HUAWEI SUN2000-4.95KTL-NHL2 SmartACBox User Guide

June 13, 2024
Huawei

HUAWEI SUN2000-4.95KTL-NHL2 SmartACBox

HUAWEI SUN2000-4.95KTL-NHL2 SmartACBox

NOTICE

  1. The information in this document is subject to change without notice. Every effort has been made in the preparation of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute a warranty of any kind, express or implied.
  2. Before replacing the device, carefully read the SUN2000-4.95KTL-NHL2 User Manual to get familiar with product information and precautions.
  3. Before replacing the device, check whether the configurations of SUN2000L-(4.125KTL– 4.95KTL)-JP and SUN2000-4.95KTL-JPL0 can be viewed. If they can be viewed, record the parameter settings for setting or checking parameters after the replacement.
  4. Before replacing the device, check whether the cables are long enough. If not, prepare appropriate cables.

SUN2000L-(4.125KTL–4.95KTL)-JP Replacement Scenarios

SUN2000L-\(4.125KTL–4.95KTL\)-JP Replacement Scenarios

Removing SUN2000L-(4.125KTL–4.95KTL)-JP

  • Before removing the original SUN2000, ensure that the DC switch on the SUN2000 and all the switches connected to the SUN2000 are set to OFF. Otherwise, the high voltage of the SUN2000 may result in electric shocks.
  • After the SUN2000 is powered off, the remaining electricity and heat may still cause electric shocks and body burns. Therefore, put on protective gloves and dielectric boots and begin operating the SUN2000 with specialized insulation tools five minutes after the power-off.

Removing Cables from SUN2000L-(4.125KTL–4.95KTL)-JP for Future Use

  1. Power off the SUN2000 to be replaced.

  2. Remove the AC connector and remove the AC output power cable from the mating socket for future use.
    Removing Cables from SUN2000L-\(4.125KTL–4.95KTL\)-JP for Future
Use

  3. Remove the DC connectors and use a cable cutter to cut off the terminals of DC input power cables. Set the cables aside for future use.
    NOTICE
    The DC terminals of SUN2000L-(4.125KTL–4.95KTL)-JP must be cut off. If the DC connectors of SUN2000L-(4.125KTL–4.95KTL)-JP are directly connected to SUN2000-4.95KTL-NHL2, the SUN2000 may be burnt.
    Removing Cables from SUN2000L-\(4.125KTL–4.95KTL\)-JP for Future
Use

  4. Remove the signal cable connector from the COM port for future use.
    Removing Cables from SUN2000L-\(4.125KTL–4.95KTL\)-JP for Future
Use

  5. Disconnect the PE cable and remove the crimped OT terminal. Set the cable aside for future use.
    Removing Cables from SUN2000L-\(4.125KTL–4.95KTL\)-JP for Future
Use

Removing SUN2000L-(4.125KTL–4.95KTL)-JP

  1. (Optional) Open the anti-theft lock.

  2. Remove the two hex screws.
    Removing SUN2000L-\(4.125KTL–4.95KTL\)-JP

  3. Remove the SUN2000 from the rear panel.

Installing SUN2000-4.95KTL-NHL2

  1. (Optional) Install the locking screw for the DC switch.
    Installing SUN2000-4.95KTL-NHL2

  2. Remove the native hanging kit from SUN2000-4.95KTL-NHL2.
    Installing SUN2000-4.95KTL-NHL2

  3. Install the hanging kit delivered with SUN2000- 4.95KTL-NHL2.
    Note

    • The marking-off template, mounting bracket, and M6x60 expansion bolts delivered with SUN2000-4.95KTL-NHL2 are not used during replacement.
    • Prepare an anti-theft lock suitable for the lock hole diameter (Ф8 mm) and ensure that the lock can be installed successfully. An outdoor waterproof lock is recommended.
      Installing SUN2000-4.95KTL-NHL2
  4. Install the SUN2000 on the mounting bracket.

  5. Tighten screw assemblies.
    Installing SUN2000-4.95KTL-NHL2

Completing Electrical Connections of SUN2000-4.95KTL-NHL2

  1. Install the PE cable for SUN2000-4.95KTL-NHL2.
    NOTICE
    Before connecting cables, ensure that the DC switch on the SUN2000 and all the switches connected to the SUN2000 are set to OFF. Otherwise, the high voltage of the SUN2000 may result in electric shocks.
    NOTE

    • It is recommended that silica gel or paint be used around the ground terminal after the PE cable is connected.
    • It is recommended that you connect the PE cable to the right ground point and reserve the other ground point.
      Completing Electrical Connections of SUN2000-4.95KTL-
NHL2
  2. Install the WLAN antenna
    Completing Electrical Connections of SUN2000-4.95KTL-
NHL2

  3. Install the AC output power cable for SUN2000-4.95KTL-NHL2
    Completing Electrical Connections of SUN2000-4.95KTL-
NHL2

  4. Install DC input power cables for SUN2000-4.95KTL-NHL2
    NOTICE

    • Ensure that the PV module output is well insulated to ground.
    • Use the positive and negative Staubli MC4 metal terminals and DC connectors supplied with the SUN2000. Using incompatible positive and negative metal terminals and DC connectors may result in serious consequences. The caused device damage is not covered under warranty.
    • The DC input voltage of the SUN2000 cannot exceed the maximum input voltage under any condition.
    • Before installing DC input power cables, label the cable polarities to ensure correct cable connections.
    • If the polarities of the DC input power cables are reversed, do not operate the DC switch or the positive/negative connector immediately. Failing to do so may cause device damage, which is not covered under warranty. Wait until the night when solar irradiance declines and the PV string current drops to below 0.5 A. Then set the DC switch to OFF, remove the positive and negative connectors, and correct the polarities of the DC input power cables.
      Assembling DC connectorsAssembling DC connectors Installing DC Input Power Cables
      NOTE
      If the original DC input power cables are not long enough, add DC input extension cables.
      Installing DC Input Power Cables
      Installing DC Input Power Cables
  5. Install signal cables for SUN2000-4.95KTL-NHL2.
    Installing DC Input Power Cables

Checking the Installation of SUN2000-4.95KTL-NHL2 and Powering On the SUN2000

Post-Installation Check

No Acceptance Criteria
1 The SUN2000 is installed correctly and securely
2 The WLAN antenna is installed correctly and securely.
3 Cables are routed properly as required by the customer.
4 Cable ties are evenly distributed and no burr exists.
5 The PE cable is connected correctly and securely
6 The DC switch and all the switches connected to the inverter are set to OFF
7 The AC output power cable, DC input power cables, and signal cables are

connected correctly and securely.
8| Unused terminals and ports are covered by watertight caps
9| The installation space is proper, and the installation environment is clean and tidy.

Powering On the SUN2000

NOTICE

Before turning on the AC switch between the SUN2000 and the power grid, check that the AC voltage is within the specified range using a multimeter.

  1. Turn on the AC switch between the SUN2000 and the power grid.

  2. (Optional) Remove the locking screw beside the DC switch.
    Powering On the SUN2000

  3. Turn on the DC switch (if any) between the PV string and the SUN2000.

  4. Turn on the DC switch at the bottom of the SUN2000.

Commissioning SUN2000-4.95KTL-NHL2

  1. Download and install the latest installation package of the app.
    Method 1: Search for Fusion Solar in Huawei AppGallery.
    Method 2: Visit https://solar.huawei.com using your mobile phone browser.
    Commissioning SUN2000-4.95KTL-NHL2
    Method 3: Scan the QR code.
    QR-Code

  2. Access Device commissioning. Commissioning SUN2000-4.95KTL-NHL2

  3. Connect to the solar inverter WLAN and log in as installer to access the device commissioning screen.
    Commissioning SUN2000-4.95KTL-NHL2

  4. Choose Maintenance > Device replacement, select the type of the original device, and complete the replacement.
    Commissioning SUN2000-4.95KTL-NHL2

  5. (Optional) If you need to set other parameters, tap Settings.
    Commissioning SUN2000-4.95KTL-NHL2

  6. Connect the SUN2000 to the management system.
    SmartLogger1000 Networking
    Choose Maintenance, log in to the SmartLogger1000 as Advanced  User or Special User, and choose Device Mgmt. to connect the new SUN2000 to the system.asSmartLogger1000 Networking SmartLogger1000A/SmartLogger3000 Networking
    Connect to the Smart Logger WLAN. Log in to the app as Advanced User or Special User for the SmartLogger1000A, or as installer for the SmartLogger3000. Choose Maintenance > Device Mgmt. to connect the new SUN2000 to the system.SmartLogger1000A/SmartLogger3000
Networking NOTE
     You can also manage devices on the SmartLogger WebUI. Log in to the SmartLogger WebUI as Advanced User or Special User for the SmartLogger1000 or 1000A, or as an admin user for the SmartLogger3000. Choose Maintenance > Connect Device to connect the new SUN2000 to the system.SmartLogger1000A/SmartLogger3000 Networking

  7. Log in to the SmartPVMS and navigate to the Device Management page to replace the SN of the old SUN2000 with the SN of the new SUN2000. The historical data of the old SUN2000 will be inherited.
    SmartLogger1000A/SmartLogger3000 Networking
    NOTE
    You can also complete historical data inheritance in the FusionSolar app. Log in to the app and choose Device management > Device Replacement to replace the SN of the old SUN2000 with the SN of the new SUN2000. The historical data of the old SUN2000 will be inherited.
    SmartLogger1000A/SmartLogger3000 Networking

SUN2000-4.95KTL-JPL0 Replacement Scenario

SUN2000-4.95KTL-JPL0 Replacement Scenario

Removing SUN2000-4.95KTL-JPL0

  • Before removing the original SUN2000, ensure that the DC switch on the SUN2000 and all the switches connected to the SUN2000 are set to OFF. Otherwise, the high voltage of the\ SUN2000 may result in electric shocks.
  • After the SUN2000 is powered off, the remaining electricity and heat may still cause electric shocks and body burns. Therefore, put on protective gloves and dielectric boots and begin operating the SUN2000 with specialized insulation tools five minutes after the power-off.

Removing Cables from SUN2000-4.95KTL-JPL0 for Future Use

  1. Power off the SUN2000 to be replaced.

  2. Remove the AC connector and remove the AC output power cable from the mating socket for future use.
    Removing SUN2000-4.95KTL-JPL

  3. Remove the DC connectors and use a cable cutter to cut off the terminals of DC input power cables. Set the cables aside for future use.
    Notice
    The DC terminals of SUN2000- 4.95KTL-JPL0 must be cut off. If the DC connectors of the SUN2000- 4.95KTL-JPL0 are directly connected to SUN2000-4 .95KTL-NHL2, the inverter may be burnt.

  4. (Optional) Remove the signal cable connector from the COM port for future use.
    Removing Cables from SUN2000-4.95KTL-JPL0 for Future
Use

  5. Disconnect the PE cable and remove the crimped OT terminal. Set the cable aside for future use.
    Removing Cables from SUN2000-4.95KTL-JPL0 for Future
Use

Removing SUN2000-4.95KTL-JPL0

  1. (Optional) Open the anti-theft lock.

  2. Remove the SUN2000 from the mounting bracket.
    Removing SUN2000-4.95KTL-JPL0

Installing SUN2000-4.95KTL-NHL2

  1. (Optional) Install the locking screw for the DC switch
    Installing SUN2000-4.95KTL-NHL2

  2. Install the SUN2000
    Installing SUN2000-4.95KTL-NHL2

  3. (Optional) Install an antitheft lock.

NOTE

  * The marking-off template, mounting bracket, and M6x60 expansion bolts delivered with SUN2000-4.95KTL-NHL2 are not used during replacement.
  * Prepare an anti-theft lock suitable for the lock hole diameter (Ф10 mm) and ensure that the lock can be installed successfully. An outdoor waterproof lock is recommended.

Completing Electrical Connections of SUN2000-4.95KTL-NHL2

  1. Install the PE cable, WLAN antenna, AC output power cable, signal cables, and DC input power cables.
    NOTE
    See section 1.3 ”Completing Electrical Connections of SUN2000-4.95KTL- NHL2”.

Checking the Installation of SUN2000-4.95KTL-NHL2 and Powering On the SUN2000

NOTE
See section 1.4 “Checking the Installation of SUN2000-4.95KTL-NHL2 and Powering On the SUN2000”.

Commissioning SUN2000-4.95KTL-NHL2

NOTE
See section 1.5 “Commissioning SUN2000-4.95KTL-NHL2”

Customer Support

Huawei Digital Power Technologies Co., Ltd.
Huawei Digital Power Antuoshan Headquarters
Futian, Shenzhen 518043
People’s Republic of China
solar.huawei.com

References

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

Related Manuals