-ESU. This AutoSequence includes all steps of the preventive maintenance inspection procedure specified by the manufacturer in the ConMed 5000 service manual (CONMED Manual No. 60-8-17-ENG Rev. S, 2010).
Biomedical Engineering Dept.
St. Joseph’s Hospital
1234 Main Street
MyTown MyState 98765
Phone: 123-456-7890 Ext. 123
File: CN1838_20151116_125648_P.txt
Date: 2015 Nov 16
Time: 12:56:48
vPad-ESU: VRF15010100
Equipment Information…
Control Number: CN1838
Description: Electrosurgical unit
Manufacturer: ConMed
Model: System 5000
Serial Number: 13DGP121
Location: OR14
Facility: St. Joseph’s Hospital
Technician ID: RWJ
Tech Time (hrs): 2.50
Overall Result: PASS
Next Test Due: 2016 Nov 16
Signature:__ Date:__
Detailed Test Data…
AutoSequence: ConMed System 5000 PM Inspection.rfa
Test Run-Time: 109 minutes
Task: Perform POWER-ON test. Confirm: audio tones emitted; all displays
operational; and no error codes displayed after self-test.
Result: PASS
Task: Check operation of CUT footswitch control
Result: PASS
Task: Check dispersive alarm indicators and sound
Result: PASS
Task: Verify keypad operation for Pure Cut Mode
Result: PASS
Task: Verify keypad operation for: BLEND 1, 2 & 3; COAG Pinpoint, Standard &
Spray; BIPOLAR Micro & Macro; PULSE Cut & Coag; FLUIDS & LAP modes
Result: PASS
Task: Verify keypad operations associated with Specialty Modes (Fluids & Lap)
Result: PASS
Task: Check operation of BIPOLAR footswitch control
Result: PASS
Task: Connect forceps or jumper lead to front-panel Bipolar receptacle. Check
activation of Bipolar output.
Result: PASS
Task: Confirm Single and Dual Dispersive Electrode Status/Alarm indicators are
alternately flashing red
Result: PASS
Task: Check operation of dispersive receptical and single-pad indicator
Result: PASS
Task: Depress CUT treadle of monopolar footswitch.
Confirm yellow Cut Activation indicator lights up and cut activation sound is
heard.
Result: PASS
Task: Check operation of COAG footswitch control
Result: PASS
Task: Use hand-controlled accessory or test pencil to verify handswitch
operation of both monopolar receptacles
Result: PASS
Task: Disconnect dispersive electrode and confirm generator beeps three times
and Single and Dual Dispersive Electrode Status/Alarm indicators alternately
flash red
Result: PASS
REM (CQM) TEST…
Resistance Limit(s) REM Test
(ohms) (ohms) Alarm Result
158 158+/-0 ON PASS
140 140+/-0 OFF PASS
15 15+/-0 OFF PASS
7 7+/-0 OFF PASS
HF OUTPUT TEST: Load=300 ohms Result: PASS
ESU settings: Bipolar MACRO, 10W
Power (watts): 10.0, limit=7.0-13.0
Current (mA): 183.5, limit=153.0-208.0
Voltages (V): Vrms=54.8, Vpk=96.6, Vp-p=173.4; CF=1.76
HF OUTPUT TEST: Load=300 ohms Result: PASS
ESU settings: Bipolar MACRO, 20W
Power (watts): 19.9, limit=17.0-23.0
Current (mA): 258.4, limit=238.0-277.0
Voltages (V): Vrms=77.1, Vpk=135.1, Vp-p=243.6; CF=1.75
HF OUTPUT TEST: Load=300 ohms Result: PASS
ESU settings: Bipolar MACRO, 90W
Power (watts): 89.0, limit=81.1-98.8
Current (mA): 546.1, limit=520.0-574.0
Voltages (V): Vrms=163.0, Vpk=281.0, Vp-p=512.5; CF=1.72
HF OUTPUT TEST: Load=50 ohms Result: PASS
ESU settings: Bipolar MICRO, 10W
Power (watts): 10.4, limit=7.0-13.0
Current (mA): 457.3, limit=374.0-510.0
Voltages (V): Vrms=22.7, Vpk=39.1, Vp-p=73.3; CF=1.72
HF OUTPUT TEST: Load=50 ohms Result: PASS
ESU settings: Bipolar MICRO, 25W
Power (watts): 25.7, limit=22.0-28.0
Current (mA): 718.6, limit=663.0-748.0
Voltages (V): Vrms=35.7, Vpk=60.4, Vp-p=114.6; CF=1.69
HF OUTPUT TEST: Load=50 ohms Result: PASS
ESU settings: Bipolar MICRO, 50W
Power (watts): 51.1, limit=45.0-55.0
Current (mA): 1013.7, limit=949.0-1049.0
Voltages (V): Vrms=50.4, Vpk=83.0, Vp-p=159.4; CF=1.65
HF LEAKAGE: Isolated active lead Result: PASS
ESU load: None
Conditions: Bipolar R, MACRO 90W
Leakage: 40.7 mA
Limit: 67.0 mA
HF LEAKAGE: Isolated active lead Result: PASS
ESU load: None
Conditions: Bipolar L, MACRO 90W
Leakage: 38.1 mA
Limit: 67.0 mA
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PURE CUT, 10W
Power (watts): 11.1, limit=7.0-13.0
Current (mA): 149.7, limit=118.0-161.0
Voltages (V): Vrms=74.4, Vpk=108.0, Vp-p=213.6; CF=1.45
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PURE CUT, 20W
Power (watts): 21.6, limit=16.9-23.8
Current (mA): 208.4, limit=184.0-218.0
Voltages (V): Vrms=103.7, Vpk=150.0, Vp-p=296.6; CF=1.45
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PURE CUT, 50W
Power (watts): 52.3, limit=45.0-55.1
Current (mA): 324.4, limit=300.0-332.0
Voltages (V): Vrms=161.3, Vpk=232.5, Vp-p=460.3; CF=1.44
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PURE CUT, 100W
Power (watts): 103.1, limit=89.9-110.0
Current (mA): 455.2, limit=424.0-469.0
Voltages (V): Vrms=226.4, Vpk=328.4, Vp-p=649.9; CF=1.45
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PURE CUT, 200W
Power (watts): 204.1, limit=180.0-219.8
Current (mA): 640.6, limit=600.0-663.0
Voltages (V): Vrms=318.6, Vpk=462.3, Vp-p=915.0; CF=1.45
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PURE CUT, 300W
Power (watts): 305.2, limit=270.1-329.7
Current (mA): 783.4, limit=735.0-812.0
Voltages (V): Vrms=389.6, Vpk=568.4, Vp-p=1123.1; CF=1.46
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 1, 10W
Power (watts): 11.4, limit=7.0-13.0
Current (mA): 151.2, limit=118.0-161.0
Voltages (V): Vrms=75.2, Vpk=133.1, Vp-p=265.4; CF=1.77
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 1, 20W
Power (watts): 21.8, limit=16.9-23.8
Current (mA): 209.5, limit=184.0-218.0
Voltages (V): Vrms=104.2, Vpk=185.0, Vp-p=369.2; CF=1.78
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 1, 50W
Power (watts): 52.9, limit=45.0-55.1
Current (mA): 326.1, limit=300.0-332.0
Voltages (V): Vrms=162.2, Vpk=287.5, Vp-p=574.5; CF=1.77
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 1, 100W
Power (watts): 103.9, limit=89.9-110.0
Current (mA): 457.0, limit=424.0-469.0
Voltages (V): Vrms=227.3, Vpk=401.9, Vp-p=803.7; CF=1.77
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 1, 200W
Power (watts): 205.3, limit=180.0-219.8
Current (mA): 642.5, limit=600.0-663.0
Voltages (V): Vrms=319.5, Vpk=564.8, Vp-p=1128.9; CF=1.77
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 2, 10W
Power (watts): 11.1, limit=7.0-13.0
Current (mA): 149.6, limit=118.0-161.0
Voltages (V): Vrms=74.4, Vpk=166.4, Vp-p=329.8; CF=2.24
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 2, 20W
Power (watts): 21.5, limit=16.9-23.8
Current (mA): 207.9, limit=184.0-218.0
Voltages (V): Vrms=103.4, Vpk=231.9, Vp-p=459.7; CF=2.24
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 2, 50W
Power (watts): 52.2, limit=45.0-55.1
Current (mA): 323.8, limit=300.0-332.0
Voltages (V): Vrms=161.1, Vpk=358.3, Vp-p=712.5; CF=2.22
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 2, 100W
Power (watts): 102.9, limit=89.9-110.0
Current (mA): 454.8, limit=424.0-469.0
Voltages (V): Vrms=226.2, Vpk=501.2, Vp-p=998.9; CF=2.22
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 2, 200W
Power (watts): 204.3, limit=180.0-219.8
Current (mA): 640.9, limit=600.0-663.0
Voltages (V): Vrms=318.7, Vpk=689.0, Vp-p=1375.2; CF=2.16
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 3, 10W
Power (watts): 11.1, limit=7.0-13.0
Current (mA): 149.1, limit=118.0-161.0
Voltages (V): Vrms=74.2, Vpk=211.5, Vp-p=408.2; CF=2.85
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 3, 20W
Power (watts): 21.4, limit=16.9-23.8
Current (mA): 207.4, limit=184.0-218.0
Voltages (V): Vrms=103.2, Vpk=299.1, Vp-p=574.0; CF=2.90
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 3, 50W
Power (watts): 52.0, limit=45.0-55.1
Current (mA): 323.4, limit=300.0-332.0
Voltages (V): Vrms=160.8, Vpk=472.7, Vp-p=902.5; CF=2.94
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 3, 100W
Power (watts): 102.7, limit=89.9-110.0
Current (mA): 454.5, limit=424.0-469.0
Voltages (V): Vrms=226.0, Vpk=652.2, Vp-p=1245.9; CF=2.89
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar BLEND 3, 200W
Power (watts): 204.2, limit=180.0-219.8
Current (mA): 640.8, limit=600.0-663.0
Voltages (V): Vrms=318.7, Vpk=827.7, Vp-p=1651.1; CF=2.60
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar SPRAY coag, 10W
Power (watts): 11.3, limit=7.0-13.0
Current (mA): 150.9, limit=118.0-161.0
Voltages (V): Vrms=75.0, Vpk=811.8, Vp-p=1347.0; CF=10.82
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar SPRAY coag, 20W
Power (watts): 21.6, limit=16.9-23.8
Current (mA): 208.6, limit=184.0-218.0
Voltages (V): Vrms=103.8, Vpk=1016.9, Vp-p=1569.5; CF=9.80
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar SPRAY coag, 50W
Power (watts): 52.5, limit=45.0-55.1
Current (mA): 325.0, limit=300.0-332.0
Voltages (V): Vrms=161.6, Vpk=1363.6, Vp-p=2103.2; CF=8.44
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar SPRAY coag, 80W
Power (watts): 84.4, limit=71.8-88.2
Current (mA): 411.8, limit=379.0-420.0
Voltages (V): Vrms=204.8, Vpk=1516.8, Vp-p=2525.1; CF=7.40
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar STANDARD coag, 10W
Power (watts): 11.1, limit=7.0-13.0
Current (mA): 149.5, limit=118.0-161.0
Voltages (V): Vrms=74.4, Vpk=441.4, Vp-p=677.6; CF=5.93
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar STANDARD coag, 20W
Power (watts): 21.7, limit=16.9-23.8
Current (mA): 208.9, limit=184.0-218.0
Voltages (V): Vrms=103.9, Vpk=616.1, Vp-p=951.2; CF=5.93
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar STANDARD coag, 50W
Power (watts): 53.1, limit=45.0-55.1
Current (mA): 326.6, limit=300.0-332.0
Voltages (V): Vrms=162.4, Vpk=930.3, Vp-p=1449.6; CF=5.73
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar STANDARD coag, 100W
Power (watts): 105.2, limit=89.9-110.0
Current (mA): 459.9, limit=424.0-469.0
Voltages (V): Vrms=228.8, Vpk=1308.0, Vp-p=2036.0; CF=5.72
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar STANDARD coag, 120W
Power (watts): 126.0, limit=108.1-132.1
Current (mA): 503.4, limit=465.0-514.0
Voltages (V): Vrms=250.4, Vpk=1430.8, Vp-p=2229.6; CF=5.71
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PINPOINT coag, 10W
Power (watts): 11.5, limit=7.0-13.0
Current (mA): 151.9, limit=118.0-161.0
Voltages (V): Vrms=75.5, Vpk=340.7, Vp-p=585.6; CF=4.51
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PINPOINT coag, 20W
Power (watts): 22.2, limit=16.9-23.8
Current (mA): 211.1, limit=184.0-218.0
Voltages (V): Vrms=105.0, Vpk=465.9, Vp-p=812.9; CF=4.44
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PINPOINT coag, 50W
Power (watts): 53.9, limit=45.0-55.1
Current (mA): 329.0, limit=300.0-332.0
Voltages (V): Vrms=163.7, Vpk=699.9, Vp-p=1266.1; CF=4.28
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PINPOINT coag, 100W
Power (watts): 106.2, limit=89.9-110.0
Current (mA): 462.2, limit=424.0-469.0
Voltages (V): Vrms=229.9, Vpk=955.5, Vp-p=1760.9; CF=4.16
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Monopolar PINPOINT coag, 120W
Power (watts): 127.5, limit=108.1-132.1
Current (mA): 506.4, limit=465.0-514.0
Voltages (V): Vrms=251.9, Vpk=1027.1, Vp-p=1927.0; CF=4.08
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Mono PULSED STANDARD coag, 10W
Power (watts): 10.6, limit=7.0-13.0
Current (mA): 146.2, limit=118.0-161.0
Voltages (V): Vrms=72.7, Vpk=612.5, Vp-p=944.7; CF=8.42
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Mono PULSED STANDARD coag, 20W
Power (watts): 20.9, limit=16.9-23.8
Current (mA): 205.1, limit=184.0-218.0
Voltages (V): Vrms=102.0, Vpk=840.0, Vp-p=1308.0; CF=8.23
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Mono PULSED STANDARD coag, 60W
Power (watts): 62.1, limit=54.1-65.9
Current (mA): 353.4, limit=329.0-363.0
Voltages (V): Vrms=175.8, Vpk=1443.8, Vp-p=2252.0; CF=8.21
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Mono PULSED SPRAY coag, 10W
Power (watts): 10.7, limit=7.0-13.0
Current (mA): 146.5, limit=118.0-161.0
Voltages (V): Vrms=72.9, Vpk=1025.6, Vp-p=1581.7; CF=14.08
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Mono PULSED SPRAY coag, 20W
Power (watts): 20.6, limit=16.9-23.8
Current (mA): 203.5, limit=184.0-218.0
Voltages (V): Vrms=101.2, Vpk=1253.8, Vp-p=1901.7; CF=12.39
HF OUTPUT TEST: Load=500 ohms Result: PASS
ESU settings: Mono PULSED SPRAY coag, 40W
Power (watts): 41.1, limit=35.9-44.1
Current (mA): 287.5, limit=268.0-297.0
Voltages (V): Vrms=143.0, Vpk=1518.2, Vp-p=2523.6; CF=10.62
HF LEAKAGE: Isolated neutral lead Result: PASS
ESU load: None
Conditions: RETURN; Foot ctl; Std COAG 120W
Leakage: 66.5 mA
Limit: 100.0 mA
HF LEAKAGE: Isolated neutral lead Result: PASS
ESU load: None
Conditions: RETURN; Foot ctl; Pure CUT 300W
Leakage: 73.5 mA
Limit: 100.0 mA
HF LEAKAGE: Isolated neutral lead Result: PASS
ESU load: None
Conditions: DISPERSIVE; L.Hand ctl; Std COAG 120W
Leakage: 88.3 mA
Limit: 100.0 mA
HF LEAKAGE: Isolated neutral lead Result: PASS
ESU load: None
Conditions: DISPERSIVE; R.Hand ctl; Std COAG 120W
Leakage: 88.1 mA
Limit: 100.0 mA
HF LEAKAGE: Isolated active lead Result: PASS
ESU load: None
Conditions: R.HAND OUTP; R.Hand ctl; Std COAG 120W
Leakage: 70.7 mA
Limit: 100.0 mA
HF LEAKAGE: Isolated active lead Result: PASS
ESU load: None
Conditions: L.HAND OUTP; L.Hand ctl; Std COAG 120W
Leakage: 70.1 mA
Limit: 100.0 mA
HF LEAKAGE: Isolated active lead Result: PASS
ESU load: None
Conditions: FS OUTPUT; Foot ctl; Std COAG 120W
Leakage: 68.4 mA
Limit: 100.0 mA
HF LEAKAGE: Cross-coupling test Result: PASS
ESU load: 200 ohms
Conditions: BIPOLAR to FS OUTPUT; MACRO 90W
Leakage: 0.0 mA
Limit: 20.0 mA
HF LEAKAGE: Cross-coupling test Result: PASS
ESU load: 200 ohms
Conditions: BIPOLAR to L.HAND; MACRO 90W
Leakage: 0.0 mA
Limit: 20.0 mA
HF LEAKAGE: Cross-coupling test Result: PASS
ESU load: 200 ohms
Conditions: BIPOLAR to R.HAND; MACRO 90W
Leakage: 1.4 mA
Limit: 40.0 mA
HF LEAKAGE: Cross-coupling test Result: PASS
ESU load: 200 ohms
Conditions: L.HAND to FS OUTPUT; Std COAG 120W
Leakage: 11.1 mA
Limit: 50.0 mA
HF LEAKAGE: Cross-coupling test Result: PASS
ESU load: 200 ohms
Conditions: R.HAND to FS OUTPUT; Std COAG 120W
Leakage: 10.4 mA
Limit: 50.0 mA
HF LEAKAGE: Cross-coupling test Result: PASS
ESU load: 200 ohms
Conditions: R.HAND to L.HAND; Std COAG 120W
Leakage: 13.5 mA
Limit: 50.0 mA
HF LEAKAGE: Cross-coupling test Result: PASS
ESU load: 200 ohms
Conditions: R.HAND to L.BIP.; Std COAG 120W
Leakage: 32.1 mA
Limit: 48.0 mA
HF LEAKAGE: Cross-coupling test Result: PASS
ESU load: 200 ohms
Conditions: R.HAND to L+R.BIP.; Std COAG 120W
Leakage: 1.5 mA
Limit: 48.0 mA
END OF RECORD