LG RBA008K0A00 Energy Storage System Instruction Manual
- June 15, 2024
- LG
Table of Contents
LG RBA008K0A00 Energy Storage System
Product Information
Specifications
- Model: LG ESS Home 8 (RBA008K0A00)
- Components: PCS (RA768K00A10), Battery Module (BPLG004HBG1), SE Box (REA200AP0)
- Proprietary Data Notice: This document and all related materials are the property of LG Electronics U.S.A., Inc.
Product Usage Instructions
Getting Started
Please follow the instructions below to ensure safe and proper installation of the Energy Storage System (ESS).
Important Safety Instructions
It is crucial to adhere to the following safety instructions to prevent harm or damage:
- Do not open the door. Only trained service providers should perform any servicing.
- After disconnecting all sources, wait for at least 10 minutes before removing the door to avoid electric shock from stored energy in the capacitor.
- When the product cover is removed, do not touch uninsulated wires to avoid electric shock.
- Do not attempt to disconnect, disassemble, or repair the product on your own to avoid injuries, electric shock, or burns.
- The ESS contains high voltages that can cause electric shock or serious burns. Exercise caution.
- The AC cables carry high voltage, which can be fatal if mishandled.
- Failure to follow precautions may result in fire, high voltages, or explosion leading to death or serious injury.
- Avoid placing flammable or potentially explosive objects near the product or in explosive atmospheres.
- Charge and discharge the ESS only as directed to prevent faults, electric shock, or burns.
- Avoid damaging the unit through dropping, deforming, impacting, cutting, or spearing with sharp objects. Such damage may cause electrolyte leakage or fire.
- Breakdown of the unit can result in electrolyte leakage or flammable gas generation.
- In case of electrolyte leakage, avoid contact with eyes, skin, or clothes.
FAQs
Q: Can I perform service or repairs on the Energy Storage System myself?
A: No, all servicing should be performed by trained service providers. Opening the door or attempting repairs can be dangerous and may result in electric shock or other injuries.
Q: Are the AC cables safe to touch?
A: No, the AC cables carry high voltage and pose a risk of electric shock. Do not touch them when the product cover is removed.
Q: What should I do if electrolytes leak from the unit?
A: In case of electrolyte leakage, avoid contact with eyes, skin, or clothes. Take appropriate precautions and seek medical attention if necessary.
INSTALLATION MANUAL
Energy Storage System
Please read this manual carefully before operating and retain it for future
reference.
Model LG ESS Home 8 (RBA008K0A00)
Home 8 (RA768K16A11) Smart Energy Box (REA200AP0)
MFL71893101
Rev.E 16/08/2023
http://www.lg.com/us/ess Copyright © 2022 – 2023 LGEUS All Rights Reserved.
Due to our policy of continuous product innovation, some specifications may change without notice. ©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
PROPRIETARY DATA NOTICE
This document, as well as all reports, illustrations, data, information, and
other materials, are the property of LG Electronics U.S.A., Inc., and are
disclosed by LG Electronics U.S.A., Inc. only in confidence.
Do not throw away, destroy, or lose this manual.
Please read carefully and store in a safe place for future reference. Content
familiarity is required for proper installation.
The instructions included in this manual must be followed to prevent product
malfunction, property damage, injury, or death to the user or other people.
Incorrect operation due to ignoring any instructions will cause harm or
damage. The level of seriousness is described by the summary list of Important
Safety Instruction.
For continual product development, LG Electronics U.S.A., Inc. reserves the right to change specifications without notice. © LG Electronics U.S.A., Inc.
2
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Important Safety Instructions
IMPORTANT: This product should not be used for any purpose other than the
purpose described in this installation manual. SAVE THESE INSTRUCTIONS : This
manual contains important instructions for LG ESS Home 8 (RBA008K0A00)
consisting of PCS (RA768K00A10), Battery Module (BPLG004HBG1), and SE Box
(REA200AP0) that shall be followed during the installation and maintenance of
Energy Storage System (ESS).
The LG ESS Home 8 has been designed and tested to meet applicable North
America and International safety standards. As with any electrical and
electronic devices, safety precautions must be observed during the
installation and operation of the LG ESS Home 8 to reduce the risk of personal
injury and to ensure safe installation. Installation, commissioning, service,
and maintenance of the LG ESS Home 8 must be performed only by trained service
providers who are licensed and/or who meet the applicable state, local
jurisdiction regulations, follow the instructions in this manual, and using
personal protective equipment (PPE). All transport or handling of the LG ESS
Home 8 product must be done in accordance with local safety standards. Before
starting the installation or commissioning of the LG ESS Home 8, read through
the entire manual and take note of all precautions. All U.S. and Canada
electrical installations must be done in accordance with local codes and the
National Electric Code (NEC) ANSI/NFPA 70 or the Canadian Electrical Code CSA
C22.1. In Canada, the installation and wiring methods used must comply with
parts I and II of the Canadian Electric Code, and local AHJ inspector
requirements. When required by Part 1 of the Canadian Electrical Code, system
grounding is the responsibility of the installer.
LG ESS system is not intended for use as a primary or backup power source for
life-support systems, other medical equipment, or any other use where product
failure could lead to injury to persons or loss of life or catastrophic
property damage. LG disclaims any and all liability arising out of any such
use of the system. Further, LG reserves the right to refuse to service any
system used for these purposes and disclaims any and all liability arising out
of LG’s service or refusal to service systems in such circumstances.
Due to our policy of continuous product innovation, some specifications may change without notice.
3
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Indicates a hazardous situation that will result
DANGER in death or serious injury if the instruction is not followed.
y Do not open the door. There are no user serviceable parts inside. Service
may be performed only by trained service provider.
y Risk of electric shock from energy stored in capacitor. Do not remove the
door until 10 minutes after disconnecting all sources when service needed.
y Electric shock hazard. Do not touch uninsulated wires when the product cover
is removed. y Do not disconnect, disassemble, or repair to avoid injuries,
electric shock or burns. y There is a high possibility of electric shock or
serious burns due to the high voltages in
the ESS. y The AC cables are high voltage. Risk of death or serious injury due
to electric shock. y This product poses potential danger such as death or
serious injury by fire, high voltages,
or explosion if appropriate precautions are not read, fully understood, and
followed. y Do not place or install flammable or potentially explosive objects
near the product or in
explosive atmospheres. y Do not charge or discharge arbitrarily. It may lead
to fault, electric shock, or burns. y Do not damage the unit in any manner,
such as by dropping, deforming, impacting,
cutting, or spearing with a sharp object. It may cause electrolyte leakage or
fire. y Breakdown of the unit may cause electrolyte leakage or flammable gas
generation. y If electrolytes leak, avoid contact with eyes, skin, or clothes.
In event of accidental contact,
flush with water and seek medical help immediately. y Do not place near open
flame or incinerate. It may lead to fire or explosion. y Keep the unit away
from moisture or liquid. Do not touch or use the product if liquids
have been spilled on it. y Keep out of reach of children or animals. y
Electrical installations must be done in accordance with local standards,
national electrical
safety standards, and the manufacturer’s instructions. y The battery system is
a bidirectional source of voltage. The battery circuit breaker and
inverter must both be off before working in the wiring box. y Disconnect each
circuit individually before servicing. Both AC and DC voltage sources are
terminated inside this equipment. y Do not dispose of batteries in a fire. The
batteries may explode. y Do not open or assemble while product is working.
4
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
WARNING
Indicates a potentially dangerous situation. Death or serious injury may result if appropriate precautions are not taken.
y A potentially hazardous circumstance such as excessive heat or electrolyte
mist may occur due to improper operating conditions, damage, misuse and/or
abuse.
y The contents included in this box are the ESS and its accessories. The total
weight is very heavy. Serious injury may occur due to the weight of the
package containing the ESS and accessories. Therefore, special care must be
taken in handling. Make sure to use the handle lift to deliver and install the
package.
y Do not open or damage batteries. Released electrolyte is harmful to the skin
and eyes. It may be toxic.
y Do not place heavy objects on this product. It may cause deformation or
fracture. y Do not place any kind of objects on top of the product during
operation. y All work on the ESS must be carried out by trained service
providers only. y Electrical installations must be done in accordance with the
local and national electrical
safety standards.
y Wear rubber gloves and protective clothing (including protective glasses and
boots) when working on the ESS.
y To reduce the risk of fire, do not connect to an AC load center (circuit
breaker panel) with multiwire branch circuits connected.
Due to our policy of continuous product innovation, some specifications may change without notice.
5
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
CAUTION Indicates a situation where damage or injury may occur. If it is not
avoided, minor injury and/ or damage to property may result.
y Before testing electrical parts inside the system, there is a minimum of a
10 minute standby period to completely discharge the system.
y Do not use any damaged, cracked, or frayed electrical cables or connectors.
Protect the electrical cables from physical or mechanical abuse, such as being
twisted, kinked, pinched, closed in a door, or stepped on. Periodically
examine the electrical cables of your product. If the appearance indicates
damage or deterioration, discontinue use of this product and have the cables
replaced with an exact replacement part by a qualified personnel.
y Ensure that you connect the earth ground wire to prevent possible electric
shock. Do not try to ground the product by connecting it to telephone wires,
lightning rods, or gas pipes.
y Do not put the product or components in water or liquid. y Make sure that
there are no water sources, such as faucets or sprinklers, near the
installation site. y Do not block any ventilation openings. Ensure reliable
operation of the product and
protect it from overheating. Do not block any openings by placing objects on
this product. y The metal enclosure may heat to a high temperature during
operation. y The product must be disposed of according to local regulations. y
If the ESS is not operated for a long time, the battery may be overdischarged.
y Do not step on the product or the product package. The product may be
damaged. y Batteries may present a risk of electrical shock and high short-
circuit current. The
following precautions should be observed when working on the ESS system
include:
a) Remove watches, rings, and other metal objects.
b) Use tools with insulated handles.
c) Wear rubber gloves, boots, and glasses.
d) Do not lay tools or metal parts on top of the system. y In the event of
fault, the system must not be restarted. Product maintenance and repairs
must be performed by trained service providers. y If a system fault occurs
immediately after starting the system, check the error code on
the Smart Energy Box (SE Box) display and follow the solution described in the
manual.
6
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
INFO Indicates a risk of possible damage to the product.
y This product is intended for residential use only and is not intended for
use in industrial Purposes.
y The System consists of Home 8 and SE Box. They must be installed together
and it will not work when installing unauthorized components to the system.
y The unit is designed to feed power to the public grid only. Do not connect
the unit to a generator as connecting the power to external devices could
result in serious damage to the equipment.
y LG ESS Home 8 performs best when it is connected to the internet and
registered through the ThinQ service, so that the firmware may be remotely
updated periodically.
y For the latest ESS documents, visit: – Warranty :
https://www.lg.com/us/ess/warranty – Installation Manual :
https://www.lg.com/us/ess/Installationmanual – User Manual :
https://www.lg.com/us/ess/usermanual – Quick Installation Guide :
https://www.lg.com/us/ess/quickstart
y If the S/W version is not up to date during installation, update the S/W
using a FAT32 formatted USB storage device. When the SE Box is connected to
Ethernet through a LAN cable after normal operation, it is automatically
updated to the latest S/W version.
y Handling of batteries should be performed or supervised by a trained service
provider. y The battery does not discharge when the load is under a certain
level. y To prevent network problems, check the “Network Settings” before
installation. y Do not store or place any objects on top of or against the
unit. It may cause serious
malfunction or other problems. y Never use any solvents, abrasives, or
corrosive materials to clean this unit. y Under backup operation, whether the
battery SoC is higher than 90% or the ESS needs
to reduce the charging power, the ESS may reduce the solar power generation. y
If the battery SoC is too low during backup operation during a power outage,
the system
operates as follows.
– Even though the PV system is equipped, the system will not supply power to
the home load. However, the system can charge the battery from the PV system
first and then supply power to the home again if the battery SoC is
sufficiently charged.
– If the PV system is not equipped, the system cannot supply power to the home
load and the system will go into sleep mode.
Due to our policy of continuous product innovation, some specifications may change without notice.
7
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
First Aid Measures
The Product includes internal fault mechanisms designed to prevent failures
and subsequent risk hazards. However, LG Electronics cannot guarantee the safe
performance of the Product if it is ever exposed to abuse, damage, or
negligence. If a user happens to be exposed to the internal materials of the
battery cell due to damage on the outer casing, the following actions are
recommended. – In case of inhalation: Leave the contaminated area immediately
and seek medical attention. – In case of contact with eyes: Rinse eyes with
running water for 15 minutes and seek medical
attention. – In case of contact with skin: Wash the contacted area with soap
thoroughly and seek medical
attention. – In case of ingestion: Induce vomiting and seek medical attention.
Fire Fighting Measures
Suitable extinguishing media Use metal fire extinguishing powder or dry sand
if only a few cells are involved. In case of a large fire, use a large amount
of water to extinguish. Special hazards arising from the chemical May form
hydrofluoric acid if electrolyte comes into contact with water. In case of
fire, the formation of the following flue gases cannot be excluded: Hydrogen
fluoride (HF), Carbon monoxide, and carbon dioxide. Protective equipment and
precautions for firefighters If batteries are charging, shut off power. Wear a
self-contained breathing apparatus and protective suit.
WARNING
If heated above 130 °C (266 °F), there is a risk of fire, explosion, physical
injury, or death.
Effective way to deal with accidents
– On land : Do not touch the damaged battery and call your local fire
department or service engineer. – In water : Stay out of the water and do not
touch anything if any part of the ESS or wiring is
submerged. – Do not use the submerged battery again. Contact your service
engineer for assistance.
8
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
This product is an All In One Energy Storage System (ESS) designed with a
grid-connected inverter and integrated battery. Also, it is possible to supply
power in case of a power outage through the Smart Energy Box (SE Box). The
built-in PMS (Power Management System) in SE Box provides the optimal
charging/discharging operation by monitoring the home power usage status, PV
power generation, grid power status, consumer electricity plan, and weather
forecast. ATS function can be enabled for backup power in the built-in PMS,
which can provide automatic seamless transfer switching.
(In order to use all functions smoothly, users must connect this product to
the Internet and subscribe to the LG ThinQ® service.)
LG ThinQ
PV Module
Mobile Phone
PV inverter1) (optional)
LED Lighting
Air Conditioning
SE Box
Grid (Utility)
Utility Meter
Direct Current Alternative Current Data Line
Home 8
Refrigerator
TV
HVAC
Heater
Oven
Washing Machine
Electric Vehicles
- PV inverter is NOT PROVIDED by LG Electronics.
y All In One ESS LG ESS Home 8 is a product designed to integrate a grid- connected inverter and battery in one enclosure. This product is an AC-Coupled type and is directly connected to the household power grid.
y Single-phase Three-wire Connection (Split Phase Only) This product is for use exclusively for single-phase three-wire electric power grids used in the home.
y Smart Management The built-in Smart PMS analyses PV generation, load consumption, electricity rate, and weather information. It also monitors the main system & battery conditions to maintain a stable condition. Internet connection and LG ThinQ® connection required.
Due to our policy of continuous product innovation, some specifications may change without notice.
11
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
y App & Web-Monitoring Service The home owner and installer can monitor their
ESS with various devices such as a PC, tablet, or smart phone.
y Backup Mode During a power outage, this system supplies emergency power to
the household loads. When the grid experienced an outage, SE Box can
automatically switch the power source from the utility grid to Home 8. For
these functions, “Backup” should be enabled in the system.
y System Scalability Up to 4 Home 8 units can be connected to one SE Box. (The
required number of Home 8 may vary depending on the electric service capacity,
the load consumption characteristic, and the preferred operation of the home.
Please contact an authorized dealer or the seller for more details.)
System configuration
Whole Home backup
PV inverter
SE Box
Utility Meter
Partial Home Backup
SE Box
Main Panel (Non-Backup)
PV inverter
Utility Meter
Home 8
Main Panel (Backup)
Home 8
Sub-panel (Backup)
Product Specifications
All specifications and descriptions contained in this document are verified to
be accurate at the time of printing. However, since continuous improvement is
a goal at LGEUS, we reserve the right to make product modifications at any
time.
The images provided in this document are for demonstration purposes only.
Depending on product version and market region, details may appear slightly
different.
©2022 LGEUS Inc. All rights reserved. Due to our policy of continuous product
innovation, some specifications may change without notification. ©LG
Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a
registered trademark of LG Corp.
12
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Symbol Used on Labels
Symbol
Description
E521851
UL approval Listing Mark UL approval Recognized
Risk of Electric Shock
This product should not be disposed of with other household waste. Disposal
regulations of the country should be observed.
Identifies any terminal intended for connection to an external conductor for
protection against electrical shock in case of a fault or the terminal of a
protective earth (ground) electrode.
Read the instruction manual/booklet before starting work or before operating
equipment or machinery.
Caution, risk of danger
Caution, hot surface
Caution, risk of electric shock, energy storage timed discharge Caution, risk of electric shock No open flame, open ignition source, or smoking Wear protective glasses when working on the battery unit. Install this product out of reach of children. Take care when handling corrosive substances. Take care when handling explosive materials. Serious injury may occur due to the heavy weight of the product.
Due to our policy of continuous product innovation, some specifications may change without notice.
13
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Symbol
Description
Observe precautions for handling electrostatic discharge sensitive devices.
Disconnect the machine or equipment before carrying out maintenance or repair.
Take care to avoid causing a fire by igniting flammable material.
Ensure adequate ventilation of the charging area and take care to avoid coming
in contact with acid. In case of contact with acid material, immediately flush
the area with plenty of water. Get medical attention immediately. Wash
contaminated clothing before reuse with sufficient water.
Fire extinguishers must be used to put out flames.
Ensure the conductive terminals are matched to their corresponding
counterparts.
Abbreviations in this Manual
Abbreviation ESS
Designation Energy Storage System
Explanation
Inverter system that stores energy in a battery and uses it.
Home 8 SE Box
PCS PMS
ATS PV SoC 14
All In One unit
Battery integrated PCS
Smart Energy Box
Micro-grid interface device that consist of an ATS (automatic transfer switch), energy meter, and Smart Controller.
Power Conditioning System
A device intended to convert AC/DC electricity to charge and discharge the battery.
Power Management System
A device to control the whole system, including the power management algorithm, and to communicate with the cloud server.
Automatic Transfer Switch
A device to separate the home micro grid from the utility grid.
Photovoltaic
A solar panel system that converts solar energy into direct current electricity.
State of Charge
The current charge level of a rechargeable battery relative to its capacity.
Due to our policy of continuous product innovation, some specifications may change without notice. ©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Abbreviation BCU
Designation Battery Control Unit
DC AC DHCP
Direct Current
Alternating Current
Dynamic Host Configuration Protocol
LAN
Local Area Network
IP
Internet Protocol
Getting Started
Explanation
An electronic system that control a rechargeable battery system for securing
battery safety.
–
–
Standardized network protocol used on Internet Protocol (IP) networks for
automatic distributing network configuration parameters, such as IP addresses
for interfaces and services.
A network that interconnects computers within a limited area.
A set of rules for sending data across a network.
Due to our policy of continuous product innovation, some specifications may change without notice.
15
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Unpacking
Unpacking the SE Box
Unpack the SE Box from its packaging.
WARNING
Take care when moving or installing the SE Box. It may cause injury due to the
weight. At least 2 people are needed for safe installation and moving.
Remove the package banding and open the box.
Take out all the accessories and components.
Pull out the SE Box from the package.
16
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Unpacking the Home 8
Unpack the Home 8 from its packaging.
WARNING
y When working on the Home 8, at least 3 people are needed for safe
installation and moving. y Make sure the lift does not move when standing the
product on the lift. y When moving the product using a lift, secure the
product using a belt, etc.
INFO
Be careful not to damage Home 8 when standing the product on the hand lift.
The cut-out part at the bottom of the box can be used to prevent scratches by
inserting it between the product and the hand lift.
Remove the package banding and open the box. Take out all the accessories and
components.
Cut the bottom of the box so that the hand lift can fit through the bottom.
WARNING
Be careful to avoid injury when cutting the bottom of the package.
Due to our policy of continuous product innovation, some specifications may change without notice.
17
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
INFO
If the installation location has excessive presence of insects, block the vent
hole with the Vent Plug, if needed.
Put the hand lift into the bottom of the package and stand the Home 8 upright
on the hand lift.
18
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Home 8 Contents
Getting Started
Home 8 (1EA)
Wall bracket (2EA)
Communication terminal block (2EA)
Vent plug
SE Box Contents
SE Box
Quick Installation Guide & Mount Hole Guide
200A CT for PV
CT harness
N-GND bonding busbar
O rings (4EA)
CT terminal block (2EA)
Due to our policy of continuous product innovation, some specifications may change without notice.
19
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Required Tools
Insulated gloves (Class 0: 1,000AC
/1500 DC-Red recommended)
Safety glasses
Protective footwear
Lift equipment (190 kg up to 1.5 m)
Drill and drill bit
Torque wrench with hex socket
M5 (1/4 inch), M6 (3/8 inch), M8 (5/16 inch)
Screw driver Phillips (5 mm) Flat head (6, 5, 4, 2
mm)
Hex wrench 6 mm (1/4 inch), 8 mm (5/16 inch)
Inclinometer
Tape measure
Writing utensil
Cutter
RJ 45 climping tool
Wire strippers (A)
Wire strippers (B)
Wire strippers (C)
Wire cutter (A)
Wire cutter (B)
Spanner
Ring terminal crimping
17 mm (21/32 inch)
tool (optional)
WARNING
The Home 8 and SE Box are heavy. Wear appropriate personal protective
equipment (such as gloves and protective footwear) when handling the these
units.
20
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Required Materials and Components
y SE Box mounting hardware and a Home 8 wall bracket y Conduit or raceway
(depending on local electrical requirements) y Conduit adapters.
– necessary for cable entry into Home 8 wiring compartment and the SE Box. –
For conduit adapters, use only UL Listed 3R type raintight or wet location
hubs for entry into the
enclosure. y Communication Cable (SE Box-Home 8)
– Minimum 300V rated 6-conductor Shielded Twisted Pair copper (Cu) cable (or
Double-insulated Shielded Twisted Pair copper (Cu) cable)
– CAT5 STP or CAT6 STP 24-16 AWG would be used (ULapproved Required) – Two
6-position terminal blocks for this communication cable are included in the
Home 8 package. y Communication Cable (RS485, STOP, AUX in the SE Box)
– Minimum 300V rated unshielded twisted pair cable. – CAT5 UTP or better y
Ethernet Cable (SE Box)
– Minimum 300V rated CAT5 UTP or better (If needed, RJ45 connectors should be
prepared) y Power and Grounding Cable for Home 8 connection
– Minimum 600 V rated copper (Cu) cable rated at 90 °C (194 °F) – 6-4 AWG
(BLACK/WHITE/RED) – 8-6 AWG (GREEN) – Follow NEC and local codes y Power and
Grounding Cable for SE Box connection
– Minimum 600 V rated copper (Cu) or aluminum (Al) cable rated at 90 °C (194
°F) or better. – 6 AWG – 250 kcmil (BLACK / WHITE / RED) – 14 AWG – 2/0 AWG
(BLACK / WHITE / RED / GREEN or Bare) – Follow all NEC and local codes y
Breakers, Lugs, and Accessories
– Follow all NEC and the local codes for breaker sizing. Please refer to
“Compatible Eaton Parts” . – Main Breaker : CSR2100, CSR2125N, CSR2150N,
CSR2175N, CSR2200N, BW2100, BW2125,
BW215N, BW2175 or BW2200 from Eaton – Branch Breaker for Home 8 and PV
inverter connection : Eaton BR series should be used for the
internal panelboard. – Hold Down Kit for fixing BR series circuit breaker :
BRHDK125 – Sub feed lug for the internal panelboard : Eaton BRPSF225 y (If
required) External CT and its connecter
– If you would like to know in which situations an external CT is required,
please refer to “Usage of External CTs”. These CTs are available from LGEUS
and the additional cables are required to connect external CTs to a SE Box.
The installer should prepare CTs and related components before the
installation and make them on site.
– CT : CTD-1X.200.1A.XXX – Cable : 600V UL 1015 AWG 18 recommended – Ring
terminal lugs : stud size – 1/4 inch, wire range – 18AWG min.
Due to our policy of continuous product innovation, some specifications may change without notice.
21
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Part Names
Front and Rear (Home 8)
22
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Connection Parts (Home 8)
WARNING
The battery packs and harness contain high voltages. Risk of death or serious
injury due to electric shock. Before working on any Home 8 wiring, make sure
the Home 8 battery circuit breaker is set to OFF.
12
12
PCS
Batter y
DIP switches AC power terminals (L1, Neutral, L2) (CN_GRID) Communication terminal block (to another Home 8) (CN_PCS) Communication terminal block (to the SE Box) (CN_ATS) Ground terminal (Protective Earth terminal, AC Power) Ground terminal (Protective Earth terminal, Communication) Battery fuse Battery circuit breaker
Due to our policy of continuous product innovation, some specifications may change without notice.
23
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
LED Indications (Home 8)
LED (PV) (Grid)
(Gateway)
Charge Discharge
Fault
Green Generating
Green Normal Green Connected SoC level + % On-Grid
On BAT. Charging
On BAT. Discharging
On Fault
Status and Indications Red
Not generating Red
Abnormal Red
Not Connected Remaining time + hr
Backup operation Off
Not operating Off
Not operating Off
Normal
Red Blink + Error code SE Box Fault
Red Blink + Error code PCS Fault
Red Blink + Error code Battery Fault Error code Fault
24
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Front and Rear (SE Box)
Getting Started
Front cover Cover lock Conduit knockout (right)
Due to our policy of continuous product innovation, some specifications may change without notice.
25
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Getting Started
Connection Parts (SE Box)
Communication terminal (to Home 8) (CN1000) Panelboard Backup load terminals (L1) Backup load terminals (L2) Neutral terminals for grid and load HMI (Human Machine Interface) display Grid terminal (L2)
Grid terminal (L1) Neutral terminals for Home 8 and PV inverter Non-backup load terminals (L2) Non-backup load terminals (L1) Ground terminals for grid and load Ground terminals for Home 8 and PV inverter
26
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Plan the Installation
Installation
1. Select Installation Location
y Select an appropriate installation location for the safe use of the product.
y For guidance on the selection of a proper environment, see “Installation
location.” y The Home 8 unit must be installed on the floor with the wall
support due to its heavy weight. y Choose a leveled floor and wall capable of
supporting the full weight of the Home 8 and SE box. y Prepare appropriate
screws, anchors, and additional supports for the wall type.
2. Plan the Cable Connection
y Determine the cable route for the connection to the SE Box. y The SE box has
6 knockouts for connecting the conduit. y The Home 8 has 1 hole for the 1.5
inch conduit. y For detailed positions, refer to “Front and Rear (Home 8)”and
“Front and Rear (SE Box)”.
3. Plan the Conduit or Raceway
y Depending on the cable size and local code requirements, select the proper
Conduit or Raceway size and amount.
y When installing a conduit or raceway as needed, the conduit adapter must be
attached to the inlet of the wiring compartment.
y Conduit adapters are required for all installations, and NEMA Type 3R
conduit adapters are needed when installing outdoors. (One for each used
conduit opening.)
4. Distance Between Components
Follow the table below for the maximum allowable length between system
components. Wire gauge must meet local codes and, in some circumstances, the
wire gauge requirements change based on length.
Types of Connections SE Box to Home 8 (Power) SE Box to Home 8 (Communication)
Wired Ethernet connection
200A CTs to SE Box
RS485 communication cable
Maximum Cable Length
Max 30 m (When multiple Home 8 units are installed, this max value is applied
to each unit.) Max 30 m (Total length of the communication cable, including
daisy-chained connections, through the last Home 8 in the chain) Max 100 m Up
to 30 m (Total length between CT and SE Box) Up to 30 m
Due to our policy of continuous product innovation, some specifications may change without notice.
27
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Installation Location
Before installing the product, select an appropriate installation location for
the safe use of the product. The Home 8 and SE Box has been certified NEMA 3R
and can be installed indoors as well as outdoors. However, if installed
outdoors, do not allow the product to be exposed to water sources or
continuously exposed to sunlight or other conditions that result in a
consistent operating temperature below -10°C (14°F) or exceeding 45°C (113°F).
y Power limitation phenomena in the battery (with a resulting decrease in
energy production by the
system). y Premature wear of the electrical/electromechanical and mechanical
components. y Reduction in performance, performance warranty, and possible
damage of the battery
WARNING
y Install the unit considering the possibility of strong winds or earthquakes.
y Please follow NFPA 855, NFPA 70 and local codes. y If the installation is in
an area that consistently receives heavy snowfall or is subjected to blooding,
make the foundation as high as possible and indoors installation recommended
in cold climates regions. y If the product is continuously exposed to sunlight
or other conditions that result in a consistent operating temperature below
-10°C (14°F) or exceeding 45°C (113°F), it may degrade the performance and
life cycle.
33°C (91.4°F)
0°C (32°F)
y This product is designed to be installed for indoor/outdoor use.
y Install this product in the place where PV cables, energy meter cables, grid
cables and battery cables are easily accessible.
y The recommended operating temperature range is from 0°C to 33°C (32°F to
91.4°F).
y Indoors installation is recommended in cold climates regions below 0°C
(32°F).
y Avoid installing this product in a location exposed to direct sunlight.
28
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
3 000 m (9842 ft)
Installation
y This product is designed to be installed on the floor standing with a wall
support. Do not install this product laying on its side.
y This product must be install on a leveled floor and the mounting surface
must be able to support the weight of the product. (approx.165 kg (364 lbs))
y Do not install the product on the ceiling. y Do not install the product
widthwise or install
on a wall with a lean of more than 10 degrees. y Do not install the product
tilting forward.
y This product must be installed or used at an altitude of less than 3,000 m
(9,842 ft).
y Do not install this product in an area prone to flooding
95%
y Do not install this product in a highly humid area such as a bathroom. y Do not install the product in an area with vibrations.
y Do not install this product in a place with ammonia, corrosive vapours,
acids, or salts.
y Install this product out of reach of children and pets.
Due to our policy of continuous product innovation, some specifications may change without notice.
29
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
y Do not install this product in places or environments subject to the heavy
build-up of dust.
y Do not block the air ventilation openings for cooling. y When cleaning the
air duct, shut off all of the systems including the
Home 8 and SE Box.
y This product generates some noise at times and should not be installed close
to living or sleeping areas.
y Please consult the location with your installer when installing in places
subject to noise sensitivity.
HOT
y The upper side of the installed Home 8 can become hot due to the heat from the air outlet. Do not place any object near the air outlet.
Sea wind
Wall Home 8
sea Installation location
y Do not install Home8sac within 500m of the seashore. Sea salt in the air may
cause the product to corrode.
y But, If the wind does not directly touch the product, it can be installed
within 500m.
500m
Distance Between Components
Follow the table below for the maximum available length between system
components. Wire gauge must meet local codes and in some circumstances wire
gauge requirements may change based on length.
Types of Connections
SE Box to Home 8 (Power) SE Box to Home 8 (Communication) Wired Ethernet
connection 200A CTs to SE Box RS485 communication cable
Maximum Cable Length
Max 30 m (When multiple Home 8 units are installed, this max value is applied
to each unit.) Max 30 m (Total length of the communication cable, including
daisychained connections, through the last Home 8 in the chain) Max 100 m Up
to 30 m (Total length between CT and SE Box) Up to 30 m
CAUTION
If you do not follow maximum cable size and length requirements, it may result
in intermittent or unreliable operation of the Home 8 system. In addition,
performance issues may arise even after successful commissioning in systems
that still need to meet these minimum requirements.
30
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Minimum Clearance
Installation
305 mm (12 inches)
915 mm (36 inches)
915 mm (36 inches)
305 mm (12 inches)
700 mm (28 inches)
305 mm (12 inches)
700 mm (28 inches)
305 mm (12 inches)
305 mm (12 inches) (348.768inmchmes)
This product must be installed with clearance at the left, right, top, bottom
and front of the product as shown in the figure. Make sure to keep at least a
305 mm (12 inches) distance between Home 8 units and between Home 8 and other
devices.
Keep at least a 700 mm (28 inches) distance between the front door and any
obstacles in order to allow space for installation and servicing.
If the door is closed, all other products should be at least 305 mm (12
inches) from the front door for safety operation.
Ensure that the distance between the wall and Home 8 is at least 25 mm (1
inch). Be sure not to place any object on top of the Home 8 to prevent risk of
fire or serious injury due to high temperature.
If the ESS is installed outdoors with eaves, there must be at least a 915 mm
(36 inches) clearance to the eaves. The National Electric Code may required
significantly larger working clearances (see NEC Section 110.26).
INFO
When installing the product in a garage, a vehicle crash protection guide must
be installed to disassemble for the repair and replacement of the product.
Due to our policy of continuous product innovation, some specifications may change without notice.
31
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
When installing the Home 8 next to an air conditioner outdoor unit, install the Home 8 in a position that avoids any hot air expelled from the air conditioner outdoor unit.
32
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Floor Standing Wall Support
Installation
The Home 8 unit must be installed on the floor with the wall support due to
its heavy weight. The proper environments described in “Installation Location”
must be considered. Be sure to follow the instructions exactly.
Mounting the Home 8
WARNING
y It is important to ensure that the drilling locations are not located on any
electrical wiring or plumbing inside the wall.
y Align both bracket positions correctly. If the bracket positions are not
correct, the Home 8 may not be mounted properly.
y The system should be installed according to NFPA 855 used for reference
installation guidance and local AHJ requirements.
CAUTION
y Make sure the screws, anchors, and additional supports are appropriate for
the wall type. y Make sure the pilot hole size matches the anchor type. y The
weight of the Home 8 is 163kg (359 lbs), and the SE Box is 25 kg (55 lbs). The
wall
must contain blocked studs that can bear the weight and are of masonry or
other suitable structures.
INFO
y When attaching the wall bracket to a wall, adjust the horizontal level using
an inclinometer or a leveler.
y When indicating the position to drill, you can refer to the Mount Hole Guide
which is a true to scale print of the actual wall bracket if required.
y The Mount Hole Guide is in the SE Box accessory package. y Before fixing the
bracket screws, check the horizontal level once again using an inclinometer
or a leveler.
y Depending on the surface, different screws and anchors may be required for
installing the wall bracket. Therefore, these screws and anchors are not
contained in the product. The system installer is responsible for selecting
the proper screws and anchors.
y It is recommended to use stainless steel screws which are 8 mm (5/16 inch)
and 76 mm (3 inch) in length.
Due to our policy of continuous product innovation, some specifications may change without notice.
33
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
INFO
y The following images are for reference. For safe installation, the
installers must assess whether additional fixing is required. Place the wall
bracket on a wall which meets every installation condition and clearance
requirement. Indicate the positions to drill using a pencil or other writing
utensil Drill holes in the indicated positions. It may help to use the true to
scale print of the actual wall bracket which provides the hole positions
included in the package. Refer to “Mounting details for wall brackets” for
more information.
406 mm (16 inches)
305 mm (12 inches)
Affix the wall bracket to the wall with screws or anchors. Align the upper and
lower brackets so that they are straight vertically.
768 mm (30.2 inches) From floor 404 mm (15.9 inches)
34
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
WARNING
y The Home 8 must be installed on the floor due to its the heavy weight. Wall
supporting is only for supporting purposes.
y If installation is difficult due to a Stem Wall, reinforce the wall or floor
to ensure proper installation.
y Be sure the floor is hard enough to support the weight of the Home 8. y
Rotate the legs at the bottom of the Home 8 to adjust the level.
CAUTION
y The Home 8 is very heavy. Serious injury may occur due to the heavy weight
when mounting it to the wall. Therefore, special care must be taken in
handling. Make sure to use the lift instead of using human strength when
installing.
y When hanging the Home 8 on the wall bracket, slowly lower the Home 8 and
make sure the Home 8 is properly mounted on the wall bracket.
y If 4 points on the wall brackets (both sides of the 2 wall brackets) are not
properly fixed to the wall, the product may fall over.
INFO
In areas where installation is difficult due to the heavy weight of the Home
8, the battery can be disassembled and installed. Refer to the “Battery Pack
Disassembly Guide” for battery disassembly.
Hang the Home 8 on the wall bracket using the lift. Then rotate the legs to
bring the Home 8 level with the floor.
Due to our policy of continuous product innovation, some specifications may change without notice.
35
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
WARNING
y Before making a connection to the Home 8, make sure that the battery circuit
breaker is OFF. If the circuit breaker is ON, death or serious injury may
occur due to electric shock.
y High voltage is energized through the internal battery module and wiring.
Special care must be taken when working on a Home 8 connection.
y High voltage may be energized inside the safety cover. Do not open the
safety cover of the Home 8.
Install a conduit as needed and attach the conduit adapter to the inlet of the
wiring compartment. The wiring compartment inlet accepts a standard 1 inch
conduit adapter. (The following is an example of possible conduit
installation. Depending on the site, the required conduits and the knockout
position of the SE box may vary.)
Home 8
INFO
After installing a conduit on the side of the Home 8, decide the installation
location of the SE Box considering the conduit position.
36
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Mounting details for wall brackets
INFO
y Refer to local building codes for the appropriate fastener. y Below are the
minimum guidelines for mounting and are not guaranteed to ensure profer
mounting. y Screws must be placed balacned in each corner. y Ensure that the
screw positions are at the center of the studs when anchoring to studs.
Wall Type Wood Studs Concrete or Masonry
Screw
M8 (5/16 inch) Lag screws with
washers M8 (5/16 inch) Concrete fasteners with washers
Length (Minimum) 76 mm (3 inches) 63 mm (2.5 inches)
Number of screws 8 16
Due to our policy of continuous product innovation, some specifications may change without notice.
37
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Mounting the SE Box
Use a flat head screwdriver to open the door. Then remove the safety cover’s 4
screws using a Phillips screwdriver.
CAUTION
When opening the door, do not use any tool other than an 8 mm hexagon wrench
and do not apply too much force. It may cause the lock to break.
38
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Place the SE Box on a wall which meets every installation condition and
clearance requirement. Mark the positions to drill using a pencil or other
writing utensil. Drill holes in the indicated positions. It may help to use
the true to scale print of the SE Box which provides the hole positions
included in the package. (The following is an example of possible conduit
installations. Depending on the site, the required conduits and knockout
position of the SE box would vary.)
500 mm (19.7 inches) 400 mm (15.8 inches)
520 mm (20.5 inches) 600 mm (23.6 inches) 1,478 mm (58.2 inches) From floor
WARNING
y Take care in holding the product when mounting the SE Box as it is heavy. It
may cause injury. y Do not hold the door when mounting. Do not hang anything
on the door. It may lead to
deformation or fracture. y It is important to ensure the drilling locations
are not located on any electrical wiring or
plumbing inside the wall.
CAUTION
Be careful not to be injured by the sharp edge when make the conduit hole or
connecting a conduit.
Due to our policy of continuous product innovation, some specifications may change without notice.
39
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Fix the SE Box with 4EA screws and anchors with O-rings in each position.
Before fastening the screws, place the supplied O-rings on the screws.
INFO
y The O-rings must be installed to meet the NEMA 3R requirements when
fastening the mounting screws. The mounting screws should be chosen
considering the O-ring. The internal diameter of the O-ring is the 8 mm (5/16
inches).
y Adjust the horizontal level using an inclinometer or a leveler when
attaching the SE Box to a wall before fixing the screws.
y Depending on the surface, different screws and anchors may be required for
installing SE Box. Therefore, these screws and anchors are not included.
y The system installer is responsible for selecting the proper screws and
anchors. y It is recommended to use stainless steel screws which are 8 mm
(5/16 inch),
76 mm (3 inch) in length and have a head diameter of more than 16mm (0.63
inch).
40
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Connections
Whole Home Backup (Service Equipment)
PV power measuring CT
Installation
Utility Meter
Home 8
PV inverter
L1 L2 N G
SE Box
Main bonding conductor
Main panel with main breaker (Backup)
Due to our policy of continuous product innovation, some specifications may change without notice.
41
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Service Equipment Preparation (If Required)
Neutral-Ground Bonding Busbar Connection
If not needed as a service equipment, this step may be skipped. A proper earth
connection and N-GND Bonding busbar connection are required for safe operation
of the system and for compliance with local code requirements. If the system
is installed as service equipment, connect the Neutral and Ground terminals on
the SE Box using the provided N-GND bonding busbar (Cross-sectional area: 45
mm2).
Remove the two nuts positioned in the figure. Assemble N-GND bonding busbar on
Neutral and Ground terminals and fasten the two nuts.
10 mm hex 75 kgf·cm (65 lbf·in)
torque
WARNING
To ensure the safe operation in backup mode, a local earth connection must be
present on the site such as an earth rod or ground electrode. Connection of
the earth rod must comply with local regulations.
42
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
SE Box Main Breaker Installation
If the system is installed as service equipment, a main breaker must be
installed. LGEUS does not provide the main breaker.
Remove the L1 and L2 lugs on the supply side using a 10 mm hex socket wrench.
Install a compatible main breaker by fastening the 2 nuts.
10 mm hex 75 kgf·cm (65 lbf·in)
torques
L2
L1
L1
L2
WARNING
Before mounting a main breaker in an electrical system, make sure there is no
voltage present where work is to be performed. The voltage in energized
equipment may cause injury or death.
INFO
y Main breaker terminal insulators are recommended any time a main breaker is
installed in the SE Box.
y Eaton® CSR or BW type breakers can be used. Refer to “Compatible Eaton
Parts” for breaker types and required accessories.
Due to our policy of continuous product innovation, some specifications may change without notice.
43
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Internal Panelboard and Additional Fastener
SE Box has an internal panelboard, where Eaton BR circuit breakers and
BRPSF225 (sub-feed lug block) can be installed. The internal panelboard
provides 5 spaces for 2-pole breakers as shown in the following diagram (a ~
e). Use hold down kit (Eaton BRHDK125), when an additional fastener is
required for the circuit breaker to comply with NEC and the local code. This
hold down kit can be used in placement of a ~ c only. Use d ~ e placements
stainless steel screws with, when the sub-feed lug block may be needed to
install multiple Home 8 units and PV inverters. It is recommended that the
terminal of the lug block should head to the right in consideration of wire
bending space. Do not connect the load to the internal panelboard to insure
the stable operation of the whole system. The ampacity sum of the circuit
breakers should not exceed 200Amps. If a 200A circuit breaker is used at the
main breaker load center connected to the lug block, no additional circuit
breakers should be installed on the internal panelboard. Following the NEC and
local codes is first priority.
a
b
c
d
e
44
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Wiring Connection between the SE Box and Home 8
This is an example of 1 Home 8 connection. For multiple Home 8 connections,
please refer to “Multiple Home 8 Units or PV Inverters Connection”.
WARNING
y The system wiring must follow ANSI/NFPA 70 and other local codes. y Conduit
adapters are required for all installations, and NEMA Type 3R conduit adapters
are
needed when installing outdoors. (One for each used conduit opening.) y
Required when torqueing connections
– Follow NEC 2017 110.14(D) – A well-calibrated torque tool must be used to
achieve the indicated torque values. – Use tamper-proof torque mark/paint
after torquing connections. y Class 1 wiring methods are to be used for field
wiring connections to terminals of a Class 2 circuit. y The AC output should
be isolated from the enclosure and system grounding.
INFO
y Refer to “Wiring Reference” for wiring specifications. y The wiring images
are pictures to help your understand and they may be different from the
actual work.
Connect the conduit to the SE Box.
Home 8
SE Box
Due to our policy of continuous product innovation, some specifications may change without notice.
45
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
WARNING
y Before making a connection to the Home 8, make sure that the battery circuit
breaker is OFF. If the circuit breaker is ON, death or serious injury may
occur due to electric shock.
y High voltage is energized through the internal battery module and wiring.
Special care must be taken when working on a Home 8 connection.
y High voltage may be energized inside the safety cover. Do not open the
safety cover of the Home 8.
Remove the screws on the right side and open the front cover of the Home 8.
(Hex socket : M8) Before starting the wiring, make sure the circuit breaker of
the Home 8 is OFF.
ON
OFF
46
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Pass the 6-conductor communication cable and the AC power conductors (L1, L2,
Neutral and Ground) through the conduit installed between the Home 8 and SE
Box.
L1 (Black) L2 (Red) N (White) G (Green) Com. (Gray)
Strip off the AC power conductors (L1, L2, Neutral, and Ground) on both the
Home 8 and SE Box sides as shown in the figure below.
6-4 AWG
18 mm (0.7 inch) 13 mm (0.5 inch)
8-6 AWG
Due to our policy of continuous product innovation, some specifications may change without notice.
47
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
12
Installation
On the Home 8 side, connect the AC conductors to the corresponding terminals
as shown in the figure below. There are two ground terminals on the Home 8
side. Connect the AC power ground to the upper ground terminal. The ground
terminals are identified with the following symbol:
L2 (Red) N (White) L1 (Black) G (Green)
Flat head screwdriver 6 4 AWG
52 kgf·cm (45 lbf·in) torque
48
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
On the Home 8 side, strip the 6-conductor communication cable and wind up the
communication wires and drain wire using insulation tape as shown in the
figure.
When taping the communication wire, wrap the remaining wire and cover it with
insulation tape.
Connect the 6-conductor communication wires to the communication terminal
block as shown.
8 mm (0.3 inch)
50 mm (2 inches)
80 mm (3.2 inches)
Blue Blue-White
Green Green-White
Orange Orange-White
6. GND 5. GRID CHECK 4. RELAY CHECK
3. 12V 2. CAN LOW
1. CAN HI
Insulation tape Drain wire, 80 mm (3.2 inches)
Remaining wires
On the SE Box side, strip the 6-conductor communication cable as shown in the figure. The stripped length of the outer insulation should not be over 2 inches to keep the proper isolation from the power cable in the SE Box. Keep the wiring route of the communication cable should be followed by NEC rule and local codes.
8 mm (0.3 inch)
50 mm (2 inches)
Due to our policy of continuous product innovation, some specifications may change without notice.
49
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Plug the green terminal block into the communication socket. Connect the drain
wire to the lower ground terminal as shown in the figure.
12
(CN_PCS)
Communication terminal block (CN_ATS)
CAUTION
When you install multiple Home 8 units, the DIP switch settings on each Home 8
should be different.
Set the terminating resistor for CAN communication by using a DIP switch. When
multiple Home 8 units are installed, this terminating resistor should be ON in
the last Home 8 in the daisy chain. Refer to “Multiple Connection ID Setup
Method” for more information.
12
ON OFF ON OFF
12
50
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
To make an electrical connection between the Home 8 and SE Box, installing the
required ampacity circuit breakers on the SE Box is required. (40A breaker is
required.) Install a 40A circuit breaker in the Home 8 as shown in the
following figure.
On the SE Box side, connect the AC conductors to the corresponding terminals as shown in the figure.
Flat head screwdriver Depending on wire size. Follow the guide from the Eaton
BR series.
L1 (Black) L2 (Red)
N (White) G (Green)
From Home 8
Flat head screwdriver
2-2/0 AWG 58 kgf·cm (50 lbf·in) torque
6-4 AWG 52 kgf·cm (45 lbf·in) torque
14-8 AWG 40 kgf·cm (35 lbf·in) torque
CAUTION
Before inserting the cable conductors to the terminals, loosen the screw and
then fix the screws tightly. Shake the cable to check the connection status.
Due to our policy of continuous product innovation, some specifications may change without notice.
51
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
At the end of the 6-conductor communication cable on the SE Box side, insert
the wires into the 6-position connectors as shown in the figure. Fix the cable
in the upper hook as shown in the figure. Arrange the cable between the
plastic case and metal enclosure. Cut back the drain wire and shield. The
drain wire should be terminated at the Home 8 chassis ground terminal only.
1. CAN HI (Orange-White) 2. CAN LOW (Orange) 3. 12V (Green-White) 4. RELAY
CHECK (Green) 5. GRID CHECK (Blue-White) 6. GND (Blue)
(CN1000)
52
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Grid and Load Connections
INFO
y Must use copper or aluminum wire rated at 90 °C (194 °F) for the AC power
connection. y Strip the ends of the wires and insert into the corresponding SE
Box terminal lugs. y Using the proper torque tool, tighten the lugs according
to the table on the following page.
Connect the grid conductors (L1, L2, Neutral, and Ground) to grid terminals in
the SE Box as shown in the following figure. When a main breaker is required,
install the main breaker ahead of wiring connection. Please refer to “SE Box
Main Breaker Installation”. (Follow the local code.)
1/4 inch Hex 288 kgf·cm (250 lbf·in)
torque
5/16 inch Hex 317 kgf·cm (275 lbf·in) torque
Flat head screwdriver
2 2/0 AWG 58 kgf·cm (50 lbf·in) torque
6 4 AWG 52 kgf·cm (45 lbf·in) torque
14-8 AWG 40 kgf·cm (35 lbf·in) torque
From Grid
G (Green) L1 (Black) L2 (Red) N (White)
Due to our policy of continuous product innovation, some specifications may change without notice.
53
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Connect the home load conductors (L1, L2, Neutral, and Ground) to the SE Box
backup load terminals as in the following figure.
5/16 inch Hex 317 kgf·cm (275 lbf·in) torque
Flat head screwdriver
2 2/0 AWG 58 kgf·cm (50 lbf·in) torque
6 4 AWG 52 kgf·cm (45 lbf·in) torque
14-8 AWG 40 kgf·cm (35 lbf·in) torque
L1 (Black) L2 (Red) N (White) G (Green)
From Backup Load
INFO
There are 6 conduit knockouts on the left, right, and bottom of the SE Box.
Select the appropriate conduit knockouts and grounding location so that the
cables are not twisted.
Home 8 SE Box Side Hole
SE Box Button Hole
Knockout Position
Inner Outer Inner Outer
Recommended Conduit Body Index Size
1 ½ inch 1 inch 1 ½ inches 1 ½ inches 2 inches
54
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
For partial home backup with non-backup loads under 100A, a non-backup panel
can be connected to the SE Box (The total load should not exceed 200A).
Connect the non-backup load conductors (L1, L2, Neutral, and Ground) from the
non-backup panel to the SE Box non-backup load terminals as in the following
figure.
5/16 inch Hex 317 kgf·cm (275 lbf·in) torque
Flat head screwdriver
2 2/0 AWG 58 kgf·cm (50 lbf·in) torque
6 4 AWG 52 kgf·cm (45 lbf·in) torque
14-8 AWG 40 kgf·cm (35 lbf·in) torque
From Non-backup Load
G (Green) L1 (Black) L2 (Red) N (White)
INFO
There are 6 conduit knockouts on the left, right, and bottom of the SE Box .
Select an appropriate conduit knockouts and grounding location so that the
cables are not twisted.
Due to our policy of continuous product innovation, some specifications may change without notice.
55
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Any circuit connected to the SE Box will not be powered when disconnected from
the grid. During on-grid operation, these circuits are still metered by the
internal site net metering with no additional metering hardware required.
However, if non-backup load panels exist upstream of the SE Box, additional
CTs are required. In this case, refer to “Usage of External CTs”.
Terminals
Wire Gauge
Grid lug (L1, L2) 6 AWG ~ 300kcmil
Non-Backup Load Lugs (L1, L2)
Backup Load Lugs (L1,L2)
Large Neutral Lugs
6 AWG 250 kcmil 6 AWG 250 kcmil 6 AWG 250 kcmil
Tool Size 1/4 inch Hex 5/16 inch Hex 5/16 inch Hex 5/16 inch Hex
Strip Length
32 mm (1.25 inches)
32 mm (1.25 inches)
32 mm (1.25 inches)
32 mm (1.25 inches)
Medium Neutral Lugs
14 AWG 2/0 AWG
Flat head Screwdriver (6 mm)
20 mm (3/4 inches)
Earth Lugs
14 AWG 2/0 AWG
Flat head Screwdriver (6 mm)
20 mm (3/4 inches)
Torque
288 kgf-cm (250 lbf·in) 259 kgf·cm (225 lbf·in)
317 kgf·cm (275 lbf·in)
2 2/0 AWG 58 kgf·cm (50 lbf·in) 6 4 AWG 52 kgf·cm (45 lbf·in) 14-8 AWG
40 kgf·cm (35 lbf·in)
INFO
y Refer to “SE Box Wiring: Power” for all wiring requirements and
recommendations, including wire colors and gauges.
y Refer to “Whole Home Backup (Service Equipment)” for example system wiring
diagrams.
56
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Connect to PV Inverter
This is an example of a 1 PV inverter connection. For multiple Home 8
connections, please refer to “Multiple Home 8 Units or PV Inverters
Connection”.
INFO
y PV inverters must support a Frequency-Drop or Frequency-Watt functions. y
Make sure the PV inverter is a product that satisfies UL1741SA or UL1741SB. y
Make sure that the Frequency-Drop or Frequency-Watt function is enabled in the
PV
inverter configuration. y If the PV inverter does not support this function or
the function is turned off, the product
may malfunction during the backup operation. y A PV inverter that does not
support a Frequency-Drop or Frequency-Watt function may be
connected to a non-backup port in the SE Box or a non-backup load panel.
Install the circuit breaker for the PV inverter as shown in the figure. Follow
local codes when selecting the circuit breaker ampacity.
Due to our policy of continuous product innovation, some specifications may change without notice.
57
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Pass the PV L1 cable from the PV inverter through the 200 A CT as shown below.
The side with the markings P1 and K on the CT faces the PV inverter, and the
side with the L and P2 faces the SE Box.
PV
L1
inverter
L2
CAUTION
y Make sure the CT sensor’s direction is correct. y Fix the CT sensor and the
L1 cable with a cable tie and position the CT sensor inside of the
SE Box.
INFO
Make sure the CTs are facing the proper direction as described in this manual.
A CT will show a negative current if installed in reverse.
58
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Using the supplied CT Harness, connect it to the upper side of the CT. When
wiring, refer to the figure below for the direction of the Ring Terminal. S1 :
Black (PV L1+), S2 : White (PV L1-) Ring terminal: stud size – 1/4 inch, wire
range – 18AWG By using the sealable covers included in the CT packaging box,
protect screw terminals to always assure the best safety. Refer to the manual
included in the CT package to assemble the sealable covers.
After connecting the end of the CT Harness to pins 1 and 2 of the terminal
block for PV CT in the SE Box, respectively, S1 (PV L1+) and S2 (PV L1-), plug
it into the connector and tighten the screws on both sides of the terminal
block. Fix the cable in the hook as shown in the figure below.
Due to our policy of continuous product innovation, some specifications may change without notice.
59
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Connect the PV inverter conductors (L1, L2, Neutral, and Ground) to the
corresponding terminals as shown in the figure. Fasten the PV CT to the PV L1
cable using a cable tie or other method. Arrange the power cables between the
plastic case and metal enclosure and fasten them at the point indicated by the
arrow using a cable tie.
Flat head screwdriver Depending on wire size. Follow the guide from the Eaton BR series.
Flat head screwdriver
2 2/0 AWG 58 kgf·cm (50 lbf·in) torque
6 4 AWG 52 kgf·cm (45 lbf·in) torque
14-8 AWG 40 kgf·cm (35 lbf·in) torque
L1 (Black) L2 (Red) N (White) G (Green)
From the PV Inverter
INFO
y Refer to “SE Box Wiring: Current Transformer (CT)” for additional diagrams
on configuring energy metering.
y Refer to “SE Box Wiring: Current Transformer (CT)” for CT configuration
troubleshooting tips.
60
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Internet Connection
Internet connection and a ThinQ service subscription are required for the
10-year limited warranty and to view the system status in the LG ThinQ® App.
INFO
y Connect the ethernet cable first, then connect the communication cable.
Ethernet Connection
y Ethernet cable must be CAT5 UTP(24 AWG) or better. y If it is not possible
to run an Ethernet cable directly to the customer’s network router, a
Powerline
Ethernet socket adapter may be used. y Fix the cable to the lower hook as
shown in the figure. Arrange the cable between the plastic case
and metal enclosure.
Due to our policy of continuous product innovation, some specifications may change without notice.
61
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
External Shutdown Switch Installation (If Required)
WARNING
y Before making a connection on the shutdown switch, you must ensure
disconnection from the Home 8, Grid, and other power sources. It may cause
death or serious injury due to electric shock.
y Conduit fittings (hubs) are required for all installations. NEMA Type 3R
conduit fittings (hubs) are required when installing outdoors. (One for each
used conduit opening)
y Before working with a hole saw, clear a space in the conduit area. It may
cause damage to cables.
INFO
This section provides guidelines on system functionality. Please consult your
local AHJ or Utility before use.
The External Shutdown Switch is wired through a low voltage, 12 V DC, control
circuit connected to a SE Box AUX/Comms port.
Using at least 24 AWG conductors (maximum 16 AWG) with wiring methods
according to code, connect pin 5 and 6 (labelled “STOP_P” and “STOP_N”) to a
compatible shutdown switch.
1 2
3 4 5 6 7 8 9
10
Additional opening for the shutdown switch. (If needed)
OFF
62
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Confirm that all Home 8 operation is shut down when the switch is pressed with a plunger type switch or OFF position with the rotary type switch.
External Shutdown Switch Requirements
y The External Shutdown Switch is supported on firmware version 1.0.2641 or
later. y Must be listed or recognized as an “Emergency Stop Button,”
“Emergency Stop Device,” or an “Emergency
Stop Unit.” y Must have an ON/OFF position. y Must have a clear ON/OFF
position indicator. y Must be rated for outdoor use. (NEMA 3R or higher) y
Should be installed externally in a readily accessible location, preferably by
the utility meter. y The maximum length of the low voltage wire running from
the switch to the SE Box should not
exceed 300 feet (90 m). y Should observe 12V, 0.1A ratings.
Please consider a switch or contact type when preparing the external shutdown switch.
Switch Type
Rotary Switch Plunger Type (Mushroom)
Contact Type
Short in ON position NC (Normally Closed)
Short released
System Energized ON position Released
System Shutdown OFF position Pressed
Due to our policy of continuous product innovation, some specifications may change without notice.
63
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
External Shutdown Switch Operation
The External Shutdown Switch option must be enabled on the HMI screen in order
to use it. Please ensure that this function is operating normally after the
installation.
If it is enabled, the external shutdown switch will make the system operate as
stated in the following table.
Shutdown Switch
Plunger Type (Mushroom)
Rotary Type
Pressed
OFF position
Released
ON Position
Home 8 Operation
All Home 8 operations will be shut down (The Home 8 will be in standby mode
with no AC voltage output.). This operation is the same regardless of AC grid
presence. [AC grid present] The system operation will resume normally soon.
[AC Grid not present (Off-grid or AC grid is down)] Home 8 operation will only
resume when the utility grid is recovered or when woken by “Black Start” on
the Home 8.
y When Black Start operation is required, follow the guidelines for “Black Start”.
64
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Backup Load Connection
Available Backup Power
Maximum discharging power/current: 7.5kVA / 31.25A Peak discharging
power/current (for 10s) : 9.0kVA / 37.5A Considering the available backup
power, please connect the loads to the backup panel. After the installation,
please check whether the LG ESS Home 8 can provide backup power properly in
“Backup Testing Guidelines”. – The backup load will be supplied by the LG ESS
Home 8 and PV during a power outage. – The non-backup load will power down
during a power outage.
Backup Load Considerations
The backup power is a limited power source stored in the battery system.
Depending on the load types, the stored energy in the battery may be drained
rapidly or the system may restart due to big load changes (likely due to the
inrush current), or the system may be shut down to protect the battery and the
whole system. Please be careful to use the battery system in backup operation
by referring to the following table.
Classification General appliance
Large load
High inrush load
Types of Loads
Small plug-in appliance such as TVs, Laptops/PCs, Radios, Routers, and Mobile
chargers Lightings (Compact fluorescent or LED recommended) Refrigerator and
freezers. Small kitchen appliances (Coffee makers, Cookers, Microwaves)
AWHP (Air to water heat pumps) / Electric water heaters Electric cooktops /
Electric ovens Spas / Saunas Washers / Dryers Hair Dryers EV Chargers
Air conditioners Pool pump, Well pump, Sump pump
y Do not use loads exceeding the maximum power or current in the backup load,
which may shut down the whole system.
y Using a large load can rapidly drain the battery. y For a high inrush load,
please use the soft starter to consider the LRA spec on the labels from the
loads. Depending on the base power consumed for backup operation, the
available supply to the inrush current from the LG ESS Home 8 may vary.
y When using an air conditioner, it is especially important to perform a
backup test. If the system frequently restarts, use a soft-starter for the air
conditioning unit.
y The application is subject to change for appliance improvement purposes
without notice.
Due to our policy of continuous product innovation, some specifications may change without notice.
65
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Backup Testing Guidelines
After the installation, please check whether the LG ESS Home 8 can provide
backup power properly through the following steps. * LG ESS Home 8 provides
the seamless transition within 100ms.
Run the LG ESS Home 8 and make sure the system is operating and not set to
“STOP” To prevent a system malfunction caused by the backup operation, please
leave the PV circuit breaker in the OFF position during this step. Simulate a
power outage by turning off the dedicated breaker of the SE Box or the Service
Disconnect Switch. – If you turn off the service disconnect switch, the non-
backup loads will be powered down. – If you turn off the dedicated circuit
breaker of the SE Box, the non-backup loads will be still powered by the
utility grid in the partial backup system. Check that the LG ESS Home 8
provides backup power without any faults or errors. If there were any faults
or errors, LG ESS Home 8 will automatically restart within 10 minutes. It may
generally take 2 minutes for a single ESS installation. If the system does not
restart within 10 minutes, please turn on the dedicated breaker of the SE Box
or the Service Disconnect Switch and check the event history. If it works
normally, please connect the system to the grid connection by turning on the
dedicated breaker of the SE Box or the Service Disconnect Switch for the grid
recovery. It will take around 1 minute. Check that the system operates with
the grid connection. Turn on the PV circuit breaker and check the PV
generation on the HMI screen. After the PV generation, simulate a power outage
again. In the beginning of the backup, the LG ESS Home 8 system shifts AC
frequency to block the PV generation for a stable transition to backup
operation. Please check that the PV generation stopped at the start of the
backup operation, and then wait at least 5-8 minutes for PV generation,
depending on the grid profile of the PV inverters. Check that the PV
generation and LG ESS Home 8 operate well. Depending on the PV generation
power and the backup load consumption, the LG ESS Home 8 will be charged or
discharged to the backup load. If there were no problems, turn on the
dedicated breaker of the SE Box or the Service Disconnect Switch for grid
recovery. It will take about 1 minute. Check that the system operates well
with the grid connection.
66
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Backup Test Troubleshooting Guide
If you have any problems in testing the backup, please read the following
carefully. Please connect the system to the utility grid to check the system
status. Please check the event history during the backup testing on the HMI
screen: [Menu] > [Installer Settings] > [PCS Settings] > [Event history] Check
the opened and closed events. If you can find any fault related to over
current (OC), the overloaded, or over power faults in the history, please
check the load connection and the types of loads. 1. Air conditioners If the
air conditioner was connected to the backup load, please perform backup
testing without the air-conditioner connected. Please turn off the air-
conditioner circuit breaker and then do a backup testing again. If the system
operates well, a soft-starter should be installed for the air conditioner. 2.
Pumps (Well pumps, Sump pumps, Pool pumps, etc.) If the pumps were connected
to the backup load, please check it through the same method as listed for the
air conditioner backup testing listed above.
If the system cannot operate normally without using the air conditioner or
pumps during the backup test, 1. Check the load consumption power in backup
and check the ambient temperature around the Home 8
unit. The output power may be de-rated by the temperature to protect the
battery units. If the total load consumed power is over the available maximum
discharging power, large loads may also need to be move to non-backup panel.
2. Check the power connection and the polarity of the power cables in the
system. Make sure the same polarity is used for multiple Home 8 installation.
3.Check the load imbalance between L1-N and L2-N. Even though the total load
consumed power is not over the available output power, the imbalance could
make the system over-loaded condition. Please make the 120V load balanced to
avoid the over-loaded condition. If the system is still not working well,
please contact to a service professional.
Due to our policy of continuous product innovation, some specifications may change without notice.
67
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Installation Completion
Before closing any installed hardware, take photos of the completed wiring in
the SE Box, Home 8, and main panel. Make sure that all conduit junctions and
cable entry points are secure and properly sealed. Arrange the communication
and AC power wires neatly inside the Home 8 wiring compartment. Install the SE
Box safety cover and secure it firmly with the original screws. Before
attaching the safety cover to the SE Box, remove the panels on the circuit
breaker installed positions. When removing the panels, make sure the burr
parts in each panel hole are cleanly removed.
CAUTION
The labels and markings must comply with the NEC and local code. The
corresponding labels must be attached after the installation inspection has
been approved by AHJ.
Attach naming labels to distinguish the breakers.
68
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
CAUTION
High voltage is energized through the internal battery module and wiring.
Special care must be taken.
Switch the battery circuit breaker on the Home 8 to the ON position and close
the front cover. When closing the front cover, make sure the front cover is
securely fitted to the gasket for a proper waterproof seal.
ON
OFF
12
Due to our policy of continuous product innovation, some specifications may change without notice.
69
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
CAUTION
Make sure the door is correctly closed and all bolts are fastened. Otherwise,
the NEMA 3R grade cannot be maintained.
Fasten the screws on the right side of the Home 8. (25 kgf·cm (22 lbf·in)
torque, Hex socket : M8)
INFO
The main circuit breaker for the SE Box should be installed in the SE Box or
upstream of the SE Box.
Switch the main circuit breaker for the SE Box to the ON position and wait
until the main screen appears on the HMI display. It will take about 30
seconds. Switch the circuit breaker for the Home 8 to the ON position. Switch
the circuit breaker for the PV inverter to the ON position (if equipped).
70
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Press the POWER button and press and hold the BLACK START (6s) button for at
least 6 seconds until you hear a “click.” If the SoC level is shown on the LED
display of the Home 8, the booting process has been completed normally.
INFO
The SoC level displayed on the LED display after turning on Home 8 may differ
from the actual SoC level. It may take up to 30 minutes to synchronize with
the actual SoC level.
CAUTION
All covers must be correctly reassembled. Otherwise, the NEMA 3R grade cannot
be maintained.
Close and lock the front door using a flat head screwdriver. When closing the
SE Box front door, check the direction of the locking rack. If the direction
of the locking rack is not correct, the door will not close properly.
Set all of the system settings on the HMI display of the SE Box and start commissioning.
Due to our policy of continuous product innovation, some specifications may change without notice.
71
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Wiring Reference
Home 8 Wiring
12
No. Home 8 Terminals a CAN + (CAN HI) b CAN – (CAN LOW) c 12V d RELAY CHECK e
GRID CHECK (LOGIC) f GND
g Cable Shield/Drain Wire
h L1 (Line 1) i N (Neutral) j L2 (Line2) k Chassis Ground Lug
Recommended Wire Color Orange-White (CAT 5E STP) Orange (CAT 5E STP) Green- White (CAT 5E STP) Green (CAT 5E STP) Blue-White (CAT 5E STP) Blue (CAT 5E STP) (Terminate at the Home 8 chassis ground lug only) Black White Red Green / Yellow
Wire Gauge 24 16 AWG 24 16 AWG 24 16 AWG 24 16 AWG 24 16 AWG 24 16
AWG
6 4 AWG 6 4 AWG 6 4 AWG 8 6 AWG
y Depending on the local code for installation methods and cable sizing
calculations. y If a communication cable may use cable types other than CAT 5E
STP,, follow the twisted pair
correctly. Twisted-pair: CAN HI – CAN LOW / 12V – RELAY CHECK / GRID CHECK –
GND
INFO
y Refer to local codes and standards for correct wiring practices and colors.
y Suitable wire ferrules may be used for power terminals, but are not
required.
72
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
SE Box Wiring: Power
Installation
No. Home 8 Terminals
a Grid Terminal (L1,L2)
b
Ground Terminal (Grid, Load) – 6 Positions
c Backup Load Terminal (L1,L2)
d Neutral Terminals (Grid, Load)
e
Neutral Terminals (Home 8, PV Inverter)
f
Ground Terminal (Home 8, PV Inverter) 6 positions
g Non-Backup Load Terminals (L1,L2)
h N-GND Bonding Busbar
i RESET Button
j USB Connector
k DRM Connector
l Ethernet Connector
Recommended Wire Color Black, Red Green, Bare Black, Red White White
Green, Bare Black, Red Included with the SE Box –
- Use copper or aluminum conductors rated at 90 °C (194 °F).
Wire Gauge 6 AWG 300 kcmil 14 AWG 2/0 AWG 6 AWG 250 kcmil 6 AWG 250
kcmil 14 AWG 2/0 AWG
14 AWG 2/0 AWG 6 AWG 250 kcmil 45 mm2 (Optional) 24 AWG CAT5 or better
Due to our policy of continuous product innovation, some specifications may change without notice.
73
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
SE Box Wiring: Internal Panelboard
The internal Panelboard is 200A-rated and supports 5 x 2-pole breaker spaces
(10 circuits) using Eaton BR Branch circuit breakers up to 125 A.
If an external generation panel is required for a large PV and Home 8 system,
use a sub-feed lug (Eaton BRPSF225) on the internal panel board. In this case,
other spaces on the internal panelboard can not be used for the circuit
breaker. Leave no breakers.
The Home 8 connection to the SE Box always requires a 40 A Circuit breaker.
This breaker serves as circuit protection for the Home 8.
Breaker sizing, connection, and installation must comply with the National
Electric Code.
For more information, please refer to “Internal Panelboard and Additional
Fastener”.
No. Terminals
a
BR Series Circuit Breaker on the Internal Panel Board
b
Neutral Terminal (Home 8, PV Inverter) 6 Positions
c
Ground Terminal (Home 8, PV Inverter) 6 Positions
Recommended Wire Color L1 : Black, L2 : Red Green, Bare Green, Bare
Wire Gauge Depends on the breaker sizing 8 6 AWG
8 6 AWG
- Use copper or aluminum conductors rated at 90 °C (194 °F).
74
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
SE Box Wiring: Communication
Installation
AUX/Comms Home 8
AUX/Comms
No. Terminals a RS485 #1 B (LOW) b RS485 #1 A (HIGH) c RS485 #2 B (LOW) d
RS485 #2 A (HIGH) e STOP_P f STOP_N g AUX1_P h AUX1_N i AUX2_P j AUX2_N
Home 8
No. Terminals a CAN + (CAN HI) b CAN + (CAN LOW) c 12V d RELAY CHECK e GRID
CHECK (LOGIC) f GND
Recommended Wire Color Black Red Black Red Black White Black White Black White
Wire Gauge 24 16 AWG 24 16 AWG 24 16 AWG 24 16 AWG 18 – 16 AWG 18 – 16 AWG 18 – 16 AWG 18 – 16 AWG 18 – 16 AWG 18 – 16 AWG
Recommended Wire Color Orange-White (CAT 5E STP) Orange (CAT 5E STP) Green- White (CAT 5E STP) Green (CAT 5E STP) Blue-White (CAT 5E STP) Blue (CAT 5E STP)
Wire Gauge 24 16 AWG 24 16 AWG 24 16 AWG 24 16 AWG 24 16 AWG 24 16 AWG
Due to our policy of continuous product innovation, some specifications may change without notice.
75
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
SE Box Wiring: Current Transformer (CT)
a Internal site net metering CT cable (L1) b Internal site net metering CT cable (L2)
c External site net metering CT connector (L1,L2) d PV Generation metering CT connector (two L1)
Home 8 SE Box Wiring : External Site Net Metering CT Connector
No. Terminals Ext. site net CT L1 + Ext. site net CT L1 Ext. site net CT L2 + Ext. site net CT L2 –
Recommended Wire Color Black White Red or Black White
Wire Gauge 18 14 AWG 18 14 AWG 18 14 AWG 18 14 AWG
y If external site net metering CTs are required, refer to “Usage of External
CTs” for the exact wiring requirements for external site net metering.
Home 8 SE Box Wiring PV Generation Metering CT Connector
No. Terminals PV CT L1 + PV CT L1 PV CT L1 + PV CT L1 –
Recommended Wire Color Black White Black White
Wire Gauge 18 14 AWG 18 14 AWG 18 14 AWG 18 14 AWG
y Pin 1 and Pin 3, Pin 2 and Pin 4 are shorted inside of the circuitry. All
pins may be used for multiple CTs for PV generation if required. If only 1 CT
is used in the system, please use pins 1-2 or pins 3-4.
y Twisted cable may improve the CT measuring. If an extended cable is
required, please twist.
76
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Installation
Extending CT Cable Length
A CT cable (1.5 m) is included in the SE Box package for PV generation
metering. The ring terminals are required for additional CT connections.
(Insulated type is recommended.) The stud size is 1/4 inch (M6) and the
required wire range is 18 AWG. A suitable crimp tool is required.
When extending the wire is required, the installer should prepare the cable
following this guidance.
Most of the CT cable noise will be line noise (50 or 60 Hz). Since this noise
generates at the same frequency as the signal measured by CT, induced noise
may affect the accuracy of current measurements, especially at a low current
level.
General Guidelines y Keep the cables as short as possible. y Route the CT
cables through a dedicated conduit. y Do not route CT cables through the same
conduit as the voltage cables. y Keep as far away as possible from other power
cables, VFDs (Variable Frequency Drives), and other
heavy machinery. y Do not run cables in parallel with other power cables.
Specific guidelines and requirements. y Use the same wire type and gauge to
match that of the CTs. (The provided CT cable uses UL1015,
18 AWG.) y The extension cable pair must be twisted (about one twist per
inch). The twisted cable increases
the cable’s differential immunity to induced noise at line frequency (50 or 60
Hz). The direction of the twisting should be same as the provided or existing
twisted cables. y Avoid large open loops in the cable at the joint Maintain
the twisting until as close to the joint as possible. y The best ways to
create the electrical connection at the joint: – The best way to join the
wires is a solder joint covered and insulated with heat shrink tubing.
Alternately, the provided cable can be switched out for a new, longer cable
suitable for the long distance CT. – Wago 221 Series Lever Nuts (TWO 2-pole
lever nuts are required for 1 CT.) – Crimp-On Butt Splice (insulated type).
These require a special crimping tool, so this method is not always practical.
– Do not use normal electrical wire nuts, as these do not provide a good
electrical or mechanical connection with 18 AWG wire. – Do not simply twist
the bare wires together.
Due to our policy of continuous product innovation, some specifications may change without notice.
77
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Installer Setup Wizard
When this product is turned on for the first time, the installer setup wizard
may be used by an authorized service personnel. Before starting the SE Box
settings, the physical connection and installation must be securely done
exactly as described in this manual.
INFO
y Touch operation may not be possible when wearing gloves. y Touch operation
may not work if your fingers are wet or sweaty.
Step 1: Country And Language Settings
You can choose the country and language to use for the system settings.
[Country]: Press the currently selected country and select the desired country from the list. [Language]: Press the currently selected language and select the desired language to change.
78
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Step 2: Network Type
You can choose the network settings for the system. Refer to “Network
Settings” for more information.
Settings
Wired If the network is connected by an ethernet cable, select [Wire] in the [Network Type] wizard. Wireless If you want to use the wireless network connection , select [Wireless] in the [Network Type] wizard. Skip Internet Settings If you do not want to connect the system to the internet., select [Skip Internet Settings] in the [Network Type] wizard.
If the system is not connected to the internet, the installer cannot monitor the system status through the web monitoring system or mobile app.
Due to our policy of continuous product innovation, some specifications may change without notice.
79
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Step 3: Installer Password Setting
You can set a password for accessing the system display.
Press the [Input password] field and input the desired password. Your password
must be at least 8 characters long. The password must contain at least one
number, one special character, and one letter. Press the [Confirm Password]
field and input your password again, then press [Apply] to set the password.
Step 4: System Information
You can check the system information.
Check that the loaded system information is correct. If it is not, check the DIP switches on each Home 8 and press [Rescan] to retrieve the information. Refer to step i of the “Wiring Connection between the SE Box and Home 8” for DIP switch settings. For multiple connections, see “Multiple Connection ID Setup Method”.
80
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Step 5: Firmware Update
You can update the firmware of the system to the latest version via USB .
Settings
The current version and new version of the system firmware are displayed.
Connect a USB storage device containing the latest software to the USB
connector and press [Firmware update] to start the firmware update.
Step 6: Date & Time Settings
You can set the current date and time. Refer to “Date & Time Settings” for
more information.
Due to our policy of continuous product innovation, some specifications may change without notice.
81
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Step 7: Additional System Information
You can input the system name and installation date.
Step 8: Utility Information
You can set up a communication connection with utility company and grid
profile.
Utility Company
Input the name of a utility company. Grid Profile Select the appropriate grid
profile option for the system environment. Select the grid profile at your
location.
82
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Config Parameters Set the config parameters of the selected grid profile. The available config parameters are displayed when you click the “Edit” button. y Table of field adjustable trip limits for voltage and frequency
Category
Region
OV Level1
AC Voltage (% of
Nominal Voltage)
UV Level1
OV Level2
UV Level2
UV Level3
HF Level1
Frequency
LF Level1
HF Level2
LF Level2
Voltage Range Trip Time Range Voltage Range Trip Time Range Voltage Range Trip Time Range Voltage Range Trip Time Range Voltage Range Trip Time Range Frequency Range Trip Time Range Frequency Range Trip Time Range Frequency Range Trip Time Range Frequency Range Trip Time Range
IEEE1547
UL1741SB
Unit Default (as shipped)
Min
Max Default
Min
Max
%
110
110 120 110 110 120
sec
13
1 13
13
1 13
%
88
0 88
88
50 88
sec
21
21 50
21
21 50
%
120
–
–
120
–
–
sec
0.16
–
–
0.16
–
–
%
50
0 50
50
–
–
sec
2
2 21
1.5
0.5 21
%
50
0 50
50
–
–
sec
2
2 21
1.5
0.5 21
Hz
61.2
61 66 60.5 60.1 66
sec
300
180 1000 300 0.16 1000
Hz
58.5
50 59 58.5 57 59.9
sec
300
180 1000 300 0.16 1000
Hz
62
61.8 66
62
62 64
sec
0.16
0.16 1000 0.16 0.16 1000
Hz
56.5
50 57
57
53 57
sec
0.16
0.16 1000 0.16 0.16 1000
Due to our policy of continuous product innovation, some specifications may change without notice.
83
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Step 9: PV
You can check the information for the PV inverter that is connected to the
system.
If you are using a PV inverter, set this option to [Use] and fill the [PV Rate
Output Power] and [Installed PV Panel Capacity] fields.
Step 10: External Device
If you are using an external shutdown switch, set the [External Shutdown
Switch] option to [Installed]. You can check the device that are connected to
port 1 and port 2. If no devices are connected to the ports, it will display
as [None].
84
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Step 11: Operating Mode
You can select an operating mode. Refer to “Operating Mode” for more
information.
Settings
Step 12: Battery Settings
You can set the battery’s reserve SoC level in case of a power outage. The
default level is set to 20%.
Due to our policy of continuous product innovation, some specifications may change without notice.
85
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Step 13: Summary
This is the last stage of the settings. Before operating the system, check all
of the settings on the [Summary] display. Before operating the system, running
a [Commissioning Test] is a way to verify that the system has been set up
correctly. If it is not possible to run a [Commissioning Test], select [Start
System] to launch the system.
86
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
About the HOME Screen
The HOME screen displays and indicates the current system status. You can also
check several settings and other information on the HOME screen. A
B
C
E
D
Displays the sub-menu. Displays the currently running mode. Displays the
system status. (Waiting, Charging, Discharging, Warning, Fault, Standby, Stop,
Disconnected, or Force Stop) Displays the charge status of the battery. You
can check the power flow and error messages for the PV, Battery, Grid, and
Home load.
If there are 2 or more Home 8 units installed in the system, each Home 8’s
status and error messages are displayed on the HOME screen as shown below.
Due to our policy of continuous product innovation, some specifications may change without notice.
87
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Errors
If an error occurs in the SE Box or Home 8, the current error information is
displayed in the Event History. Press 6 to show the errors.
[Type] shows the severity of the error, [Device] shows the information of the
device where the error occurred, and [Code] shows the error code.
Backup History
If the system is in backup mode due to a power outage, you can check the time
when the backup started, the time the power outage ended, and how long the
power outage was maintained. Press [ ] > [Backup History] to show the event
history.
88
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Installer and User Settings
The installer or user may need to change the system settings, even if all of
the settings were set when the system was initially installed. Press [ ] to
enter either the [User] or [Installer] settings menu.
To enter the Installer settings menu, you need to input the password on the screen. Input the password to enter the settings menu.
If you input the incorrect password 5 times, you cannot attempt to input another password for one minute.
Due to our policy of continuous product innovation, some specifications may change without notice.
89
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
General Settings
Country
Press the currently selected country and select the desired country to change.
Language
Press the currently selected language and select the desired language to
change.
90
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Network Settings
You can choose the network setting for the system. Select the connection type,
either [Wired] or [Wireless].
Wired If the network is connected by an ethernet cable, select [Wired] on the [Network Settings] screen.
If the [IP Settings] option is set to [DHCP], the system will automatically be
allocated an IP address from the local area network (LAN) through the wired
connection. You may need to set the network connection manually depending on
the network conditions. In this case, press [DHCP] to change to [Static].
If you set the [IP Settings] option to [Static], fill in the [IP address],
[Network Subnet Mask], [Gateway Address] and [DNS Address] options manually
and press [Apply] to apply the network settings.
Due to our policy of continuous product innovation, some specifications may change without notice.
91
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Wireless If you want to use a wireless network connection, select [Wireless]
on the [Network Settings] screen. Available SSIDs are listed on the screen.
Select a SSID you would like to connect the system on the SSID list. Input
password of the SSID in the [Password] field. After entering all the fields,
tab [Connect] to finish the wireless network connection.
LG SE Box provides both wired and wireless internet connection. Depending on
the SE Box location and the router, the wireless signal may be too weak to
connect to the internet. The HMI screen on the SE Box will display a warning
sign as shown below if the wireless signal is too weak.
It is also necessary to check if the signal strength is sufficient under poor conditions (such as while the entrance or garage door is closed) during usage. If the signal is not strong enough to connect the internet, please consider installing the LG SE Box as close as possible to the router or install a WiFi range extender or Signal Booster.
92
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
INFO
y Many network connection problems during set up can often be fixed by re-
setting the router or modem. After connecting the product to the home network,
quickly power off and/or disconnect the power cable of the home network router
or cable modem. Then power on and/or connect the power cable again.
y Depending on the internet service provider (ISP), the number of devices that
can receive internet service may be limited by the applicable terms of
service. For details, contact your ISP.
y LGEUS is not responsible for any malfunction of this product and/or the
internet connection feature due to communication errors/malfunctions
associated with your broadband internet connection, or other connected
equipment.
y Some internet connection operations may not be possible due to certain
restrictions set by the Internet service provider (ISP) supplying your
broadband Internet connection.
y A 10 Base-T or 100 Base-TX LAN port is required for wired connection to this
product. If your internet service does not allow for such a connection, you
will not be able to connect this product.
y A DSL modem is required to use DSL services and a cable modem is required to
use cable modem services. Depending on the access method and subscriber
agreement with your ISP, you may not be able to use the internet connection
feature contained in this product or you may be limited to the number of
devices you can connect at the same time. (If your ISP limits connection to
one device, this product may not be allowed to connect when a PC has already
been connected.)
y The use of a “Router” may not be allowed or its usage may be limited
depending on the policies and restrictions of your ISP. For details, contact
your ISP directly.
y Turn off all unused network equipment in your local home network. Some
devices may generate network traffic.
y For the purpose of better wireless transmission, install the SE Box as close
as possible to the access point.
y In some environments, placing the access point at least 0.45 m above the
ground may improve the reception.
y When using a wireless network connection, remove all obstacles between the
SE Box and the access point for better transmission.
y The reception quality over wireless depends on many factors such as type of
the access point, distance between the SE Box and access point, and the
location of the SE Box.
Due to our policy of continuous product innovation, some specifications may change without notice.
93
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Firmware Version
You can check the current firmware version and update the firmware.
How to update the firmware. Before updating the firmware, you need to store
the latest firmware on a USB storage device and insert the USB storage device
to the USB connector on the SE Box. When the [USB Status] field displays
[Plugged] on the screen, the firmware is ready to update. Press [Firmware
Update] to start the firmware update.
Date & Time Settings
You can set the current date and time.
Timezone Press [Timezone] and select the time zone for the region where the
system is located.
Automatic date and time If you set this option to [Auto], the date and time
settings are automatically set through the internet.
Date / Time You can set the date and time manually. Press [Date] or [Time] and
set the current date and time.
Time format Press [Time format] and select either [12 Hours] or [24 Hours].
94
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Soft AP
The Soft AP (Software enabled Access Point) function provides a virtual AP
function so that you can connect to the system through the LG ThinQ® App on a
mobile device. Press the ON/OFF switch to enable or disable this function.
INFO
To use the Soft AP function, you need to register your system through the LG
ThinQ® App. Refer to the LG ThinQ® App guide for detailed information.
Open Source
Press [Open Source] to see the Open Source Software Notice.
Reboot
Press [Reboot] to turn off and restart the system.
Due to our policy of continuous product innovation, some specifications may change without notice.
95
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Dump Log (Installer Only)
The system stores the logs for the last 30 days. To download the log files
from the system, you need to connect a USB storage device to the SE Box and
tap [Dump Log] to download the log files to the USB storage device.
The current version and new version of the system firmware are displayed.
Connect a USB storage device containing the latest software to the USB
connector and Press [Firmware update] to start the firmware update.
INFO
y Only FAT32 formatted USB storage devices are able to download the logs. y
The log files are stored in a folder named the serial number of the system.
Factory Reset (Installer Only)
Press [Factory Reset] and select [Reset] in the pop-up to reset all of the
settings to factory default.
96
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
PCS Settings
Operation
Press the [Start/Stop] switch to enable or disable the system operation.
System Information
You can check the system information on the screen. If the loaded information
is not correct, press [Rescan] to retrieve the information.
System Name
Press [PCS Settings] > [System Name] to set a system name.
Due to our policy of continuous product innovation, some specifications may change without notice.
97
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Installation Date
Press [PCS Settings] > [Installation Date] to set the system installation
date.
Utility Information
You can set up a communication connection with a utility company and grid
profile.
Utility Company
Input the name of a utility company. Grid Profile Select the appropriate grid
profile option for the system environment. Select the grid profile at your
location.
98
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Config Parameters Set the config parameters of the selected grid profile. The available config parameters are displayed when you click the “Edit” button. y Table of field adjustable trip limits for voltage and frequency
Category
Region
OV Level1
AC Voltage (% of
Nominal Voltage)
UV Level1
OV Level2
UV Level2
UV Level3
HF Level1
Frequency
LF Level1
HF Level2
LF Level2
Voltage Range Trip Time Range Voltage Range Trip Time Range Voltage Range Trip Time Range Voltage Range Trip Time Range Voltage Range Trip Time Range Frequency Range Trip Time Range Frequency Range Trip Time Range Frequency Range Trip Time Range Frequency Range Trip Time Range
IEEE1547
UL1741SB
Unit Default (as shipped)
Min
Max Default
Min
Max
%
110
110 120 110 110 120
sec
13
1 13
13
1 13
%
88
0 88
88
50 88
sec
21
21 50
21
21 50
%
120
–
–
120
–
–
sec
0.16
–
–
0.16
–
–
%
50
0 50
50
–
–
sec
2
2 21
1.5
0.5 21
%
50
0 50
50
–
–
sec
2
2 21
1.5
0.5 21
Hz
61.2
61 66 60.5 60.1 66
sec
300
180 1000 300 0.16 1000
Hz
58.5
50 59 58.5 57 59.9
sec
300
180 1000 300 0.16 1000
Hz
62
61.8 66
62
62 64
sec
0.16
0.16 1000 0.16 0.16 1000
Hz
56.5
50 57
57
53 57
sec
0.16
0.16 1000 0.16 0.16 1000
Due to our policy of continuous product innovation, some specifications may change without notice.
99
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
PV
You can set the connected PV inverter information.
If you are using a PV inverter, set the [PV Inverter] option to [Use] and fill
the [PV Rate Output Power] and [Installed PV Panel Capacity] fields.
External Device
If you are using an external shutdown switch, set the [External Shutdown
Switch] option to [Installed]. You can set any connected devices that are
connected to port 1 or port 2. You can set each port to [Modbus] or [AWHP]. If
no devices are connected to the ports, it will display as [None].
Modbus
If the port setting is set to [Modbus], set the detailed settings such as
[Slave ID], [Baud rate], [Start Bit], [Parity], and [Stop Bit].
100
Due to our policy of continuous product innovation, some specifications may change without notice. ©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
AWHP If the port setting is set to [AWHP], set the [AWHP Type] and [Energy
Level Setting] options. The AWHP settings run the heatpump with the energy
generated by the surplus power of the system. If the AWHP function is
activated, the AWHP status and AWHP energy flow can be checked on the HOME
screen. External Shutdown Switch To use an external shutdown switch, set the
[External Shutdown Switch] option to [Installed].
Operating Mode
You can select a operating mode.
PV Self-consumption Mode
This mode operates by minimizing the power used in the system. Power generated
from solar power is supplied to the load and the battery is charged with the
remaining surplus power. When the battery is fully charged, the surplus power
is supplied to the grid. If the load used power is greater than the solar
power, the power stored in the battery is used.
ToU Mode
In this mode, charging/discharging is performed for each section by directly
inputting the rate applied for each time period.
Available tables are [Summer/Weekday], [Summer/Weekend], [Winter/Weekday], and
[Winter/ Weekend]. You can make up to 24 sections with the designated load
type. The load type can be set to [Off-Peak], [Shoulder], [Peak], or [Super-
Peak].
Backup Only Mode
This mode fully charges the battery in case of a power outage. If this mode is
selected, the battery is fully charged and it is not discharged until the mode
is changed.
Due to our policy of continuous product innovation, some specifications may change without notice. ©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
101
Settings
Battery Settings
You can set the battery’s reserve SoC level in case of a power outage. The
default level is set to 20%.
102
Due to our policy of continuous product innovation, some specifications may change without notice. ©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Commissioning Test
All of the relative devices in the [Test Readiness] section should display a
ready status before starting the test. If every device is ready to test, press
[Start] in the [Charging] and [Discharging] test sections. If the [Test
Readiness] section is not at a ready status, [Start] cannot be activated.
The Charge and Discharge tests are each around 10 minutes. The result is
displayed when each test is completed. When there is no problem with the test,
[Success] is displayed. When [Fail] is displayed, press each test result to
display the detailed information. Check and solve the errors by referring to
the error code in the information, then perform the test again. For
information on an error code, refer to “Error Codes and Messages”.
Due to our policy of continuous product innovation, some specifications may change without notice. ©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
103
Settings
When all charge/discharge tests are successful, the backup test status changes
to [READY]. When the [Backup] status is ready, the installer opens the main
circuit breaker. If the ESS has successfully obtained backup status, the
[Backup] status changes to [RUNNING]. If it fails, the status changes to
[FAIL]. If the ESS is in backup status, the installer changes the main circuit
breaker to closed. If the grid status is idle for a certain period of time,
the grid relay status is closed and the [Backup] state is [SUCCESS].
104
Due to our policy of continuous product innovation, some specifications may change without notice. ©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Settings
Public Safety Power Shutoffs
If utility companies expect a wildfire or natural disaster, they notify the
user of it. After receiving the information, the user can set this function.
When you set the start and end time/date, the system fully charges the battery
before the set time, considering the current time, the current SoC, and the
function start time.
Emergency Ready
This function is a method of operating the system to prepare for an
insufficient electricity supply due to bad weather that may occur in the near
future. Press the [Use/Not Use] switch to enable or disable the function.
INFO
To use the [Emergency Ready] function, the system must be registered through
the LG ThinQ® application. Even when “Emergency Ready” is enabled, alert
signal may not be received due to network problems, etc. If more energy
security is prefered, keeping the reserved mode SOC higher is recommended.
Due to our policy of continuous product innovation, some specifications may change without notice. ©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
105
Settings
Event History
If an error occurs in the system, the current error information is displayed.
[Level] shows the severity of the error, [Devi
References