Village Greens Play System Installation Guide
- May 15, 2024
- Village Greens
Table of Contents
- Inground Post/Mount Installation
- Square Deck Installation
- Right Triangle Deck Installation
- 3.5-inch Clamp Installation Guide
- 36” Transfer Station (for 3.5” post) Install
- 3.5-inch 2-Clamp Arch Rail Installation
- 3.5-inch 4-Clamp Arch Rail Installation
- 3.5-inch Metal Barrier Installation
- 3-foot Right Turn Slide Installation
- 4-foot Single Wave Slide Installation
- 4-foot Vertical Ladder Installation
- Figure Climber Installation
- Leaf Roof Installation
- Ships Wheel Installation
- Read User Manual Online (PDF format)
- Download This Manual (PDF format)
Inground Post/Mount Installation
STEP: 1
DO NOT CEMENT POSTS/MOUNTS INTO PLACE UNTIL THE ENTIRE STRUCTURE IS ASSEMBLED.
Refer to the General Installation guide footing size information and digging proper holes for the support posts/mounts.
Created By: Gage Brown
Date: 04/26/2018
Square Deck Installation
STEP: 1
After the posts are in place, using four (4) M10*35 bolts, eight (8) M10 washers, and four (4) M10 lock nuts, attach each square deck to each pre- attached deck clamp as shown in the image.
Deck clamps are pre-attached to the posts and should not be altered in any way.
Created By: Aaron Price
Date: 3/19/2018
Right Triangle Deck Installation
STEP: 1
After the posts are in place, using three (3) M10*35 bolts, six (6) M10 washers, and three (3) M10 lock nuts, attach the triangle deck to each pre- attached deck clamp as shown in the image.
Deck clamps are pre-attached to the posts and should not be altered in any way.
Created By: Aaron Price
Date: 03/20/2018
3.5-inch Clamp Installation Guide
3.5-inch Flat Clamp
Connect half of the flat clamp to the component using one (1) M8*40 bolt. Then, using the other half of the flat clamp and the hardware provided in the clamp hardware bag, attach the other half of the tube clamp around the post.
3.5-inch Tube Clamp
Connect half of the clamp to the component using one (1) M8*30 bolt. Then, using the other half of the tube clamp and the hardware provided in the clamp hardware bag, attach the other half of the tube clamp around the post.
3.5-inch 90-Degree Flat Clamp
Connect half of the flat clamp to one panel using one (1) M8*40 bolt.
Then, using the other half of the flat clamp and the hardware provided in the
clamp hardware bag, attach the other half of the tube clamp around the post.
Then, attach the next panel to the other side of the clamp using the same
process.
3.5-inch Double Slide Clamp
Connect half of the double slide clamp to the double slide hood using one (1) M8*30 bolt. Then, using the other half of the clamp and the hardware provided in the clamp hardware bag, attach the other half of the tube clamp around the post.
Created By: Aaron Price
Date: 03/28/2018
36” Transfer Station (for 3.5” post) Install
STEP: 1
Connect half of the 3.5-inch tube clamp to the handrail using one (1) M8*30 bolt. Set the handrail into place, then attach the second half of the clamp using the hardware provided in the clamp bag. Repeat this process for the other handrail.
STEP: 2
Using three (3) M10*25 bolts, six (6) M10 washers, and three (3) M10 lock nuts, attach the top of the stairs to the square deck.
STEP: 3
Using four (4) M10*25 bolts, eight (8) M10 washers, and four (4) M10 lock nuts, connect the bottom of the handrails to the bottom of the 3-foot transfer stair.
STEP: 4
Using two (2) M10*25 bolts, four (4) M10 washers, two (2) lock nuts, attach the handrail to the square deck.
STEP: 5
Using three (3) M10*25 bolts, six (6) M10 washers, and three (3) M10 lock nuts, attach the ADA transfer deck to the base of the 3-foot ADA transfer stair.
STEP: 6
See general installation guide regarding footing information for the transfer
deck handrail & mount.
Using two (2) M10*65 bolts, four (4) M10 washers, and two (2) M10 lock nuts,
attach the transfer handrail to the ADA transfer deck.
STEP: 7
Using two (2) M10*25 bolts, four (4) M10 washers, and two (2) lock nuts, attach the transfer deck mount to the ADA transfer deck.
STEP: 8
See general installation guide regarding footing information for the ADA transfer step mount. Using two (2) M10 bolts, four (4) M10 washers, and two (2) M10 lock nuts, attach the transfer step to each ADA transfer step mount.
STEP: 9
Using three (3) M10*25 bolts, six (6) M10 washers, and three (3) M10 washers, attach the top of the ADA transfer step to the ADA transfer deck.
Created By: Aaron Price
Date Modified: 3/13/18
3.5-inch 2-Clamp Arch Rail Installation
STEP: 1
Attach the Arch Rail to the designated posts by connect half of the tube clamp to the arch rail using one (1) M830 bolt. Repeat this process for each post attachment point. Then, attach the rail to the deck using two (2) M1025 bolts, four (4) M10 washers, and two (2) M10 lock nuts. Finally, attach the second half of the clamp around the post.
Created By: Aaron Price
Date: 04/04/2018
3.5-inch 4-Clamp Arch Rail Installation
STEP: 1
Attach the Arch Rail to the designated posts by connect half of the tube clamp
to the arch rail using one (1) M8*30 bolt. Repeat this process for each
attachment point.
Set the arch rail into place, then attach the second half of the clamp around
the post. The gap between the deck and the bottom of the rail should be no
more than 3 inches.
Created By: Aaron Price
Date: 03/20/2018
3.5-inch Metal Barrier Installation
STEP: 1
Attach the metal barrier to the designated posts using two (2) tube clamps two (2) M830 bolts. Then, attach the bottom of the metal barrier to the deck using two (2) M1025 bolts, four (4) M10 washers, and two (2) M10 lock nuts.
Created By: Aaron Price
Date: 04/05/2018
3-foot Right Turn Slide Installation
STEP: 1
Take one (1) 3.5-inch flat clamp, and loosely attach it around a post using the bolts and nuts provided in the clamp hardware bag. Repeat this process on the other post. Then, use one (1) M8*40 bolt, one (1) M8 washer, and one (1) M8 lock nut to attach each side of the slide hood to each clamp. Leave bolts loose until slide is in place.
STEP: 2
See general installation guide regarding footing information for the slide end
mount. Using two (2) M8*20, two (M8) spring washers.
And two (2) M8 washers, attach the slide to the slide support post.
STEP: 3
See general installation guide regarding footing information for the middle slide support. Using two (2) M8*20 bolts, two (2) M8 spring washers, and two (2) M8 washers, attach the middle slide support post.
STEP: 4
Using one (1) M10*45 bolt, two (2) M10 washers, and two (2) M10 lock nuts, attach one side of the slide to the deck.
STEP: 5
Using one (1) M8*45 bolt, one (1) M8 washer, one (1) M12 washer, and one (1) M12 inner hex spiral nut, attach the slide to one side of the slide hood. Repeat this process for the other side of the slide.
Created By: Aaron Price
Date: 03/19/2018
4-foot Single Wave Slide Installation
STEP: 1
Take one (1) 3.5-inch flat clamp, and loosely attach it around a post using the bolts and nuts provided in the clamp hardware bag. Repeat this process on the other post. Then, use one (1) M8*40 bolt, one (1) M8 washer, and one (1) M8 lock nut to attach each side of the slide hood to each clamp. Leave bolts loose until slide is in place.
STEP: 2
See general installation guide regarding footing information for the slide end mount. Using two (2) M8*20, two (M8) spring gaskets. And two (2) M8 washers, attach the slide to the slide support post.
STEP: 3
Using one (1) M10*45 bolt, two (2) M10 washers, and two (2) M10 lock nuts, attach one side of the slide to the deck.
STEP: 4
Using one (1) M8*45 bolt, one (1) M8 washer, one (1) M12 washer, and one (1) M12 inner hex spiral nut, attach the slide to one side of the slide hood. Repeat this process for the other side of the slide.
Created By: Aaron Price
Date: 03/19/2018
4-foot Vertical Ladder Installation
STEP: 1
See general installation guide regarding footing information for the 4-foot Vertical Ladder. Attach the ladder to the deck using two (2) M10*25 bolts, two (2) M10 spring washers, and two (2) M10 washers.
Created By: Aaron Price
Date: 03/20/2018
Figure Climber Installation
STEP: 1
See general installation guide regarding footing information for the figure climber. Using two (2) M10*20 bolts, two (2) M10 spring gaskets, and two (2) M10 washers, attach the bottom of the figure climber to the climber end mounts.
STEP: 2
Using four (4) M10*20 bolts, four (4) M10 spring gaskets, and four (4) M10 washers, attach the figure climber to the square deck.
Created By: Aaron Price
Date: 03/22/2018
Leaf Roof Installation
STEP: 1
Set the leaf roof on top of the posts.
Take four (4) self-tapping screws and drill them through the notch at each
corner of the roof, into the support posts.
Created By: Aaron Price
Date: 03/19/2018
Ships Wheel Installation
STEP: 1
Detach half of the tube clamp connected to the Ships Wheel, and re-attach the clamp around the support post, as shown in the picture. Recommended install height is 20 to 36 inches above surfacing depending on age range.
Created By: Aaron Price
Date: 03/20/2018
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>