Schweitzer 7132 Substation Instrument Transformer Early Failure Detection Owner’s Manual
- June 13, 2024
- Schweitzer
Table of Contents
Substation Instrument Transformer Early Failure
Detection Using Time-Synchronized Measurement
Jason Byerly and Charles Jones
American Electric Power
Yanfeng Gong and Zachary Summerford
Schweitzer Engineering Laboratories, Inc.
Presented at the
50th Annual Western Protective Relay Conference
Spokane, Washington
October 10–12, 2023
7132 Substation Instrument Transformer Early Failure Detection
Abstract—Instrument transformers in power systems are prone to failure as a
result of aging, insulation degradationelectrical stress, mechanical damage,
and other factors. Failure othese transformers can have severe consequences
including relamis-operation, damage to other equipment, and safety risks. Athe
power grid ages, a large number of instrument transformersin service will
inevitably fail, leading to significant undesireconsequences. The lack of
economical conditioning monitorinsolutions for these instrument transformers
often results in thembeing run until they fail.
This paper presents a real-world abnormality of an extra-higvoltage (EHV)
coupling-capacitor voltage transformer (CCVTthat caused a 765 kV-bus relay
mis-operation and equipmentdamage from an overvoltage transient. The paper
examinevoltages recorded by different intelligent electronic devices
(IEDsconnected to the same station bus within the substation, showingthe
abnormality of the single CCVT. By examining past evenrecords triggered by the
relays connected to the voltagtransformer, we show abnormal voltage
measurements datinback months.
The paper proposes three methods to address the need for earldetection of
instrument transformer abnormalities before theybecome catastrophic failures.
These methods use timesynchronized measurements among IEDs to cross-check
anverify the integrity of measurement and provide early warning oany
measurement mismatch, which indicates potential instrumenttransformer failure.
The first method uses the built-in capabilitof a digital relay that can
process synchrophasor measuremenfrom as many as two other digital relays
connected to the saminstrument transformer. The paper discusses algorithms
that are
implemented to detect power system signal magnitude and angmismatches to
provide early warning and protection supervisionand avoid relay mis-operation.
This method is economical andoes not require additional devices. The second
method uses dedicated synchrophasor data processor that implements similaor
more sophisticated algorithms to detect instrumentransformer abnormalities.
The third method uses IEC 61850GOOSE messaging for power system signal
measuremenexchange among IEDs. The paper discusses the pros and cons oeach
method and how each method can be used in differentscenarios.
INTRODUCTION
Power system instrument transformers, which include current transformers (CTs)
and voltage transformers (VTs), play an essential role in the operation,
control, and protection of electrical power systems. Instrument transformers
provide input to metering and protective relays, allowing for accurate
monitoring of power system states and quick isolation of failed power system
components. Undetected instrument transformer failures pose significant safety
risks, including fires and explosions, that can lead to personnel injuries or
fatalities and damage to nearby equipment and infrastructure. Depending on the
failure mode, some failed instrument transformers may be properly isolated by
the protection system without causing cascading failure. Some failed
instrument transformers will provide incorrect measurements to protective
relays and cause relay mis-operations to isolate major power system assets
such as a substation or power lines.
Most of the existing work focuses on using measurements from different
instrument transformers to detect single-phase abnormalities. Synchrophasor
voltage measurements (magnitude and angle) at the same location are used to
detect instrument transformer abnormalities [1] [2]. These methods apply
advanced algorithms to improve security and dependability. A linear state
estimator has been implemented using measurements from different instrument
transformers within a substation to detect abnormalities within a substation
[3]. The proposed synchrophasor-based methods are implemented using a software
solution to provide warnings and situation awareness to system operators.
Reference [4] proposes a negative-sequence voltage-based method to detect
potential coupling-capacitor voltage transformer (CCVT) failure based on the
long-term negative-sequence voltage trending. Caution should be taken to
differentiate an external system disturbance from a potential CCVT failure for
this method.
Most instrument transformers have multiple outputs. For example, an extra-high
voltage (EHV) CCVT typically has 3–5 outputs from the same capacitor stack,
other than the secondaries tapped off at different positions. Similarly,
bushing CTs typically support multiple secondary windings with different turns
ratios. Manufacturers test and calibrate instrument transformers to meet the
measurement accuracy requirements, therefore measurements from different
secondary windings on the same CCVT or CT should be within the specified
measurement accuracy Fig. 1 shows an actual field event during which one of
the phases of a 765 kV CCVT experienced a sudden voltage surge.
Relays are connected to each of the two windings of the CCVT.
As a result of the voltage surge the relays connected to that secondary
winding of the CCVT was partially damaged and resulted in a bus relay trip.
The top two subplots in Fig. 1 show healthy A-phase and B-phase voltages. The
third plot shows the faulted C-phase voltage. These two relay event records
are aligned with GPS timestamps. The two healthy phase voltages from the same
CCVT almost perfectly overlap with each other.
However, the C-phase voltage from two relays began showing some degree of
deviation in magnitude before the sudden voltage surge in one of the
windings. It is reasonable to assume that the voltage deviation between two
windings has existed for some time before this event. If there were measures
in place to closely monitor the voltage deviation between two relays, this bus
tripping event could have been prevented.
Considering
the reliability of the instrument transformer, NERC PRC-005-2 requires
maintenance for voltages and current-sensing devices that do not have real-
time monitoring to be on a 12-month calendar year cycle [5]. If voltage- and
current-sensing devices connected to microprocessor relays are continuously
verified by comparison of sensing input value to an independent alternating
current (ac) measurement source, with alarming for unacceptable error or
failure, no periodic maintenance is required. Most modern substations are
equipped with multifunctional microprocessor relays that have protection
functions, such as overcurrent protection and distance protection, and support
various industry standard communication protocols such as synchrophasor
measurement and IEC 61850 GOOSE messaging [6] [7]. American Electric Power
(AEP) is moving toward microprocessor relay comparison to reduce maintenance
burdens and be proactive, rather than reactive, to instrument
transformer/microprocessor failures.
In this paper, we report three economical methods of monitoring the status of
an instrument transformer and providing an early warning and failure detection
method using synchrophasor measurement or GOOSE messaging. The first and third
methods do not require any additional hardware if the relays include the
required features and functions.
A. Direct Synchrophasor Data Exchange Between Relays A commercially available
relay family supports a built-in phasor data concentrator (PDC) function for
advance synchrophasor-based applications (e.g., inter-area oscillation
detection). The built-in PDC function allows the relay to directly receive
synchrophasor measurements from other relays through a serial-to-serial port
connection and makes these measurements available to relay programmable
protection and automation functions to enable instrument transformer failure
detection at a fast and deterministic speed. This feature can be used for
instrument transformer condition monitoring at a minimal cost.
B. Centralized Synchrophasor-Based Method
In this approach, an external device such as a Real-Time Automation Controller
(RTAC) is used to collecsynchrophasor measurement data through a built-in PDC
function. This external device provides broader instrumenttransformer
condition monitoring within a substation instead ofmonitoring an individual
instrument transformer.
C. IEC 61850 GOOSE Message-Based Detection Method IEC 61850 GOOSE messaging is
gaining popularity in modern digital relays. Although GOOSE messaging does not
add a time stamp to the analog measurement at a fixed interval, its fast rate,
for example 4 ms in this case, alleviates the measurement time stamp alignment
requirement based on the reasonable assumption that the current and voltage
magnitudes do not change significantly within a brief time window.
To test the validity of the three methods, we use a relay test set to generate
voltage and current signals simultaneously for the two microprocessor relays
under test. Both relays support synchrophasor and GOOSE messaging. Fig. 2
illustrates the
testing system setup. GOOSE messages are routed between relays though an
Ethernet switch. Synchrophasor data are routed through a direct serial-to-
serial communication and through an Ethernet switch to the RTAC. Both relays
are connected to IRIG-B time sources to provide an accurate time stamp in the
message and facilitate performance comparison. To simulate the former
instrument failure, we altered the magnitude or the phase of one of the relay
input signals to test the system response. Relay event records were collected
to generate the performance analysis shown in the following sections.
DIRECT SYNCHROPHASOR DATA EXCHANGE BETWEEN RELAYS
While many commercially available microprocessor-based protective relays
support the transmission of synchrophasor data to a remote terminal, one
widely used family of devices allows as many as two serial channels to receive
synchrophasor data from other devices. Protective relay Systems 1 and 2
monitor the same equipment on the power system using independent CT and VT
windings. By exchanging synchrophasor magnitude and angle information for the
secondary current and voltage observed by each system, a data comparison can
be made to detect an issue within the instrument transformers, secondary
wiring, or relay CT and PT circuitry within the protective device analog-to-
digital (A/D)converter. Many microprocessor-based protective relays will
employ self diagnostics that can detect system failures beyond this point,
providing monitoring for the entire instrument transformer system.
To employ synchrophasors in a microprocessor-based protective relay, a high-
accuracy time signal must be provided to the relay. With each device time-
synchronized, phasors are created at a fundamental frequency that uses a
specific point in time as a phasor reference. While magnitudes of voltages and
currents can be exchanged and compared easily between devices, comparison of
phase angles relies on a common reference for all devices to be effective. The
common time reference provided by Synchrophasor Protocol allows for direct
phase comparisons for each of the voltage and current phasors exchanged
between devices.
Synchrophasor Protocol defines a fixed message rate and time stamp. This means
that all selected magnitudes and angles are updated at a deterministic
interval. Time alignment also allows for a local analog value to be compared
to the remote analog value with certainty that any calculated error is a
system issue and not caused by a channel alignment, phasor reference
differences, or defined communication deadbands. The requirement is that a
dedicated Synchrophasor Protocol communication channel must be in place
between each relay and the peers it is working in with.
Elements are programmed into custom logic to compare each analog magnitude as
a ratio of Relay 1 to Relay 2 and can compare this ratio to a threshold used
for alarming. This method can be applied to each phase voltage and current
that is set to be transmitted over the synchrophasor channel. A small signal
cutoff should also be implemented to ensure at least one of the devices
detects the phase current or voltage magnitude above a pre-determined
threshold. Selecting a difference of 0.05 pu between Relay 1 and Relay 2
magnitudes and a small signal cutoff of 5% of nominal can be implemented using
the logic shown in Fig. 3.Because phase angles can vary
greatly in value, the alarm logic for angle comparison should use the
difference between the Relay 1 angle and Relay 2 angle as an operate quantity.
This value can be compared to a static angle threshold to determine if an
alarm should be issued. As with phase magnitudes, this logic should also be
secured with a signal cutoff threshold to ensure that an alarm condition is
not declared for conditions when primary equipment is out of service or
minimal load flow is present. This logic with a 10° alarm threshold can be
implemented as shown in Fig. 4.
An
additional consideration is that synchrophasors provide a phase angle within a
range of –179.99°–180.00°. Should a phase angle of any phasor fall close to
these boundaries, there is a chance that the reported value from one relay may
be a negative angle while the other is positive, creating a large difference
between them. When using a small alarm threshold such as 10° difference
between Relay 1 and Relay 2, custom logic can be implemented to ensure that
the smaller of the two angles between System 1 and System 2 phase angle
measurements is being used to alarm while maintaining reliability. This logic
is implemented as shown in Fig. 5.
While synchrophasors provide a deterministic message rate that
can be applied to produce consistent timing for alarms that operate closer to
protection speeds than other methods, there are several user-defined options
within Synchrophasor Protocol that can affect the response time of these
elements. While IEEE C37.118-2011 defines message rates as high as 120
messages per second, many devices do not support rates that high or may become
overburdened at high rates. A lower message rate may be selected to meet
desired delay specifications within the operating parameters of the selected
hardware. IEEE C37.118-2011 also defines two classes of synchrophasors:
protection and measurement. The standard outlines specifications for both
classes including latency,
filtering, accuracy, over- and undershoot, as well as other parameters. Each
class should be reviewed thoroughly to determine which provides
characteristics that will meet the desired application specifications.
Lab tests provided the results shown in Fig. 6 using two microprocessor-based
relays of the same family, each publishing a synchrophasor stream on one
serial port while receiving the stream from the other device on a second
serial port. The synchrophasor channels were set to send P class information
with a wide bandwidth filter at a rate of 30 messages per second. Both relays
are configured with a 300:1 CT ratio, 3000:1 PT ratio, and a nominal secondary
VL-L of 115 V.
Simulating a case where the A-phase voltage on Relay 2 experiences a 10%
magnitude step reduction produces the results in Fig. 6.
With the magnitude step
change initiated at t = 0 ms, it can be observed that Relay 2 has a delay of
67 ms, or approximately 4 cycles, before synchrophasor data are sent showing
the reduced magnitude. Relay 1 receives these data 14 ms later, and begins
timing its alarm 57 ms later. This is a total of 138 ms of delay from
magnitude step change to Relay 1 alarm pickup. Simulating a case where the
A-phase voltage on Relay 2 experiences a 15° angle step change produces the
results in Fig. 7.
With the angle step change initiated at t = 0 ms, we observed that Relay 2 has
a delay of 80 ms, or approximately 4.8 cycles, before data are sent showing
the full value of the changed angle.
Relay 1 receives these data in the same channel delay of 14 ms later, and
begins timing its alarm 57 ms after receipt of the new angle measurement. This
is a total of 160 ms of total delay from the step angle change to remote relay
alarm pickup.
This testing shows that the
method described can be implemented for both phase magnitude and phase angle
comparisons with a deterministic implementation using microprocessor-based
relays both as synchrophasor servers and clients.
CENTRALIZED SYNCHROPHASOR-BASED METHO
This section describes a method to provide Asset Health Monitoring (AHM) for
instrument transformers and redundant microprocessor relays using
Synchrophasor Protocol and an RTAC with a built-in PDC function. AHM for
instrument transformers and intelligent electronic devices (IEDs) can be
accomplished by comparing PMUs of similar specifications. The PMU from
redundant instrument transformers should produce equivalent measurements,
allowing for some margin because of manufacturing tolerances.
Additional RTAC hardware is needed for this approach.
RTACs are widely deployed in substations for data management, AHM, and
deterministic mission-critical control applications such as power system
stability monitoring. For many substations with an existing RTAC, there is no
significant additional hardware cost when implementing AHM for instrument
transformers and relay systems. There are several advantages to using an RTAC
for this application:
- One RTAC device is typically sufficient to cover the instrument transformer condition monitoring application for the entire substation.
- RTACs have a built-in powerful deterministic logic processor that allows for more flexibility and sophisticated failure detection logic, including comparing more than two synchrophasor measurements from the same instrument transformer.
- The modular design of the instrument transformer monitoring function can be easily replicated, creating multiple instances to monitor more instrument transformers.
- RTACs have a built-in human-machine interface (HMI), including a substation one-line diagram, that visualizes the condition of each instrumenttransformer and seamlessly provides SCADA communications related to instrument transformer condition monitoring.
Within RTAC implementation, more synchrophasormeasurements from different relays connected to the sameinstrument transformer windings can be used to provide moresensitive failure detection. The decision logics shown in Section II for point-to-point connection are modified as shownin the following equations: Alarm If 1.05 > (Max(Relay_Mags) / Minimum(Relay_Mags> 0.95 AND (Minimum(Relay_Mags) > 0.05)
Alarm If Max(ABS(Relay_Ang_x – Relay_Ang_y)) > 10° AND(Minimum(Relay_Mag) >
0.05) For magnitude comparison, the maximum value and minimum value of the
phasor magnitudes are used for the decision logic. For phase angle comparison,
the angledifference between each pair of synchrophasor measurementsis
calculated and the maximum of the phase angle difference isused for
abnormality detection.
Fig. 8 and Fig. 9 illustrate the instrument transformemonitoring function
diagram that shows normal condition andalarm condition, respectively, under
different testing conditionsas used in the previous sections.
Modern RTACs have deterministic
processing times as fast as tens of milliseconds. The real-time condition
status output for the instrument transformer can be programmed as a Sequence
of Events (SOE) with a more elaborate message, as illustrated in Fig. 10. This
status output can be incorporated into different protection and control
applications as a supervisor or sent to HMIs to alert operators.
GOOSE MESSAGING BETWEEN RELAYS
This method takes the current/voltage magnitude and angle signals received
from the System 1 relay through GOOSE messaging and compares them to the
current/voltage magnitude and angle signals in the System 2 relay. The System
1 and System 2 relays see the same current parameters but from different CTs.
The System 1 and System 2 relays see the same voltage parameters but from
different windings on a CCVT or PT. This method not only monitors the
instrument transformers, but the relay wiring and relay internal current and
voltage input circuitry as well. The System 1 relay will send the
current/voltage magnitude and angle data using analog GOOSE messaging. The
System 2 relay will subscribe to these data and perform logic comparing the
System 1 data to the current and voltage magnitude and angle data directly
measured by the System 2 relay.
The data signals from the System 1 relay are transmitted to the System 2 relay
using IEC 61850 analog GOOSE messaging. Care must be taken with these data
because the signal is not necessarily continuous. These data are transmitted
to the System 2 relay under supervision of an IEC 61850 MMXU deadband setting.
For the current magnitude signals, a 0.001% change was chosen and must occur
before a new data value is transmitted from the System 1 relay. For the
voltage magnitude signals, a 0.1% change was chosen and must occur before a
new data value is transmitted from the System 1 relay. For the current and
voltage angle signals, a 0.1% change was chosen and must occur before a new
data value is transmitted from the System 1 relay.
For a 345 kV system with a CCVT ratio of 3000:1 and a CT ratio of 300:1, the
deadband will translate as follows:
- Voltage magnitude deadband: 825 V primary
- Voltage angle deadband: 0.36°
- Current magnitude deadband: 0.69 A primary
- Current angle deadband: 0.36°
The set points chosen for comparison are 5% for magnitude and 10° for angle.
Therefore, if the difference between the System 1 and System 2 data exceeds
these set points, an alarm will be generated. A 60-second delay is also
introduced to avoid any false larming because of sudden system changes. These
sudden system changes could result in momentary error exceeding the set points
because of GOOSE deadband and time delay to transmit and receive the data.
This method is not intended to provide fast detection to disable protection
and avoid a false trip; its mission is to monitor steady-state conditions and
provide alarming.
The System 2 relay, which processes the data from the System 1 relay, must
have a supervision level such that if the System 1 data are less than this
supervision level, data comparison will be blocked. This supervision reflects
the System 1 data and the deadband associated with them. In addition, the
comparison set point plays a part in the selection of this supervision value.
With a 0.001% deadband level and a magnitude set point selection of 5%, (1)
determines a good setting for this supervisory set point:
where:
X = Supervisory set point factor
Y = Mismatch set point
Z = GOOSE deadband in primary amperes
C = CT ratio
The current supervision is calculated from the following
parameters:
- X = 0.95(0.69 A)/(300(1 – 0.95)
- X = 0.0437
- Multiply by 2 for security. Round up.
- The chosen supervision set point is 0.1 A secondary.
- Translated to primary amperes, X = 0.1(300) = 30 A.
Note that regardless of the CT ratio, the supervisory set point factor
will compute to the same value. Only the primary ampere value will change per
the CT ratio.
Care was taken for the method of angle comparison. One item is time alignment.
The GOOSE messaging method will not be time stamp aligned. For example, if the
System 1 relay transmits a value of 10° and the phasors are rotating at a slip
frequency where the System 2 relay is indicating 15° at the moment of
comparison, this will be a problem. Therefore, a method must be applied that
would allow for this. AEP also has two relay systems. Each system is a
different relay manufacturer. Manufacturer 1 defines angle 0° to be equated to
the A-phase voltage. Manufacturer 2 defines angle 0° to be equated to the
positive-sequence voltage. This introduces alignment error between the two
systems. Testing by comparing the individual phase-to-ground angles will not
work.
We determined that instead of testing the phase-to-ground angles, the phase-
to-phase angles should be tested to eliminate alignment errors. To reiterate,
the goal with this method is not to provide fast detection, only to detect
errors during steady state.
Fig. 11 illustrates detection and timing data taken from lab tests for
magnitude comparison. The comparison was made between two different relay
manufacturers.
The data show the
response to a voltage magnitude change of 11% on one of the relays. The
diagram shows that from the time of the change until the algorithm detects the
change, approximately 222 ms have expired.Fig. 12 illustrates detection and
timing data taken from lab (1) tests for angle comparison. The comparison was
made between two different relay manufacturers.
The data show the response to a phase angle change of 10° on one of the
relays. The diagram shows that from the time of the change until the algorithm
detects the change, approximately 167 ms have expired.
The data shown in Fig. 13 are from field-connected devices protecting a
transmission line. These data show the angle data captured from the System 1
and System 2 relays, as well as the validity of the GOOSE data from the System
1 relay versus the measured data from the System 2 relay. The data were
recorded in the System 2 relay.
- VAFA: System 2 A-Phase Voltage Angle
- RA015: System 1 A-Phase Voltage Angle
- VBFA: System 2 B-Phase Voltage Angle
- RA016: System 1 B-Phase Voltage Angle
- VCFA: System 2 C-Phase Voltage Angle
- RA017: System 1 C-Phase Voltage Angle
- LIAFA: System 2 A-Phase Current Angle
- RA018: System 1 A-Phase Current Angle
- LIBFA: System 2 B-Phase Current Angle
- RA019: System 1 B-Phase Current Angle
- LICFA: System 2 C-Phase Current Angle
- RA020: System 1 C-Phase Current Angle
This magnitude comparison has been in service at AEP for about 14 years. The angle comparison has been in service at AEP for about one year. This is a real-time system, i.e., this system observes data in real time rather than after the fact. Initially, the test was magnitude only. Recently, angle comparison was added to the line protection schemes. The test has also been added to bus differential schemes. It is slated to be added to transformer schemes on future standard updates. In addition, the monitored data are being recorded in each relay for post-event analysis.
For CCVTs, the GOOSE method monitors separate windings on the CCVT. If the problem with the CCVT is located in the capacitive circuit, which is common to both CCVT windings, the GOOSE comparison method will not detect this condition; both relays will see the same voltage. To detect this condition, a method of monitoring the zero-sequence voltage was implemented. This detection has two set points. The lower set point has a fixed time delay to alarm. The next set point, set higher, has a much faster time delay to alarm. The goal of real-time monitoring is to eliminate the need for manual periodic testing to satisfy NERC PRC-005-2 maintenance requirements, therefore reducing costs.
SUMMARY
Instrument transformers are pivotal components in power systems and are
vulnerable to failures resulting from aging, insulation degradation,
electrical stress, and mechanical damages. These failures, as highlighted by
the severe consequences such as relay mis-operation and equipment damage,
underscore the importance of standards such as NERC PRC-005-2. This NERC
standard mandates either manual maintenance at the maximum interval of 12
years or deploying continuous monitoring solutions.
Recognizing the need to align with standards such as NERC PRC-005-2 and
preemptively detect instrument transformer irregularities, the paper
introduced three economical methods using synchrophasor measurement or GOOSE
messaging, which are built-in functions of modern IEDs. The proposed methods
for early detection of instrument transformer abnormalities offer several
benefits, especially when viewed in light of the challenges associated with
power system management and maintenance. The benefits of the proposed methods
include the following:
Early Detection of Abnormalities: The primary advantage of these methods is
the proactive identification of potential transformer failures. Early
detection can prevent catastrophic events, safeguarding the integrity of the
power grid and protecting expensive equipment from irreversible damage.
Cost Savings: Addressing instrument transformer abnormalities in their early
stages can lead to substantial cost savings. This proactive approach can
prevent more expensive repairs or replacements if the equipment fails and can
also minimize downtime, thus ensuring uninterrupted power supply and revenue
generation. All the proposed approaches are continuous online monitoring
methods that can exempt utilities from the NERC PRC-005-2 requirements of
enhanced reliability and safety.
Enhanced Reliability and Safety: Reliable instrument transformers are crucial
for the safety and stability of power systems. By ensuring these transformers
function optimally, the methods enhance the overall reliability of the power
grid and reduce safety risks associated with equipment failures, such as fires
and other hazards.
Optimal Use of Resources: The first and third methods, which use the built-in
capability of digital relays, are economical and do not require additional
devices. This efficient use of existing resources ensures optimal resource
allocation and reduces the need for further investment.
Advanced Monitoring: Using a dedicated synchrophasor data processor, as
mentioned in the second method, allows for the implementation of sophisticated
algorithms. This ensures greater accuracy in detecting abnormalities, even in
complex power system scenarios.
Flexibility and Adaptability: The three proposed methods cater to different
scenarios, offering utilities the flexibility to choose the most suitable
approach based on their infrastructure, budget, and requirements.
Enhanced Record Keeping and Analysis: By employing time-synchronized
measurements, utilities can maintain a consistent log of measurements and
events. This can be invaluable for post-event analysis, predictive
maintenance, and for compliance with regulations like NERC PRC-005-2.
Improved Protection: By cross-checking measurements and identifying
mismatches, these methods can prevent relay mis-operation, ensuring that
protective mechanisms in the power grid function as intended.
Stakeholder Confidence: Regular and efficient monitoring, coupled with
proactive maintenance, can boost confidence among stakeholders, including
investors, regulatory bodies, and consumers. A reliable power system is
foundational to modern economies, and these methods ensure consistent delivery
on this front.
In conclusion, the proposed methods not only serve to enhance the reliability
and safety of the power system but also position utilities to make informed
decisions, optimize resources, and realize significant cost savings in the
long run.
REFERENCES
- M. Rhode, M. A. Khan, J. Wold, G. Zweigle, and J. Bestebreur, “Voltage Transformer Failure Prediction With Synchrophasor Data,” 49th Annual Western Protective Relay Conference, Spokane, WA, October 2022.
- B. Cui, A. K. Srivastava, and P. Banerjee, “Synchrophasor-Based Condition Monitoring of Instrument Transformers Using Clustering Approach,” IEEE Transactions On Smart Grid, Vol. 11, Issue 3, May 2020, pp. 2688–2698.
- L. Zhang, H. Chen, Q. Wang, N. Nayak, Y. Gong, and A. Bose, “A Novel On-Line Substation Instrument Transformer Health Monitoring System Using Synchrophasor Data,” IEEE Transactions On Power Delivery, Vol. 34, Issue 4, August 2019, pp. 1451–1459.
- B. Kasztenny and I. Stevens, “Monitoring Ageing CCVTs, Practical Solutions with Modern Relays to Avoid Catastrophic Failures,” 2007 Power Systems Conference, Clemson, SC, March 2007.
- NERC Standard PRC-005-2 – Protection System Maintenance. Available: http://www.nerc.com.
- IEEE Standard C37.118.1-2011, IEEE Standard for Synchrophasor Measurements for Power Systems.
- IEC 61850 Standard – Generic Object Oriented Substation Event (GOOSE) protocol.
BIOGRAPHIES
Jason Byerly received his BS from The Ohio State University in 2004 and is
currently pursuing his MSEE from the University of Idaho. He joined American
Electric Power (AEP) in 2004 and has supported several roles in protection and
control engineering. Jason is a registered Professional Engineer (PE) in Ohio,
a senior member of IEEE, contributor to IEEE PSRC, and a member of IEC 61850
WG 10.
Charles Jones is a staff engineer with American Electric Power (AEP) in New
Albany, Ohio. He works in Protection and Control Standards where for the past
23 years has designed AEP’s Transmission Standard P&C Designs including line,
transformer, bus, and shunt reactor protection. He has been with AEP since
1982 working in protection and control, SCADA, and metering. Charles received
his BSEE in electrical engineering from West Virginia University in 1982 and
an MEEE in electrical engineering from the University of Idaho in 2011.
Yanfeng Gong earned his BS in electrical engineering with a focus on power
systems from Wuhan University, China, in 1998. He went on to obtain his MS
from Michigan Technological University in 2002 and his Ph.D. from Mississippi
State University in 2005, continuing his specialization in power systems.
Yanfeng worked as a research engineer at Schweitzer Engineering Laboratories,
Inc. (SEL) from 2005 to 2013. He later served as a principal engineer and
supervisor at American Electric Power (AEP) in the Advanced Transmission
Studies & Technologies (ATST) department from 2013 to 2019.
In 2019, he returned to SEL, assuming the role of principal engineer. In
addition to his professional endeavors, Yanfeng has played an active role in
industry committees. He served as the past chair of the IEEE Transient
Analysis and Simulation Subcommittee (TASS) and is currently the vice chair of
the IEEE Analytic Methods for Power Systems (AMPS) technical committee. He has
been an active contributor to several industry standardization efforts and
technical working groups. Yanfeng is a senior member of IEEE and is a
registered Professional Engineer (PE) in Washington.
Zachary Summerford earned his BS in electrical and computer engineering with a
focus on power systems and digital logic design from The Ohio State University
in 2012. He earned his ME in electrical engineering with a focus on power
systems from the University of Idaho in 2022. He began working for Schweitzer
Engineering Laboratories, Inc. (SEL) in 2012 and is currently a senior
application engineer for protection. He is a member of IEEE and a registered
Professional Engineer (PE) in Ohio.
© 2023 by American Electric Power and
Schweitzer Engineering Laboratories, Inc.
All rights reserved.
20230908 • TP7132-01
Documents / Resources
|
Schweitzer 7132 Substation Instrument Transformer Early Failure
Detection
[pdf] Owner's Manual
7132 Substation Instrument Transformer Early Failure Detection, 7132,
Substation Instrument Transformer Early Failure Detection, Instrument
Transformer Early Failure Detection, Transformer Early Failure Detection,
Early Failure Detection, Failure Detection
---|---
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>