Introduction
This guide outlines the recommended settings and establishing communication
for operation of one or more Any-Grid™ PSW-H-5kW-230/48V, PSW-H-5kW-120/48V or
PSW-H-6.5kW-120/48V hybrid inverter chargers with Arco Invincible III battery
modules in the low-voltage (50.4 Vdc nominal) configuration, referred to in
this guide as “battery modules”.
Note that the charge/discharge settings are automatically negotiated with the
battery if this guide is used and cannot be changed. If you wish to manually
set these settings, then a communication cable between the PSW-H and batteries
is not needed and the battery type in settings menu 05 of the PSW-H must be
set to “User defined” (USE). In this case it is your responsibility to choose
settings within the specifications of the battery to preserve the battery
warranty.
The Any-Grid must be installed according to the Any-Grid “User and
Installation Manual” included with every Any-Grid unit and available online at
www.phocos.com. The battery terminals of the Any-Grid
must be connected to the batteries according to the Arco installation manual
at the appropriate step mentioned in the chapter “5.0 Battery Settings and
Communication Cable Installation” of this manual.
WARNING: Be sure to read and respect the warnings in the installation
manuals of the Any -Grid, the battery modules and any other connected
equipment. The installation must be conducted by a trained professional.
Requirements
The following is required to proceed with this guide:
-
Any-Grid PSW-H-5KW-230/48V, PSW-H-5KW-120/48V or PSW-H-6.5KW-120/48V
Note: the minimum display unit firmware version U2 must be 06.18 or later, with the corresponding U1 firmware for your Any-Grid PSW-H. -
Battery communication cable with only the following pins connected:
Make sure the cable is correctly oriented between the battery and PSW-H unit
when installing below.
WARNING: Do not use the inverter cable included with your Arco batteries.
Wiring your own cable according to the pinout above must be done at your own
risk. Any damage to the PSW-H or battery due to incorrect wiring, cable
orientation or use of an incorrect cable is not covered by any warranty.
- Arco battery module(s)
System Overview
Battery Sizing
To maintain the full battery warranty, each battery module should be sized not
to exceed 40 Adc continuous current (verify Arco manual for details). It is
thus recommended to use at least 3 battery modules in parallel to deliver both
sufficient continuous current and peak current for a single PSW-H-5KW at full
power. When using multiple Any-Grid units, be sure to increase the number of
batteries accordingly to sustain the required currents. Using too few
batteries per inverter may void your Arco battery warranty.
The batteries must be wired in parallel to form a single large battery bank
when using multiple Any-Grids, with a nominal voltage of 50.4 Vdc. All Any-
Grids must be connected to a single battery array.
Battery Settings and Communication Cable Installation
CAUTION: Before connecting the battery modules to the Any-Grid(s), please
follow the installation instructions in this chapter step by step. The
battery, AC input source, AC output loads and PV input must remain
disconnected until instructed otherwise.
Any battery-related settings made will be over-written if the communication
cable is used. If you wish to manually use settings at your own risk, then do
not use the communication cable.
-
Make the battery communication cable as described in chapter 2. This cable is designed specifically for connecting the Any-Grid PSW-H to Arco batteries.
-
Ensure the battery modules are all turned off.
-
Set the battery DIP switches as described in the battery manual, depending on the number and arrangement of batteries used.
-
Ensure the battery modules are still turned off. Connect the Any-Grid(s) to the battery power (positive and negative) terminals with the correct polarity.
CAUTION: If the correct polarity of the battery is not observed, the Any -Grid and the battery may be damaged, this is not covered by warranty.
Connect the battery communication cable mentioned in chapter 2 to the master battery’s RS-485-1 port and the other end to the Any-Grid’s BMS port. Take care to connect the correct cable ends to the battery and Any-Grid: -
Ensure the battery modules are wired as outlined in the Arco battery manual. Turn on the batteries:
-
Ensure the “ON/OFF” load power button of the Any-Grid(s) is in the ON position (depressed), but no loads are connected: The Any-Grid(s) should now be running, the display(s) on.
-
Apply the following setting on the Any-Grid to which the Arco battery bank is connected with the communication cable. This setting refers to the Any-Grid manual, chapter Operation → Device Operation Settings → Settings menus.
- Battery type
Menu 05: User-defined battery (“USE”)
- Battery type
-
Once the setting has been applied, exit the settings menu by pressing to return to the main view.
-
Activate the circuit breakers or insert the fuses to energize the various inputs and outputs on the Any-Grid in the following order (skip any that are not connected):
- AC input
- PV input
- AC output
-
If you are using more than one Any-Grid, this procedure ensures that the unit to which the Arco battery is connected, will communicate with the Arco battery BMS. Automatically, the battery type of all other connected Any-Grid units will be set to “User-defined”, this is normal.
The commissioning and programming of the battery-related settings of the Any- Grid is now complete.
The content of this document is subject to change without notice. Copyright ©
2022 Phocos AG, all rights reserved.
Version: 20220211
Phocos AG
Magirus-Deutz-Str. 12
89077 Ulm, Germany
Phone +49 731 9380688-0
Fax +49 731 9380688-50
www.phocos.com
info@phocos.com
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>