RENOGY 4PCS Solar Panel Kit Installation Guide
- June 14, 2024
- Renogy
Table of Contents
- Introduction
- Statutes and regulations
- General Information
- Renogy solar panels installation method
- Renogy solar panels installation – Mechanical installation
- Renogy solar panels installation – Electrical installation
- Renogy solar panels installation – Grounding
- Renogy solar panels installation – Operation and maintenance
- Schedule – Renogy solar panel iteration/mix recommendation
- References
- Read User Manual Online (PDF format)
- Download This Manual (PDF format)
Find Your Energy Freedom™
Renogy
Solar Panel Installation and Maintenance
Manual
Introduction
First of all, thank you very much for choosing Renogy’s solar panels!
What should you do with Renogy solar panel installation and maintenance? This
guide has covered everything from solar panel installation to cleaning.
This guide contains important electrical and mechanical installation
information that you should first understand before you install the
components. In addition, the manual contains some other safety information
that you must be familiar with. Everything in this manual is the result of a
long process of technical exploration and experience
Failure to follow the requirements outlined in this manual may void the
limited warranty provided to the customer for the installation of the
components. The recommendations in this manual are designed to improve the
safety of the modules during installation and have been tested and proven.
Please provide this manual to the owner of the PV system for their reference
and inform them of all relevant safety, operational and maintenance
requirements and recommendations.
Statutes and regulations
The mechanical and electrical installation of PV modules should refer to the
appropriate regulations, including electrical code, building code and
electrical connection requirements.
These regulations vary depending on the location of the installation, e.g.,
building rooftop installation, vehicle-mounted applications, etc. Requirements
may also vary with the voltage of the installation system, the nature of the
current (DC or AC). Please contact your local authority for specific terms.
General Information
3.1. Solar Panel Identification
Nameplate: Type, power rating under standard test conditions, current rating,
voltage rating, open circuit voltage, short circuit current, certification
mark, maximum system voltage information.
Serial Number: Each component has a unique serial number. This serial number
is printed on a barcode, placed in the component prior to lamination, and
cannot be torn or smeared after lamination. In addition, an identical serial
number can be found above or next to the component nameplate.
1. Aluminum alloy frame | 2. PV Glass | 3. EVA | 4. Solar Cell |
---|---|---|---|
5. Backplate | 6. Silicone | 7. Junction Box | 8. Nameplate |
9. Cable Wires | 10. Connector | 11. Mounting holes | 12. Grounding hole |
13. Leakage hole | 14. Bar Code |
(The rest of the version a corresponding solar panel specifications shall prevail)
3.2. Junction box style and wiring method
Junction box location| Recommended connection & wiring method for
series connection
---|---
| Vertical installation: the standard line length can be (Note: can increase
the extension line)|
Horizontal installation: standard line length can be (Note:
can increase the extension line)
|
| Vertical installation: the standard line length can be (Note: can increase
the extension line)|
Horizontal installation: standard line length can be (Note: can increase the
extension line)|
Junction box location| Recommended connection & wiring method for
series connection
| Vertical installation: the standard line length can be (Note: can increase
the extension line)|
Horizontal installation: standard line length can be (Note: can increase the
extension line)|
Junction box location| Recommended connection & wiring method for
parallel connection
---|---
| Vertical installation: the standard line length can be (Note: can increase
the extension line)|
Horizontal installation: standard line length can be (Note: can increase
the extension line)|
| Vertical installation: the standard line length can be (Note: can increase
the extension line)|
Horizontal installation: standard line length can be (Note: can increase the
extension line)|
Junction box location| Recommended connection & wiring method for
parallel connection
| Vertical installation: the standard line length can be (Note: can increase
the extension line)|
Horizontal installation: standard line length can be (Note: can increase
the extension line)|
Attention & Notes| This table is for reference only, the actual wiring
depends on the situation, try to reduce the length of the line, avoid cross-
wiring.
3.3. General Safety
When the modules are installed on the roof, the overall fire rating of the final structure needs to be considered. Also, the overall maintenance afterwards needs to be considered. For your safety, do not work on the roof without safety precautions including, but not limited to, fall protection, ladders or stairs and personal protective equipment. For your safety, do not install or handle components in hazardous environments, including but not limited to strong winds or gusts, wet or sandy roofs.
3.4. Electrical safety
Photovoltaic products generate direct current under light conditions, so take
appropriate protective measures (insulated gloves, insulated shoes, etc.) to
avoid direct contact between personnel and 30 V or higher DC voltages. 30 V or
higher DC voltages are potentially fatal.
Components can also generate voltage when no load or external circuit is
connected. Use insulated tools and wear rubber gloves when handling the
modules in the sun.
Photovoltaic modules do not have switches. The module can only be made to stop
working by moving the PV module away from the light or by covering it with
cloth, cardboard or a completely opaque material.
To avoid arcing and electric shock hazards, do not disconnect electrical
connections with a load. Incorrect connections can also cause arcing and
electric shock. Connectors must be kept dry and clean to ensure they are in
good working condition. Do not insert other metal objects into the connectors
or make electrical connections in any other way.
Snow and water or other reflections from the surrounding environment can
increase the intensity of the irradiation received by the module and can cause
an increase in output current. The output voltage of the module will also
increase appropriately at low temperatures.
If the module glass or other encapsulation material is damaged, wear personal
protective equipment and separate the module from the circuit.
Touching wet components is strictly forbidden unless wearing shock protection
equipment that meets the requirements; when cleaning components, you must
follow the requirements of this manual for cleaning components.
The connector must not come into contact with the following chemicals:
gasoline, white flower oil, live oil, mold temperature oil, motor oil (e.g.
KV46), grease (e.g. Molykote EM-50L, etc.), lubricating oil, rust prevention
oil, stamping oil, grease, diesel oil, cooking oil, acetone, alcohol, windex,
ortho bone water, tenax, mold release agents (e.g. Pelicoat S-6, etc.), sticky
board adhesive and potting Sealant (such as KE200, CX-200, chemlok, etc.), TBP
(plasticizer), cleaning agent, etc.
3.5. Operation Safety
- To ensure the safety of the components during transportation and storage, unpack the components upon arrival at the installation site.
- Protect the packaging from damage or dropping.
- It is forbidden under any circumstances to lift the entire module by grasping the junction box or wires.
- Do not stand or walk on the module.
- Do not apply excessive loads on the module or twist the module in order to avoid glass breakage.
- Do not drill holes in the module bezel, as this will result in a reduction in the bezel’s resistance to load and lead to corrosion of the bezel, thereby voiding the warranty;
- Do not scratch the anodic oxide layer on the surface of the aluminum bezel, except when grounding connections are made. Scratching may lead to frame corrosion, affecting the frame’s load resistance and longterm reliability.
- Self-repair of components is strictly prohibited
3.6. Fire Protection and Safety
Please refer to local laws and regulations before installing the components and comply with them regarding building fire resistance requirements. Ensure adequate ventilation between the backsheet and the installation surface during installation. The structure of the roof and the way it is installed can affect the fire safety performance of the building. If not properly installed, a fire may result. To ensure the fire rating on the roof, the minimum distance between the module frame and the roof surface is 10 cm. When mounting the module on the roof of a vehicle, if brackets are used, the module must be mounted on the brackets and must not be tightly bonded to the roof itself. Use proper module accessories such as fuses, circuit breakers, and ground connectors as required by local codes. Do not use the module if there are exposed combustible gases in the vicinity.
Renogy solar panels installation method
4.1. Installation location and environment
The components are not suitable for space environment.
Do not use mirrors or magnifying glasses to artificially focus sunlight on the
modules.
Do not install the module in a location where there is a risk of water
flooding.
It is recommended that the modules be installed in an ambient operating
temperature of -40°C
to 40°C, which is the average monthly maximum and minimum temperature at the
installation site. The maximum ambient operating temperature of the module is
-40°C to 85°C.
Ensure that the module is not subjected to wind or snow pressure exceeding the
maximum allowable load after installation.
The module needs to be installed in a location where there is no shade all
year round. Make sure that there are no obstacles that may block the light at
the module installation site.
If the modules are installed in a location where there is frequent lightning
activity, the modules must be protected from lightning strikes.
Do not install and use modules near flames or combustible materials.
Modules must not be installed or used in environments subject to excessive
hail, snow, sand, soot, air pollution, soot, etc.
Components are strictly forbidden to be installed on the installation surface
that is susceptible to aging and corrosion by the environment. For example:
wood, PVC plastic, etc.
4.2. Selection of inclination angle
Module inclination: The angle between the surface of the module and the
horizontal plane.
When the module is facing the sunlight, the module will get the maximum power
output.
For installation in the Northern Hemisphere, modules should preferably face
south, and for installation in the Southern Hemisphere, modules should
preferably face north.
For detailed installation angles, please follow the standard module
installation guidelines or the recommendations given by experienced PV module
installers.
It is recommended that the mounting angle of the modules be not less than 10
degrees (RV depending on the actual situation), so that the surface dust of
the modules can be easily carried away by rainwater when it rains, thus
reducing the number of module cleaning; at the same time, it is conducive to
the flow of water on the surface of the modules, avoiding a large amount of
water from accumulating on the glass for a long period of time and leaving
marks on the glass, which in turn affects the appearance and performance of
the modules.
Serially connected/parallel connected modules should be installed in the same
orientation and angle. If the orientation or angle is different, it may cause
different amount of solar radiation received by each module, which may lead to
output power loss. To achieve maximum annual power production, the optimal
orientation and tilt of the PV modules in the area where they are installed
should be selected to ensure that sunlight can still reach the modules even on
the shortest sunny day of the year.
If connected to a stand-alone PV system, the angle of installation of the
modules should be based on the season and light conditions to obtain maximum
power output. Generally speaking, if the output of the modules can be met even
on the lowest light intensity of the year, then the output of the modules at
the chosen angle will meet the year-round demand.
Renogy solar panels installation – Mechanical installation
5.1. General Requirements
- PV panels can be installed vertically or horizontally, and please keep the drain holes on the frame unblocked.
- Please keep the backboard of the PV panels untouched with any other structures especially when there are external pressure on them.
- Please leave at least 10mm gap between PV panels in case of any potential damage caused by thermal expansion and contraction.
- Please assure the installation site, such as the roof of the house or RV, is properly sealed and appropriate for installation in case of unexpected problems and permeating.
- Please leave a 10cm clearance between the frame of PV panels and the roof or the wall to secure the ventilation and dissipation of moisture when the PV panels are installed on the mounting brackets parallel to the wall or the roof.
- Please ensure the PV panel(s) is mounted firmly on the roof of the house or RV.
5.2. Mechanical mounting of single-sided & double-sided components
Renogy currently offers components that can be installed mainly by the bolt-on
or bracket mounting methods.
Installation of components must be done in accordance with the examples and
recommendations below.
Contact Renogy prior to using alternative mounting methods since it may void
the warranty.
5.2.1. Bolt mounting method
Renogy components are equipped with corresponding mounting holes, the number &
corresponding size are detailed in the corresponding component layout;
currently, the only mounting method provided by our company is bolt mounting.
The corresponding bolt type/ size diagram and the matching module version are
as follows.
Figure 2 Schematic diagram of single-sided component mounting holes
(The remaining component mounting holes are shown in the corresponding
component layout)
SKU| Number per set| Bolt size| Pictures| Installation
schematic| Applicable component models
---|---|---|---|---|---
MTS-ZB| 4| M6| | | RSP100D-BK RNG-100D-SS RNG-30D-SS RNG-50D-SS RNG-175D(Two
sets are recommended) RSP-200D(Two sets are recommended)
MTS- ACB| 4 (Each set has 2 parts)| M6| | | RSP100D-BK RNG-100D-SS RNG-30D-SS
RNG-50D-SS RNG-175D(Two sets are recommended) RSP- 200D(Two sets are
recommended)
Remarks| Please choose the number of bolts and installation method according
to the installation environment, conditions and actual situation.
5.2.2. Bolt mounting method with brackets
Renogy also offers its customers an angled mounting bracket that allows the
customer to freely adjust the angle of the module to the light during
installation. The corresponding mounting method is also bolt-on. The module is
fixed to the bracket by means of bolts.
SKU| Number of matching solar panels| Bolt size| Pictures|
Installation schematic| Applicable component models
---|---|---|---|---|---
MTS- TMB| 1 Set for 1 panel| M6| | | RSP100D-BK RNG-100D-SS RSP80D-SS RNG-30D-
SS RNG-50D-SS
MTS- TM100| 1 Set for 1 panel| M8| | | RSP100D-BK RNG-100D-SS RNG-50D-SS RNG-
175D RSP-200D
RSP450D-120X2 RSP550D-144X2 RNG-320D
Remarks| Please choose the number of bolts and installation method according to the installation environment, conditions and actual situation.
5.2.3. Mounting method of brackets
SKU
| Number of matching solar panels| Bolt size| Pictures|
Installation schematic| Applicable component models
---|---|---|---|---|---
MTS- SP100| 1 Set for 1 panel| M8| | | RSP100D-BK RNG-100D-SS
Remarks| Please choose the number of bolts and installation method according
to the installation environment, conditions and actual situation.
5.2.4. Other installation methods
SKU
| Number of matching solar panels| Bolt size| ****
Pictures
| Installation schematic| Applicable component models
---|---|---|---|---|---
MTS-CB| 1 Set for 1 panel| /| | /| All solar panels
Remarks| This mounting method requires no additional drilling and is suitable
for all Renogy solar panels. The module needs to be pre-fixed with silicone
for installation.
5.3. Introduction of flexible module installation method
For flexible modules, Renogy recommends the use of silicone mounting on the
roof. The roof should be cleaned before installation to ensure that the
surface is free of dirt and foreign matter, and the back of the module should
be cleaned to ensure that the back of the module is free of dirt and foreign
matter. This will ensure a strong adhesion between the backsheet and the roof.
The silicone mounting method is widely used for flexible modules, which fully
combines the mechanical properties of flexible modules and to a certain
extent avoids mechanical damage during subsequent use.
Figure 3 Schematic diagram of the structure of flexible components
(The rest of the component structure diagrams are based on the corresponding)
5.3.1. Introduction to flat roof mounting methods
After cleaning the surfaces of the modules, stick double-sided tape on each
short edge of the component for fixing. Apply silicone along the component
horizontally with a width of 6~10mm and a thickness of 3~5mm. Silicone length
application is to be adjusted according to the length of the component, with
a recommended spacing of 10mm between lines. The spacing allows for heat
dissipation and lets water run down. The component needs to be mounted within
5 minutes to prevent the silicone from curing and affecting the bonding
performance. After mounting, the component needs to be lightly pressed along
the bonding surface in the same direction the silicone was applied using a
professional pressing tool. The distance between the two components being
5~10mm.
Long side facing the direction of travel
Short side facing the direction of travel
Operating notes.
- When applying silicone, it is important to not completely seal all four sides of the flexible component, as this can affect heat dissipation and drainage. Renogy recommends ensuring that at least the short edges are not sealed to ensure proper heat dissipation and drainage and to avoid the risk of fire.
- The number of horizontal silicone glue applications can be adjusted according to personal preference. Renogy recommends applying glue to the edge of the double-sided tape with a width of 6-10mm and a thickness of 3-5mm.
- Double-sided adhesive tape should be flush with the edge as much as possible.
- After the installation is completed, it should be left for 72H to ensure that the silicone is fully cured, avoiding direct sunlight, rain and other harsh weather during the curing period.
- The maximum bend of the flexible module can reach 240°, but this bend is for the convenience of storage, the actual installation is recommended to install the flexible module horizontally, or the installation bend is less than 30° to ensure power generation efficiency.
- When a short edge is used as the bending edge, the bending angle must not exceed 30°.
Note: As the installation angle becomes more curved, the non-illuminated area of the module will increase. When the bending radius exceeds 30 degrees, the non-illuminated area of the module will exceed 30%, which will affect the output of the module.
5.3.2. Introduction to non-flat roof mounting methods
After cleaning the flexible modules, stick double-sided tape on each long edge
of the component for fixing. Apply the silicone according to the width of the
corrugated roof protrusion; install the component within 5 minutes after
finishing the silicone application to prevent the silicone from curing and
affecting the bonding performance. Use a professional pressing tool and
lightly press the surface of the component along the direction of gluing. The
distance between the two components is 5~10mm.
After the installation of the silicone part is completed, the flexible
component can be further fixed by applying bolts according to the mounting
holes that come with the flexible component itself.
Note: Renogy recommends that non-flat roof need to meet a minimum of 6 silicone lines on the back side, if this condition is not met, the flexible module is not suitable for this roof.
Renogy solar panels installation – Electrical installation
6.1. Electrical parameters
The nominal values of electrical performance parameters for components, such
as Isc, Voc, and Pmax, are obtained under standard test conditions. The
standard test conditions for components include an irradiance of 1000W/m2,
cell temperature of 25°C, and air mass AM1.5.
When components are connected in series, the Voc of the combination is the sum
of the Voc values of individual components, and the Isc remains the same as
that of a single component.
When components are connected in parallel, the Voc is the same as that of a
single component, and the Isc is the sum of the Isc values of multiple
components. Refer to the figure below. It is not recommended to connect
components with different parameters, models, or brands in series or in
parallel.
The maximum number of components that can be connected in series depends on
the maximum system voltage supported by the component. After being connected
in series under the lowest local temperature conditions, the open circuit
voltage cannot exceed the maximum system voltage value specified by the
component, such as DC600V/DC1000V/DC1500V. In practical applications, the
number of components connected in series and parallel needs to be designed
according to the parameters and models of the components and controllers.
The open circuit voltage correction factor can be calculated using the
following formula:
CVoc=1-βVoc×(25-T). T is the expected minimum ambient temperature at the
system installation location, and β (%/°C) is the temperature coefficient of
the selected component
Voc (refer to the corresponding component parameter table).
If there may be reverse current passing through the component that exceeds the
maximum fuse current of the component, the same specification overcurrent
protection device must be used to protect the component. If the number of
components connected in parallel is greater than or equal to 2 in a series,
there must be an overcurrent protection device on each series component, as
shown in the figure above.
6.2. Cable and Wiring
6.2.1 Introduction of cables and connections
Renogy modules use a junction box with a protection rating for connections
(see module specification for details) to provide safe protection for the
wiring and its corresponding connections and accessible protection for non-
insulated live parts. The junction box consists of connected cables and
connectors with corresponding protection ratings, which facilitate the
series/parallel connection of modules. Each individual module has two wires
connected to the junction box, one positive and one negative. The connection
of the positive and negative poles of the modules can be achieved through the
MC4 connectors.
Special solar cables and appropriate connectors should be used in accordance
with local fire, building, and electrical regulations (the wires should be
covered by aging-resistant conduits, and if exposed to air, should have aging-
resistant properties), and the electrical and mechanical properties of the
cables should be ensured.
After the cable is installed and connected, it should be protected from
mechanical damage. Do not press the cable too hard. Although the cable is
resistant to aging and waterproof, it should also be protected from direct
sunlight and rain. The minimum bending radius of the cable should be 43mm.
6.2.2 Extension cable selection for component-to-component connection
Renogy currently provides customers with inter-module connection cables mainly
in the form of SKU: RNG-EXTCB, with a wire diameter specification of 10/12AWG,
and a maximum length of 40FT for extension cables.
6.2.3 Extension cable for connecting the component to the controller
Renogy currently provides customers with connection cables between modules and
controllers mainly in the form of SKU: RNG-AK, with a wire diameter
specification of 10/12AWG, and a maximum length of 40FT for extension cables.
6.3. Connector
Please keep the connectors dry and clean, and ensure that the nut of the
connector is in a tightened state before connecting. Do not connect the
connectors if they are wet, dirty, or in any other unfavorable condition. If
the connectors are not connected positively and negatively, they do not have
waterproof function. After installing the modules, they need to be connected
as soon as possible or appropriate measures need to be taken to avoid the
infiltration of water vapor and dust. Avoid direct sunlight and immersion in
water for the connectors. Avoid the connectors falling on the ground or on the
roof, causing particles or dust to enter the connectors and affecting
subsequent use. Incorrect connections may produce arcs and electric shocks.
Please ensure that all electrical connections are secure. Make sure all
locked connectors are fully connected. It is not recommended to use different
types of connectors together.
6.4. Bypass Diode
The solar cells in the solar module are connected in series with a bypass
diode parallel protection, which is encapsulated in the junction box. When a
hot spot phenomenon occurs in a module, the diode will start working to
prevent the main current from flowing through the hot spot cell, thereby
limiting the heating and performance loss of the module. Note that the bypass
diode is not an overcurrent protection device. If the diode is suspected or
confirmed to be faulty, please contact Renogy. It is strictly prohibited to
attempt to open the junction box of the module on your own.
Renogy solar panels installation – Grounding
The design of the module uses anodized, corrosion-resistant aluminum alloy frames as rigid support. In order to ensure safe use and prevent damage from lightning and static electricity, the module frame must be grounded. When grounding, the grounding device must be in full contact with the aluminum alloy interior, penetrating the oxide film on the surface of the frame. It is strictly forbidden to add any additional grounding holes on the module frame. The grounding conductor or grounding wire can be made of copper, copper alloy, or any other material that meets the requirements of the corresponding national electrical specifications as a conductor. The grounding conductor must be connected to the earth through an appropriate grounding electrode. The holes marked with the grounding symbol on the frame can only be used for grounding and not for module installation. For modules without grounding holes, they can be grounded by connecting them to a grounded electrical device.
Renogy solar panels installation – Operation and maintenance
It is required to perform regular inspection and maintenance of the modules, especially during the warranty period. Please contact Renogy in 2 weeks if any abnormality or damage is found.
8.1. Solar panel cleaning
The accumulation of foreign substances (such as dust and bird droppings) on
the glass surface of solar panels can affect their power output and even cause
hotspots in the area.
The extent of the impact depends on the transparency of the foreign material.
For example, a small amount of dust on the glass surface can affect the
intensity and uniformity of absorbed sunlight, this usually does not cause
damage to the solar panel, and the power output usually does not decrease
significantly. However, a large amount of dust accumulation, bird droppings,
and shading by plants can form obstructions, which can significantly reduce
power output and even form hotspots. It is recommended that the surface of
the panels should not be obstructed by anything when there is sunlight.
The cleaning frequency depends on the how much foreign matter and debris
accumulates.
In many instances the front substrate gets cleaned with the rain, and you can
decrease the cleaning frequency. It is recommended to wipe the glass surface
with wet sponge or soft cloth.
Please do not clean the glass with cleaning agent which contains acid or
alkali.
To avoid potential electrical shock or burn, please clean the PV panels in the
early morning or at dusk. Do not clean the PV panels with damage to the glass
surface, backboard or wires.
8.2. Visual Inspection of PV Panels
Inspect the PV panels visually to find if there are appearance defect,
especially:
- If the glass is broken;
- Corrosion along the cells’ busbar. The corrosion is caused by moisture that has infiltrated into the modules when the surface encapsulation material damaged during the installation or transportation.
- If there is evidence of burning on the panel.
- Check the encapsulation of the connector with the cable.
- Ensure the PV panels are untouched with sharp objects.
- Ensure the PV panels are not shaded.
- Check the connection between the PV panels and the mounts and brackets.
8.3. Inspection of the Connector and the Cable
It’s recommended to implement the following preventive maintenance every 6 months:
- Check the connections between the PV panels and other off-grid components.
- Check the sealing gel of the junction box to ensure if it is crack or crevice.
Schedule – Renogy solar panel iteration/mix recommendation
SKU| Versions| Size/mm| Mounting hole number & size|
Recommended number of mounting holes| Mixable versions
---|---|---|---|---|---
RNG-10D-SS| G1| 341 x 266| 4-107| 4| /
RNG-30D-SS| G1| 570 x 341| 4-107| 4| /
RNG-50D-SS| G1| 601 x 498| 4-107| 4| G1 / G2 / G3
RNG-50D-SS| G2| 581 x 509| 4-107| 4| G1 / G2 / G3
RNG-50D-SS| G3| 578 x 503| 4-711| 4| G1 / G2 / G3
RNG-80D-SS| G1| 920 x 498| 20-149| 4| G1 / G2
RNG-80D-SS| G2| 938 x 509| 20-149| 4| G1 / G2
RNG-100D-SS| G1| 1074 x 798| 20-149| 4| G1 / G2 / G3
RNG-100D-SS| G2| 1076 x 509| 20-149| 4| G1 / G2 / G3
RNG-100D-SS| G3| 1062 x 530| 20-149| 4| G1 / G2 / G3
RNG-100MB| G1| 1038 x 533| 20-149| 4| /
RSP100D-BK| G1| 1100 x 509| 20-149| 4| G1 / G2
RSP100D-BK| G2| 1062 x 530| 20-149| 4| G1 / G2
RNG-175D| G2| 1262 x 699| 20-149| 4| G1 / G2
RNG-175D| G1| 1328 x 670| 20-149| 4| G1 / G2
RSP200D| G3| 1491 x 699| 20-149| 4| G1 / G2 / G3
RSP200D| G2| 1650 x 670| 20-149| 4| G1 / G2 / G3
RSP200D| G1| 1620 x 657| 20-149| 4| G1 / G2 / G3
RNG-320D| G1| 1665 x 1002| 4-14.56.5| 4| G1 / G2
RNG-320D| G2| 1665 x 1002| 4-14.56.5| 4| G1 / G2
RSP450D-120| G1| 1909 x 1134| 8-149| 4| /
RSP550D-144| G1| 2279 x 1134| 8-149;
4-11*7| 4| /
RNG-10DB-H| G1| 481 x 301| 6-Inner
φ8;Outer φ14| 6| G1 / G2
RNG-10DB-H| G2| 481 x 301| 6-Inner
φ8;Outer φ14| 6| G1 / G2
RNG-50DB-H| G1| 673 x 508| 6-Inner
φ6;Outer φ11| 4| G1 / G2 / G3
RNG-50DB-H| G2| 683 x 508| 6-Inner
φ6;Outer φ11| 4| G1 / G2 / G3
RNG-50DB-H| G3| 712 x 460| 6-Inner
φ6;Outer φ11| 4| G1 / G2 / G3
RNG-100DB-H| G1| 1219 x 546| 6-Inner
φ6;Outer φ12| 6| G1 / G2 / G3
RNG-100DB-H| G2| 1219 x 546| 6-Inner
φ6;Outer φ12| 6| G1 / G2 / G3
RNG-100DB-H| G3| 1093 x 582| 6-Inner
φ6;Outer φ11| 6| G1 / G2 / G3
RSP100DL-36| G1| 1093 x 582| 6-Inner
φ6;Outer φ11| 6| /
RNG-175DB-H| G1| 1504 x 673| 6-Inner
φ6;Outer φ12| 6| G1 / G2
RNG-175DB-H| G2| 1504 x 673| 6-Inner
φ6;Outer φ12| 6| G1 / G2
RSP200DB-72| G1| 1605 x 748| 6-Inner
φ6;Outer φ11| 6| /
Renogy Empowered
Renogy aims to empower people around the world through education and
distribution of DIY-friendly renewable energy solutions.
We intend to be a driving force for sustainable living and energy
independence.
In support of this effort, our range of solar products makes it possible for
you to minimize your carbon footprint by reducing the need for grid power.
Live Sustainably with Renogy
Did you know? In a given month, a 1kW solar energy system will…
Save 170 pounds of coal from being burned
Save 300 pounds of CO2 from being released into the atmosphere
Save 105 gallons of water from being consumed
Renogy Power PLUS
Renogy Power Plus allows you to stay in the loop with upcoming solar energy
innovations, share your experiences with your solar energy journey, and
connect with like-minded people who are changing the world in the Renogy Power
Plus community.
Renogy reserves the right to change the contents of this manual without notice.
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>