ferroamp PD10008 ESS Power Case Installation Guide
- June 13, 2024
- ferroamp
Table of Contents
Installation manual
PD10008 ESS Power Case
**
**
ESS Power Case
PD10008
Rev A02
Revision history
Date | Revision | Note |
---|---|---|
2022.05.02 | A01 | First release, English only |
2023.01.12 | A02 | Updated ESO/SSO connection and ToC |
2023.02.09 | A02b | Correction under “Commissioning – Start up” |
PN: PD10008, Rev: A0, Copyright Ferroamp AB (publ) 2023. Document subject to
change without prior notice.
Verify that you have the latest version of this manual on our website.
www.ferroamp.com/downloads
Introduction
In this booklet you will find installation instructions for your ESS Power
Case. Please read the instructions carefully to ensure that no unnecessary
errors occur.
Depending on the power configuration of the ESS System you will install the
system with 1 or 2 ESO Modules (ordered separately).
1.1 Included items
The following articles are included upon delivery of a ESS Power Case:
Article | Amount |
---|---|
ESS Power Case | 1 |
Mounting rod ESO Module | 2 |
Mounting Bracket ESO Module | 1 |
Warning sticker (Eng/Swe) | 1-1 |
Warranty leaflet | 1 |
1.2 Warnings and recommendations
RECOMMENDATION! Read through the manual before installation.
RECOMMENDATION! Only use this product according to the instructions supplied
to avoid any danger.
WARNING! The electrical installations shall be conducted by authorized
personnel and in accordance with local and national electrical standards and
safety measures.
WARNING! You are not allowed to connect units to the DC nanogrid when it
is energized.
WARNING! Risk of electrical shock/arc if the product is not used
according to the instructions in the manual.
WARNING! Do not use the product if you suspect the product is damaged.
Let it be inspected by qualified personnel before use.
WARNING! Do not use the product if the housing has been tampered with or
not intact, for example during repair, do not touch exposed parts.
NOTE! The warranty does not apply if the product has been modified,
tampered with, or not installed in accordance with this manual.
1.3 Explanation of safety notices
The lightning symbol in an equilateral triangle warns of dangerous electrical
voltage.
The exclamation mark in an equilateral triangle is intended to warn the user
that negligence of this information can be life-threatening!
The exclamation mark in a circle is intended to inform the user that neglect
of this information may be associated with bodily harm and / or damage to the
product.
1.4 Dimensions
All dimensions are in mm if nothing else is specified.
1.5 Bottom connections
- External ground connection (PE)
- RJ45 cable grommet (CAN)
- Cable gland M32 (Ø 13-21mm)
- 4. Multi grommet (2 x Ø 4-8mm, 2 x Ø 9-12mm)
- Multi grommet (2 x Ø 4-8mm, 2 x Ø 9-12mm)
1.6 Internal components & connections
Installation
The installation section will take you step by step through the process of
installing an ESS Power Case.
NOTE! Ferroamp does not take responsibility for damages on the product
caused by incorrect or careless installation.
NOTE! We recommend that you use end terminals for all connection points
that have multi-threaded conductors.
Do not work alone. In an emergency, someone else’s presence may be necessary!
The electrical installation must comply with national / local laws and
regulations, appropriate standards and applicable requirements from
recognized organizations.
The electrical installation must be carried out by a qualified installer and
in accordance with the applicable electrical standard.
Ensure that the location of the ESS Power Case never is an obstacle to an
emergency evacuation path. In accordance with national and local laws.
2.1 Placement
NOTE! Ferroamp does not take responsibility for installations where the
following stated criteria are not met.
NOTE! Make sure that the ESS Power Case and the ESS Battery are
positioned close enough for the premade battery cables to reach.
Make sure that the chosen location for installation is in line with the
following criteria:
- Indoor environment is protected from rain and direct sunlight.
- Ambient temperatures must not fall below 0 °C and not exceed 45 °C.
- The environment must be non-condensing, relative humidity below 95%.
- Have free space around the ESS Power Case according to the following figures:
2.1.1 To remove the front cover by first unscrewing the two side thumbscrews (1 & 2), slide the front up (3) and lift it off (4). Finish with unscrewing the PE-cable from the baseplate (5). 2.1.2To access the distribution panel, unscrew the two slotted screws in the bottom front (2) and the top (3) then lift of the poke protection:
2.1.3 Mount the base plate on the wall, see dimensions for position of mounting holes (mm):
2.2 ESS Battery connection
2.2.1 Remove the ring terminals from the pre-made battery cables included with
the ESS Battery Controller by cutting them off.
2.2.2 Poke holes in the multi grommets and feed Bat+, Bat- and PE cables
through the smaller grommets. 2.2.3 Attach isolated ferrules and connect to
the cables to the following terminals:
2.2.4 Make sure that all terminals are tightened to 2.5 Nm, use a torque
wrench.
2.2.5 Remove the cable grommet for the RJ45 cable, poke a hole, cut it open
along one side and attach it around the communication cable. Connect the
communication cable from the ESS Battery to the outer port, “CAN 2”: The ESS
Battery is now connected!
2.3 Connection of SSO:s (1-3)
If you do not have any SSOs you can skip this section.
NOTE! To calculate correct cable dimensions you can use Ferroamp’s online
cable calculator, available at www.ferroamp.com
under the support section.
2.3.1 Feed the SSO cable through one of the larger grommets: 2.3.2 Feed
through ~40 cm of cable for and peel of ~35 cm of isolation.
2.3.3 Connect to the following terminals:
Make sure that all terminals are tightened to 2.5 Nm, use a torque wrench.
If you have 2 or 3 SSOs just repeat the steps above for each SSO.
2.4 DC nanogrid connection
NOTE! To calculate correct cable dimensions you can use Ferroamp’s online
cable calculator, available at www.ferroamp.com
under the support section.
2.4.1 Depending on the cable diameter used for the DC link, feed the cable
through the M32 cable gland or one of the larger grommets.
2.4.2 Peel of the cable isolation according to instruction in section 2.2.
2.4.3 Connect the DC nanogrid cable (L+, L- & PE) to the following terminals.
2.4.4 Make sure that all terminals are tightened to 2.5 Nm, use a torque
wrench.
Make sure that the DC nanogrid is connected to correct terminals.
2.5 Connection overview
2.5.1 Verify the correct polarity of all connected cables.
2.5.2 Control that all terminals are fastened with 2.5 Nm.
2.5.3 The key holes seen in the image below can be used to secure the cables with extra cable ties if needed.
2.6 Install ESO Modules
The ESS Power Case can be configured with either 1 or 2 ESO Modules depending
on the power configuration of the ESS System.
2.6.1 Align the ESO module against the back plate. Look from the side to
ensure that the connectors are aligned. When alignment of the connector is
good gently lower the ESO module in place, one module at the time:
a. 1 x ESO Module: Secure the ESO Modules with the mounting bracket as seen in
the images above.
2.7 Assembly finish
2.7.1 Mount the poke protection and re-attach the PE-cable to the base plate.
2.7.2 Attach the warning sticker on the poke protection.
2.7.3 Commission the system, see section 3.
2.7.4 Re-attach the PE cable to the baseplate before mounting the front cover.
Commissioning – Start up
NOTE! If this is the first time starting up the EnergyHub system you need to follow the commissioning guide included with the EnergyHub (available at www.ferroamp.com ).
- Turn on the EnergyHub.
- Close the breaker on the ESS Power Case.
- Close the breaker on the ESS Battery and press the start button for 5 seconds until it rings.
- When the system is on the battery will calibrate during the first 24 hours. During this time, you should set the charge reference to 1 kW in the system configuration (www.portal.ferroamp.com).
- After the calibration has finished you can configure the battery in the system configuration after you desired use case.
Smart
Electricity Control
Documents / Resources
|
ferroamp PD10008 ESS Power
Case
[pdf] Installation Guide
PD10008, PD10008 ESS Power Case, ESS Power Case, Power Case, Case
---|---
|
ferroamp PD10008 ESS Power
Case
[pdf] Instruction Manual
PD10008 ESS Power Case, PD10008, ESS Power Case, Power Case, Case
|
ferroamp PD10008 ESS Power
Case
[pdf] Instruction Manual
PD10008 ESS Power Case, PD10008, ESS Power Case, Power Case, Case
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>