myenergi ZAPPI-2H07UW-G eco-smart EV Charge Point Instruction Manual

June 9, 2024
Myenergi

ZAPPI-2H07UW-G eco-smart EV Charge Point

zappi
eco-smart EV charge point

Installation Manual

MODELS:

ZAPPI-2H07UW-G ZAPPI-2H07UB-G ZAPPI-2H07TW-G ZAPPI-2H07TB-G

ZAPPI-2H22UW-G ZAPPI-2H22TW-G ZAPPI-2H22UB-G ZAPPI-2H22TB-G

Rev 1.3 November 2022 ­ ENGLISH

Contents
1. Introduction……………………………………………………………………………………………………………………………………………………………5 2. Safety Information ……………………………………………………………………………………………………………………………………………….. 5 3. Disposal …………………………………………………………………………………………………………………………………………………………………. 5 4. Copyright………………………………………………………………………………………………………………………………………………………………..5 5. Overview………………………………………………………………………………………………………………………………………………………………… 6
5.1 Overview Diagram……………………………………………………………………………………………………………………………………….. 6 6. Box Contents…………………………………………………………………………………………………………………………………………………………. 8 7. Connectivity ………………………………………………………………………………………………………………………………………………………….. 8
7.1 Wireless Connection……………………………………………………………………………………………………………………………………. 8 7.2 Ethernet or WiFi Connections ……………………………………………………………………………………………………………………. 8 8. Installation …………………………………………………………………………………………………………………………………………………………….. 9 8.1 Mounting ………………………………………………………………………………………………………………………………………………………. 9 8.2 Wiring …………………………………………………………………………………………………………………………………………………………… 11 8.3 CT Sensor Installation ………………………………………………………………………………………………………………………………..17 8.4 Ethernet link ……………………………………………………………………………………………………………………………………………… 20 8.5 Fitting the Cover ……………………………………………………………………………………………………………………………………….. 21 8.6 Advanced Installation Options………………………………………………………………………………………………………………… 22 8.7 Built- in Protection ……………………………………………………………………………………………………………………………………. 24 9. Set- up………………………………………………………………………………………………………………………………………………………………….. 25 9.1 Installs in England, Scotland & Wales on or after 30th December 2022 ……………………………………………. 25 9.2 Installs in England, Scotland & Wales before 30th December 2022 …………………………………………………… 29 9.3 Installs outside of Great Britain………………………………………………………………………………………………………………. 32 9.4 WiFi Connection (Retrospective) ……………………………………………………………………………………………………………. 35 9.5 Testing ……………………………………………………………………………………………………………………………………………………….. 36 10. Pairing Devices ……………………………………………………………………………………………………………………………………………….37 10.1 Master and Slave Devices………………………………………………………………………………………………………………………….37 10.2 Channels ……………………………………………………………………………………………………………………………………………………..37 10.3 Pairing zappi …………………………………………………………………………………………………………………………………………….. 38 10.4 Device Settings…………………………………………………………………………………………………………………………………………. 38 10.5 Device Priorities ……………………………………………………………………………………………………………………………………….. 38 10.6 Removing Devices ……………………………………………………………………………………………………………………………………. 39 11. Troubleshooting ……………………………………………………………………………………………………………………………………………. 40 12. Fault Codes …………………………………………………………………………………………………………………………………………………….. 41 13. Warranty ………………………………………………………………………………………………………………………………………………………… 42 14. Product Registration ……………………………………………………………………………………………………………………………………. 42 15. Technical Specifications ………………………………………………………………………………………………………………………………. 43
Page 2 of 51

15.1 Performance ……………………………………………………………………………………………………………………………………………… 43 15.2 Electrical Specifications ………………………………………………………………………………………………………………………….. 43 15.3 Mechanical Specifications……………………………………………………………………………………………………………………….. 43 15.4 Connectivity………………………………………………………………………………………………………………………………………………. 43 15.5 Max Transmitted Power …………………………………………………………………………………………………………………………… 43 16. Model Variants ………………………………………………………………………………………………………………………………………………. 44 17. Technical Support…………………………………………………………………………………………………………………………………………. 44 Appendix A …………………………………………………………………………………………………………………………………………………………………. 45

  1. Electric Vehicles (Smart Charge Points) Regulations 2021………………………………………………………………………….. 45 1.1 Purpose of the Regulations …………………………………………………………………………………………………………………….. 45 1.2 What’s changed with zappi……………………………………………………………………………………………………………………… 45 1.3 Randomised Delay: How it works ……………………………………………………………………………………………………………. 45 1.4 Smart Scheduling: How it works……………………………………………………………………………………………………………… 46 1.5 Defaulting to `ECO+’ Mode………………………………………………………………………………………………………………………. 46 1.6 Charging Logs …………………………………………………………………………………………………………………………………………….47 Appendix B …………………………………………………………………………………………………………………………………………………………………. 48
  2. Electric Vehicles (Smart Charge Points) Regulations 2021………………………………………………………………………….. 48 2.1 Purpose of the Regulations …………………………………………………………………………………………………………………….. 48 2.2 What’s changed with zappi……………………………………………………………………………………………………………………… 48 2.3 Automatic Firmware Checking ……………………………………………………………………………………………………………….. 49 2.4 Tamper Detection …………………………………………………………………………………………………………………………………….. 49 2.5 AES Encryption …………………………………………………………………………………………………………………………………………. 49 2.6 Installer Requirements…………………………………………………………………………………………………………………………….. 50
    Page 3 of 51

NOTICE The UK Government’s Electric Vehicle (Smart Charge Points) Regulations 2021 have been introduced. Please ensure you read this manual fully before installing. Processes and features have changed.
Electric Vehicles (Smart Charge Points) Regulations 2021
From 30th June 2022, any EV charger installed in a private setting i.e. home or workplace, NOT public, in England, Scotland and Wales has to meet the Electric Vehicles (Smart Charge Points) Regulations 2021. From 30th December 2022, further regulations come into force. To ensure all our zappis are compliant by the date the regulations come into force we will be taking a phased approach with the implementation of certain features. For information on how these new regulations may affect you and your myenergi zappi please read the appended information at the back of this manual. Appendix A ­ (Electric Vehicle Smart Charge Points) Regulations 2021 ­ Regulations as of 30th June 2022 This Appendix is relevant to all zappis INSTALLED on or after the 30th June 2022 Appendix B – (Electric Vehicle Smart Charge Points) Regulations 2021 ­ Regulations as of 30th December 2022. This appendix is relevant to zappis INSTALLED on or after 30th December 2022.
Page 4 of 51

1. Introduction
Thank you for choosing zappi. Of course, we think you have made an excellent choice and are sure you will be incredibly happy with the features, benefits, and quality of your myenergi product.
These instructions will help you to familiarise yourself with the zappi. By reading the instructions, you will be sure to get the maximum benefit from your ‘eco-smart’ device.
2. Safety Information
zappi is an AC EV charger, intended to be installed in a fixed location and permanently connected to the AC supply network. It is a Class 1 item of electrical equipment in accordance with IEC 61140.
The unit is designed for indoor or outdoor use at a location with restricted access and should be mounted vertically either surface (wall) mounted or on the dedicated pole mount supplied separately by myenergi.
The device has been manufactured in accordance with the state of the art and the recognised safety standards, however, incorrect operation or misuse may result in: · Injury or death to the operator or third parties · Damage to the device and other property of the operator · Inefficient operation of the device
All persons involved in commissioning, maintaining, and servicing the device must: · Be suitably qualified · Have knowledge of and experience in dealing with electrical installations · Read and follow these operating instructions carefully · Always disconnect the device from the supply before removing the cover
The device is not to be used by persons (including children) with reduced physical, sensory, or mental capabilities, or lack of experience and knowledge, unless they have been given supervision or instruction concerning use of the device by a person responsible for their safety.
zappi comes in either tethered or untethered variants. The untethered version should only be used with a dedicated cable fitted with a Type 2 plug which is compliant with EN 62196-1 and EN 62196-2. Adaptors or conversion adapters and cord extension sets are not allowed to be used.
Failure to install and operate the zappi in accordance with these instructions may damage the unit and invalidate the manufacturer’s warranty.
3. Disposal
In accordance with European Directive 2002/96/EC on waste electrical and electronic equipment and its implementation in national law, used electrical devices must be collected separately and recycled in an environmentally responsible manner. Ensure that you return your used device to your dealer or obtain information regarding a local, authorised collection and disposal system. Failure to comply with this EU Directive may result in a negative impact on the environment.
4. Copyright
Copyright of these operating instructions remains with the manufacturer. Text and images correspond to the technical level at the time of going to press. We reserve the right to make changes. The content of the operating instructions shall not give rise to any claims on the part of the purchaser. We are grateful for any suggestions for improvement and notices of errors in the operating instructions.
myenergi zappi, myenergi eddi and myenergi harvi are registered trademarks of myenergi Ltd.
Page 5 of 51

5. Overview
Microgeneration systems such as Solar PV and small wind turbines are at their most efficient when the generated energy is consumed on-site rather than exporting it to the grid. This is what we call ‘selfconsumption’. zappi is a Mode 3 charging station, compatible with all electric vehicles that comply with EN 62196 and EN 61851-1 plug-in electric vehicle standards. zappi works like any regular charging point but has special ECO charging modes that will benefit homeowners with grid-tied microgeneration systems e.g. wind or solar generation. Two special ECO charging modes automatically adjust charging current in response to on-site generation and household power consumption. In FAST charge mode, zappi operates like an ordinary EV charger. A grid current sensor (supplied) simply clips around the incoming supply cable and is used to monitor excess power. When using the special ECO charge modes, zappi will automatically adjust the charge rate in response to available surplus.
Feature Set
· 3 charging modes: ECO, ECO+ & FAST · Optimises microgeneration self- consumption · Works with solar PV, wind turbine or micro-hydro systems · Economy tariff sense input · Programmable timer function · Charge and event logging · Remote control and monitoring add-on option · Pin-code lock function · Tap operated display backlight · Built-in protection against the loss of the protective neutral and earth (PEN) conductor as required by
BS 7671:2018 Amendment 1:2020(The “Wiring Regulations”) · Ethernet connector (for local communications between myenergi devices) · Integral cable holster (tethered units) · Supplied with 1 x clip-on grid current sensor (x3 if purchasing a 3-phase unit) · Illuminated display ­ for convenience, the display can be illuminated by simply tapping the zappi front
cover. · Integrated WiFi for connecting to internet. · Front Lid Tamper Detection
5.1 Overview Diagram
The diagram on the next page shows the zappi as part of a complete energy management system. Other myenergi products are shown with details of how they integrate with the grid connection and the microgeneration system.
Page 6 of 51

Page 7 of 51

6. Box Contents
Tethered Units · 1 x zappi unit with EV cable and connector attached · 1 x Cable wall guard · 1 or 3 x CT clamps1 · 1 x Mounting template · 1 x Mounting kit for a brick wall
Mounting kit (Tethered units) · 4 x 50mm Pozi screws · 4 x Wall mounting plug · 4 x Sealing washer · 4 x 12mm Pozi screws (countersunk)

Untethered Units · 1 x zappi unit · 1 or 3 x CT clamps1 · 1 x Mounting template · 1 x Mounting kit for a brick wall
Mounting kit (Untethered units) · 4 x 50mm Pozi screws · 4 x Wall mounting plug · 4 x Sealing washer

7. Connectivity
7.1 Wireless Connection
myenergi devices use an 868MHz / 915Mhz wireless link to communicate with each other. Although this is usually more effective at passing through walls than a standard WiFi signal, radio communication can be affected by many factors such as: · the distance between the devices · the thickness of any walls that the signal has to pass through · wall construction and insulation materials · large metal objects such as washing machines, fridges, sinks and baths · mirrors · electronic products such as televisions · other wireless devices operating on the same radio frequency
Please consider the position of your myenergi devices carefully to ensure that they operate as planned.
Although the devices work in the majority of installations and our technical support team are available to provide help in setting up your system, we cannot guarantee the performance where circumstances beyond our control affect the performance of the wireless link.
If you have any concerns about the wireless performance then we would be pleased to answer your questions, but please consider that if a WiFi signal works OK then there is a very high probability that the myenergi devices will also work without any issues.
7.2 Ethernet or WiFi Connections
zappis with the built-in vHub (identified by product code zappi-2Hxxxx and 22xxxx) are supplied with a builtin Ethernet port (RJ45) and WiFi to connect zappi to the local network (LAN).
All myenergi internet capable devices should be connected to the internet either, via WiFi or a hardwired Ethernet connection. This version of the zappi can also act as the “hub” between all your myenergi devices and the myenergi server. The “hub” device MUST be connected to the internet.
harvi can only be connected using a wireless link to the Master device
NOTICE It is not currently G100 compliant to use a harvi with zappi or libbi to measure Grid CT, in UK installations. · EV chargers and battery storage must have a hardwired Grid CT (in the UK).
When pairing devices, they will use the Ethernet link over wireless, if available.

1 1xCT clamp supplied with single phase zappi; 3xCT clamps supplied with three phase zappi Page 8 of 51

8. Installation
8.1 Mounting
NOTICE · Care should be taken to maintain the IP rating of the unit. · Ensure grommets and bungs provided are fitted, the O-ring behind the cover is seated correctly and
that the incoming power and CT cables are fitted using an appropriate size and type of gland. · zappi must be fixed to a flat vertical surface.
8.1.1 Cable and Gland Requirements
The Cross Sectional Area of the cable used should be between 4mm2 and 10mm2 The gland diameter should be a minimum of 16mm and a maximum of 25mm. Generally, a stuffing gland can be used. SWA CW outdoor glands may be used for armoured cable. The size of cable and gland used is the responsibility of the installer and should be determined on an install-by-install basis dependant upon install specifics.
8.1.2 Mounting Instructions

Step 1: Carefully remove fascia from the zappi by
pressing the 2 clips located at the bottom of unit inwards whilst pulling the fascia towards you.

Step 2: If installing a tethered zappi, you must
ensure the cable wall guard is fixed to the unit using the 4 screws supplied. If installing an untethered zappi go to next step.

Page 9 of 51

Step 3: Remove all 8 screws from the enclosure Step 4: There are 4 possible cable entry positions,

and carefully lift away.

carefully decide which one you are going to use from

the above image.

You will need an IP65 or above rated cable gland.

Carefully drill a hole into the unit to match the size of your cable gland. Attach cable gland ensuring IP rating is met.

Step 5: Using zappi template mark mounting
holes. For fixing to brick, use the top and 2 bottom holes (left/right). Use the 2 vertical holes as well as the top hole if mounting to a stud wall or joist.

Step 6: To maintain the IP rating of the unit you
will need to add bungs (provided) to the unused holes.

Page 10 of 51

Step 7: Secure the unit to the wall using the fixing Step 8: Ensure O-ring is present and sits neatly
kit provided. Ensure the grommets are used to into its channel. maintain its IP integrity. NOTICE If using the rear cable entry, remember to insert the mains cable before mounting to the wall.
8.2 Wiring
WARNING ELECTRIC SHOCK ­ An electric shock can be fatal; electrical connection work may only be carried out by a competent person. The earth conductor must be correctly installed and reliably connected. This device must b equipped with an over-current protection device of maximum 32 Amps (B32).
8.2.1 Cable and Gland Requirements
The Cross Sectional Area of the cable used should be between 4mm2 and 10mm2. The gland size should be a minimum of 16mm and a maximum of 25mm. Generally, a stuffing gland can be used. SWA CW outdoor glands may be used for armoured cable. The size of cable and gland used is the responsibility of the installer and should be determined on an install-by-install basis dependant upon install specifics.
8.2.2 Strip Length
The main terminals are designed to work with wires with a diameter up to 16mm2.
Insert the mains cable through the installed cable gland (if not already done so). Strip back outer sheath ensuring all cables reach the terminal blocks (leaving a little excess). Strip back all coloured cables approx. 18mm.
If using hard wired CT clamps now is the time to insert these too (we recommend a specialist cable gland that can accommodate multiple cables whilst still maintaining IP integrity, or two separate cable glands to ensure zappi remains sealed).
Page 11 of 51

To insert the wires into the terminal blocks a suitable sized screwdriver should be inserted into the slot. This opens the spring terminal allowing the wire to be gently pushed into the terminal. Make sure that the wire is pushed fully home and then remove screwdriver, checking that the wire is secure in the terminal.
8.2.1 Supply
The single phase zappi should be connected to a 230V/240V nominal AC supply. The supply should run from a dedicated 32A circuit breaker. The 3 phase zappi should be connected to a 400V, 4 wire, 3 phase supply. The supply should run from a dedicated 3 pole 32A circuit breaker. We recommend the use of curve B circuit breakers. Local wiring regulations should consulted to confirm whether an additional upstream RCD is also required.
8.2.2 Earthing
The zappi unit must be earthed in accordance with local regulations. When installed on a PME (TNC-S) electrical system it is necessary to protect the consumer from a potential electric shock that could occur if the combined Neutral and Earth (PEN) conductor on the supply becomes damaged or disconnected. zappi includes an additional automatic disconnection device which satisfies the requirements of BS7671:2018 Amendment 1:2020 722.411.4.1 (v) (the 18th Edition IET Wiring Regulations). This protection device
a) monitors the supply to identify if there is a problem with the PEN conductor and b) disconnects the supply if a situation arises where the end user might suffer an electric shock This means that the zappi can be installed without the need for an additional earth rod. However, if the customer or local regulations require that an earth rod is installed (for instance as part of a TT earthed system) then this should be connected to the dedicated terminal on the main circuit board using a ring terminal (as shown below).
Page 12 of 51

8.2.3 Single Phase Wiring

For single-phase installations, without the need for hardwiring an external CT, please follow the above diagram
Earth = Green / Yellow cable Neutral = Blue cable Live (L1) = Brown cable

For single phase installations, where 1 or more external/additional CTs are required, please follow the above diagram to connect the CTs. Use the extra CT terminals in the same way if required.
Positive (+) = Red Negative (-) = Black
For more details on CT installation and connection see CT Sensor Installation
WARNING It is vitally important that conductors are inserted into the correct terminal entry. If in doubt please call our Technical Support Team for guidance before installing.

Page 13 of 51

8.2.4 Three Phase Wiring

For 3 phase installations, without the need for hardwiring an external CT, please use the above diagram. Earth = Green / Yellow cable Neutral = Blue cable Live (L1) = Brown Live (L2) = Black Live (L3) = Grey

For 3 phase installations, with the need for 1 or more external/additional CTs, please use the above diagram. Positive (+) = Red Negative (-) = Black
For more details on CT installation and connection see CT Sensor Installation
WARNING It is vitally important that conductors are inserted into the correct terminal entry. If in doubt please call our Technical Support Team for guidance before installing.

Page 14 of 51

8.2.5 eSense Input
zappi has an “external Sense” or “eSense” input which can be used with an external input (such as a relay contact or voltage) to
· sense the availability of economy tariff electricity, this can be used to automatically boost the charge when in ECO or ECO+ charging modes.
· force zappi to limit the output or stop the EV charging
NOTICE The connection to the eSense input will depend on the version of the zappi. · Serial numbers starting 1xxxxxx The eSense input to the zappi is designed to work with an AC voltage between 100V and 260V. · Serial numbers from 2xxxxxxx onwards A “universal” Sense input is provided. This will work with an external voltage 24-230V AC/DC wired to the terminals marked “24-230V AC/DC in”.
To use eSense input with a simple “dry” relay contact, a 24V DC supply is provided. The external volt-free relay contact should be wired between the terminals marked “24V out” and “in”.
The eSense input is electrically isolated and effectively draws no current so the eSense signal may be connected using a wire with a small cross section. When the eSense input is active the cause the eSense symbol
will be shown on the main screen. There is no need to connect the eSense input if you do not want to use this feature.

If the eSense input is provided using an external volt-free contact then this must be connected to the outer terminals marked “24V out” and “in”
NOTICE There is no need to earth the eSense cable

If the eSense signal is provided by using an external voltage this must be connected to the two right hand terminals marked “24-230V AC/DC in”

8.2.6 Wiring Overview Diagram
The diagram on the following page gives an overview of the wiring required for a standard installation.

Page 15 of 51

Page 16 of 51

8.3 CT Sensor Installation
Current Transformers (CTs) are used to measure current at various places of the installation. For example, the Grid connection point, the solar/wind inverter, or a static battery system.
Installation of a CT to monitor the Grid connection point is required for ECO modes. Other CTs are optional and can be purchased separately. The number and location of CTs used within an installation will vary according to the devices installed and the user requirements.
CTs can be wired to any myenergi device with CT inputs (e.g. eddi, zappi or harvi). This allows for flexible installation as a CT can be wired to the nearest device. Ideally the grid CTs should be wired to the master device.
NOTICE The harvi device can be used (wirelessly) if it is not practical to connect Generation CT to the zappi.
NOTICE It is not currently G100 compliant to use a harvi with zappi or libbi to measure Grid CT, in UK installations. · EV chargers and battery storage must have a hardwired Grid CT (in the UK).

SINGLE PHASE: A CT clamp must be placed around the live meter tail as shown above with the arrow pointing towards the consumer unit.
NOTICE The clamp can be placed on the neutral tail, however the direction of the arrow shown above will need to be in reversed.

3-PHASE: A CT clamp must be placed around each phase with the arrow pointing towards the consumer unit.
NOTICE A CT cannot be clipped on to the neutral in a 3phase system.

Page 17 of 51

Once installed the CTs need to be configured. See CT Config for details of how to configure the CTs.
If using a single-phase system, the wired CT sensor (supplied) ideally needs to be clipped around the live conductor leaving the meter tail with the arrow (located on the side of the CT) pointing towards the consumer unit. It is possible to use the Neutral conductor, however you will need to reverse the direction of the sensor (arrow towards the meter).
If using a 3-phase system, a CT sensor (supplied) needs to be clipped around each live tail.
The positioning of the Grid CT sensor is crucial, please take note of the following when deciding where best to install the sensor:
· The sensor can be connected to any myenergi device with a CT input e.g. the eddi, zappi (wired sensor) or harvi (wireless sensor)
· ALL the import and exported power must be ‘seen’ by the sensor. Ensure that it is installed before ANY junction box or ‘Henley Block’ (if necessary, the CT can be fitted inside the consumer unit)
· There must be only one Grid CT per-phase for the whole installation. (There can be other CTs but only one at the grid connection point. Also note that CTs for third-party devices do not matter)
· The CTs can be clipped on either the Live or Neutral cable on single-phase systems
Note: On 3 phase system you can only use the Live tails
· The arrow on the bottom of the CT sensor must be pointing towards the consumer unit (in the direction of grid import) if on the Live cable or reversed if on the Neutral cable (single phase only)
· Ensure the CT is fully closed and clicks shut · Be sure to wire the CT the correct way round: black [­], red [+]. Failure to do so will see the import and
export readings swapped
8.3.1 Grid CT
The Grid CT sensor (supplied) needs to be clipped around either the Live or Neutral meter tail of the electricity supply meter. If using the Neutral conductor, reverse the direction of the sensor (so the arrow is reversed). The positioning of the Grid CT sensor is crucial, take note of the following when deciding where best to install the sensor:
· Can be connected to any myenergi device with a CT input e.g. the eddi or zappi (wired sensor) or harvi (wireless sensor).
· ALL of the imported and exported power must be ‘seen’ by the sensor ­ be sure to install it upstream of ANY junction box or ‘Henley Block’ (the CT can be fitted inside the consumer unit).
· There must be only one Grid CT per-phase for the whole installation. (There can be other CTs but only one at the grid connection point, also note CTs for third-party devices do not matter).
· The CT should be on the Live or Neutral cable. · The arrow on the bottom of the CT sensor must be
pointing towards the consumer unit (in the direction of grid import) if on the Live cable, or reversed if on the Neutral cable. · Ensure the CT is fully closed and clicks shut. · Be sure to wire the CT the correct way round; black [­], red [+] otherwise import and export readings will be swapped.
Page 18 of 51

8.3.2 Additional CTs
There is an option to add other CT sensors (available separately) for monitoring the generation or other appliances such as battery systems or general loads. Installing a CT for the generator (PV system) will allow the main screen to show the generated power and the total power consumption of the all the other appliances in the property. CTs can also be used to limit the power drawn from the supply:
· Additional CTs can be connected to any myenergi device with a CT input that is linked to the network. · The arrow on the bottom of the sensor must be pointing in the direction of normal power flow (e.g.
away from the PV inverter) if on the Live cable or reversed if on the Neutral cable. · Ensure the sensor is fully closed and clicks shut. · Be sure to wire the CT the correct way round; black [­], red [+] 8.3.3 Extending CT Sensor Cable
If there is a need to extend the CT sensor cable, twisted-pair cable like CAT5 or telephone cable must be used (only use one pair).
NOTICE DO NOT use mains cable, bell wire or speaker cable. It is important to use only twisted-pair cable to maintain signal integrity. The cable can be extended up to 100m.
8.3.4 Wireless CT Sensor (Optional accessory)
In some cases it can be difficult or impractical to install a wired sensor. For example, it may be the case that the zappi unit needs to be connected to a sub-board, rather than main consumer unit and two consumer units are in different buildings. The solution is to install harvi ­ a clever little device that enables the zappi product to be installed without using wired CT sensors for measuring generation power; instead the CT sensor is connected to harvi. The harvi does not need batteries or a power supply ­ the energy from the sensor is harvested and used to transmit the measurement signal to the eddi. This means batteries or electrical wiring are eliminated! Up to 3 CT sensors may be used with harvi and it also supports 3-phase systems if three sensors are connected.
Refer to the harvi installation guide for details on installing and configuring harvi for your system. NOTICE It is not currently G100 compliant to use a harvi with zappi or libbi to measure Grid CT, in UK installations. · EV chargers and battery storage must have a hardwired Grid CT (in the UK).
Page 19 of 51

8.3.5 CT Golden Rules ­ Grid CT
· Only ONE Grid CT per phase (check for only one ~ symbol in Linked Devices Info). · Located to `see’ ALL import and ALL export current (i.e. always upstream of any junction box). · Arrow pointing in direction of import (e.g. towards consumer unit if on Live cable). · Must be on the same phase as the Master myenergi device.
8.3.6 All other CTs
· Arrow should point towards the consumer unit.
8.3.7 3-phase harvi CTs
· When using harvi in 3-phase mode, the CT inputs correspond to the phase number (e.g. CT1 = Phase 1). This helps to avoid phase shifting / phase misalignment.
8.3.8 CT Can do’s
· Can be wired to ANY myenergi device in the network. · harvi can be used to make ANY CT wireless2. · Cable can be extended up to 100m (must use twisted- pair cable e.g. one pair of CAT5). · Cable can be shortened. · Can be clipped around two or more conductors feeding appliances of the same type (e.g. two Live
cables from two inverters that are on the same phase). · Can be in close proximity to other CTs. · Wires can be swapped around in device to reverse the direction of the readings (e.g. change import to
export). · Can be grouped with other CTs of the same type so that the power reading is summed (e.g. east and
west solar Generation). · Can be used on the Neutral conductor (direction of arrow or wires must be reversed). · Can be set to None if you want to exclude the reading.
8.4 Ethernet link
If you are installing a hard wired link to the router, insert the Ethernet cable into the RJ45 Port before progressing to 8.5 Ensure you connect the remaining end of the Ethernet into the home router.
NOTICE If installing alongside a libbi or another zappi, all devices MUST be paired using hardwired Ethernet. This is to ensure the installation remains G100 compliant.
2 Although CT’s connected to a harvi cannot be used with Monitor Group option. Page 20 of 51

8.5 Fitting the Cover

Step 1: Offer cover to the enclosure, ensuring all Step 2: Add fascia to the enclosure cover of the

cables are neatly secured inside the unit.

zappi as shown.

· Take particular care that the ribbon cable is not trapped between the cover and the case

Ensure O-ring (seal) is firmly placed into the channel and secure the cover to the unit using the 8 screws that were removed earlier (Torque setting = 1.2Nm).

Step 3: Ensure the 2 tabs at the bottom of the Step 4: zappi is now ready for operation.
fascia click to indicate its securely fixed in place.
Page 21 of 51

8.6 Advanced Installation Options
8.6.1 Load Balancing / Current Limiting / Load Curtailment
CTs can also be used to limit the current drawn by myenergi devices to avoid overloading circuits; this is referred to as load balancing or load curtailment. There are four different ways to limit current and they can be used alone or combined for more complex situations. See the table below:

Function Device Limit
Grid Limit
Group Limit (internal CT) Group Limit (with external CT)

Operation Sets a maximum current that can be drawn by the device (e.g. zappi). The current will not be exceeded even during Boost or Fast charge. Sets the limit that can be drawn from the grid connection (i.e. the maximum import current). The zappi and any other linked myenergi device, will limit the current they draw if there is a danger of exceeding the set Grid Limit.
Sets the combined current limit for several myenergi devices.
Sets the combined current limit for several myenergi devices that are sharing a supply with another large appliance.

Example A zappi is wired to a 20A supply (rather than 32A). The maximum current drawn will not exceed the set limit (e.g. 20A)
A property may have a grid supply limit of 65A. Several appliances are on, so the property is consuming 12kW (52A). The user wants to charge in FAST mode. Without the Grid Limit set, the total consumption would exceed the allowed import current and trip the supply or blow a fuse. However, with a Grid Limit setting of 60A, zappi would temporarily limit the charging current to 8A (about 1.8kW) and the maximum allowed import current would not be exceeded. A property has a large PV array, a swimming pool and two zappis. The supply to the zappis is only rated at 40A so to be safe a Group Limit of 40A is set. A zappi is installed in a garage which also has a washer and a dryer (2.5kW each). The garage has a supply of 32A coming from the main consumer unit in the house. If all appliances were on together and no limit had been set the total current would exceed the maximum supply current. By setting the Group Limit to 32A an overload will be avoided.

8.6.2 Three-Phase Systems
If the installation has a three-phase supply, you can use the 3 CT connectors either directly connected to the zappi (hard wired) or a harvi device (wireless ­ optional). We recommend you use one CT per phase; this will allow the zappi to show the total grid import and export figures rather than just one of the phases.
If all three phases are monitored then it is also possible to net the export power across phases, to do this, enable Net Phases in the Supply Grid menu see Supply Grid ­ Net Phases. This allows the zappi to use surplus power from any phase and not just the phase which the zappi is installed on. However, you must be sure that the electricity is metered in such a way as to allow this.
For a three phase zappi, Net Phases should be turned on.

Page 22 of 51

8.6.3 Battery Storage Systems
AC Coupled Where there is an AC coupled battery storage system, there can be a conflict as both the storage system and the zappi are competing to consume the surplus energy. Whilst this is not necessarily an issue, the results can be somewhat unpredictable. There is the option to add an additional CT sensor to monitor the battery storage. This will give control as to which device has priority. The additional CT sensor should be wired to one of the CT terminals in the zappi or harvi device (if wireless measurement is required). This CT should be clipped around the live cable of the battery inverter with the arrow on the CT pointing away from the battery and towards the consumer unit/fuse board. During the setup process it will be necessary to change the setting for the appropriate CT to AC Battery; refer to CT Config. Also refer to Supply Grid ­ Network Settings ­ Battery for information on setting the ‘priority’ of battery systems. DC Coupled / Hybrid Battery systems that charge directly from the solar array and cannot charge from AC are usually referred to as being DC coupled or Hybrid. This type of battery system uses the solar PV inverter to provide power from the batteries, thus it is not possible to differentiate between solar and battery power when using a CT to measure the AC current from the inverter. Because of this limitation, there are less options for managing the surplus power with this type of battery system. It is usually possible to give priority to the battery by setting an Export Margin in the zappi. A setting of 50W or 100W is recommended. The Export Margin setting is found in the Advanced Settings/Supply Grid menu. Third-Party Diverters Some properties have a third-party energy diverter installed and you may want the zappi to take priority (when consuming surplus power) over the diverter. This is possible by installing an extra CT to monitor the diverter. The CT should be clipped around the Live cable of the supply feeding the diverter. The arrow on the CT should be pointing away from the diverter (towards the consumer unit). Wire the CT to the nearest myenergi device or use a harvi if a wireless connection is needed. Configure the CT Type as Storage Only. See CT Config for details of how to configure CTs. Voltage Optimisers If there is a voltage optimiser (VO) installed in the property, the CT sensor and the zappi must both be on the same side of the VO; either the incoming grid supply or the optimised supply.
Page 23 of 51

8.7 Built-in Protection
zappi has a number of protection features built into the device to make it safe and simple to install.
8.7.1 Loss of PEN Conductor
The Protective Neutral and Earth (PEN) conductor refers to part of the electricity cable to the property. If this conductor is damaged there is a danger that the chassis of the electric vehicle being charged will become “live” and cause an electric shock. BS7671:2018 Amendment 1:2020 part 722.411.4.1 requires that extra protection is provided to prevent an electric shock ­ either by fitting an extra earth electrode or through a device which detects the fault and disconnects the supply. zappi has this protection built- in3 and will disconnect the output if it detects a problem with the PEN conductor or detects that there may be any electric current flowing through the chassis of the EV. This built-in protection means that there is no need to install an earth electrode with the zappi. If zappi detects a problem with the PEN conductor then the display will show PEN Fault! To reset the zappi, check the continuity of the earth cable and then press the button for three seconds.
8.7.2 Loss of Protective Earth
zappi can measure the continuity of the protective earth conductor (the earth wire) on the supply cable. If the earth is disconnected or has a high impedance, then zappi will trip and the display will show PE not connected! To reset the zappi, make sure that the fault has been removed and then press the button for three seconds.
8.7.3 Welded Contact
zappi includes protection to make sure that the supply to an EV is disconnected if there is a problem with the circuit breaker. This includes a situation where the contacts on the breaker are welded together. This is a specific requirement of the Renault “Z.E. Ready” and ASEFA “EV Ready” standards (e.g. requirement for Nissan). If zappi detects a problem with a welded contact, then the display will show RLY WELDED! If this happens and the fault cannot be reset by pressing the button for three seconds, then please contact myenergi technical support at support@myenergi.com
8.7.4 Over-current
If there is a problem with the equipment on the EV which charges the vehicle’s battery, too much current may be drawn from the supply. If this happens, zappi cannot control the charge rate as expected and it could lead to problems with overheating or tripping the main circuit breaker to the zappi. zappi provides additional protection in accordance with the EV Ready standard by opening its built-in contactor and isolating the EV if it detects that the vehicle is drawing more than 125% of the maximum current communicated to it by the zappi. If zappi detects an over-current, then the display will show Over Current! To reset the zappi, make sure that the fault has been removed and then press the button for three seconds.
3 Patent Reference GB3577354
Page 24 of 51

8.7.5 Over and Under-voltage
zappi will also isolate the supply to the EV if it detects a problem with the electricity supply voltage. The nominal supply voltage is 230V but zappi will trip the output if the measured voltage is more than 12% above or below this level for five seconds. The zappi display will show Over Voltage! or Under Voltage! zappi, will reset automatically once the voltage returns to the acceptable range (nominally 230V +/-10%)
8.7.6 Thermal Limit
zappi also includes protection against overheating. If zappi gets too warm it will attempt to reduce the current being drawn by reducing the EV charge rate. If this happens you will see the icon on the main display. If the problem continues and the zappi’s internal temperature continues to rise, then it will trip the output to the EV, and the display will show Overheating! zappi will resume normal operation once the temperature drops.
9. Set-up
After completing and checking the wiring of the supply and the current transformers (CTs), switch on the zappi via the circuit breaker. zappi will start-up and the main screen will be presented after a few seconds. If zappi has been installed alongside another zappi unit or another myenergi device, refer to Linking Devices section for guidance on pairing devices. Also refer to the instruction documentation for the other devices. Upon start up there will be a wizard where you will be taken through a number of screens. Please ensure you answer the questions correctly for a seamless set-up. The screens will vary depending on install location and install date. Ensure to read the relevant section listed below: · For installs in England, Scotland or Wales on or after 30th December 2022, see section 9.1 · For installs in England, Scotland or Wales before 30th December 2022, see section 9.2 · For installs outside of Great Britain, see section 9.3
9.1 Installs in England, Scotland & Wales on or after 30th December 2022
Installs in England, Scotland and Wales are required to be compliant with the UK Smart (Charge points) Regulations. After 30th December 2022 zappi is required to have tamper detection. For further information on the Smart Regulations; June and December 2022 iterations and retrofit tamper board kits please refer to Appendices A, B and C at the back of this manual.
Step 1: Before you begin, ensure that a tamper Step 2: Select “Yes” as Smart Regulations apply.
board is fitted to the device by looking for the words “Tamper Detection” on the rating plate.
Page 25 of 51

Step 3: If this is your first myenergi device select “1st Device Installed”. If you are adding this zappi to
an existing myenergi eco-system, select “Additional Device”.
Step 4: Review settings and press + to confirm.
Note: Selecting “1st device installed” will configure your zappi as Master and enable vHub.
Selecting “Additional device” will configure zappi as Slave and disable vHub.

Step 5: If you are connecting to the internet via
WiFi please skip ahead to Step 7 If you inserted an Ethernet cable earlier (section 9.4) zappi will detect this and attempt connect to the home router automatically.

Step 6: Once zappi has secured an internet
connection via Ethernet the below screen will show.
Skip ahead to Step 14 for next steps.

Step 7: The following steps are for zappi’s connecting to the internet via WiFi. If you have already made
a hard wired Ethernet connection jump ahead to step 14. zappi will attempt to identify WiFi details. During this attempt you will see the first screen below. Once established the second screen will show.
NOTICE
Make a note of the SSID and Password (P/W) now, for use in the next steps.
NOTICE If the screen above is skipped, please see section 9.4 for details on retrospective WiFi set-up.
Step 8: Connect your smartphone or computer to the myenergi access point by entering your phone or
computer WiFi Settings and searching for the network displayed with the same name as the SSID you noted down above. Once displayed, select the network to connect.

Page 26 of 51

Step 9: You will be prompted for a password. Enter the
password displayed on the zappi screen that you noted down at step 7.
Step 10: You will now be prompted to create a new
password to protect the WiFi settings from being changed by anyone else. The new password must be at least 8 characters long and consist of a combination of lowercase and uppercase letters and digits.
NOTICE If page doesn’t load, type 192.168.4.1 into your web browser of mobile phone browser to enter WiFi setup screen.
Step 11: Wait 5 seconds for your password to change and the webpage to reload.
Step 12: Once connected, you will be directed to the webpage below where you will need to select your
home WiFi network from the list in the “Detected Networks” box and type in your home WiFi’s password to connect to your router.
NOTICE In most cases you should leave the “Show IP Settings” option unticked. However, if you want to give your zappi a fixed IP address then tick the “Show IP Settings” box and fill in the extra information required.
Please be patient. It could take up to 15 seconds for the connection to take place.

Step 13: Once connected, you will see this screen
on your zappi display. Press + to continue.

Step 14: By this step zappi should now be internet
connected either via WiFi or hard wired Ethernet. zappi will now check for firmware updates. Please be patient. If no Firmware updates are available jump to Step 17.

Page 27 of 51

Step 15: If Firmware updates are available zappi Step 16: Once download reaches 100% zappi will

will proceed to download these. Showing the proceed to install updates.

progress percentage on the display.

zappi may reboot during this process.

Step 17: If zappi has no updates available or after updates have been installed this screen will show on
your zappi display informing you that firmware is up to date and giving you the firmware version number.
NOTICE If zappi has been installed alongside another myenergi device, refer to Linking Devices section for guidance on pairing. Also refer to the instruction documentation for the other devices.
Step 18: Jump to “9.5 Testing”.

Page 28 of 51

9.2 Installs in England, Scotland & Wales before 30th December 2022
Before following the steps below, check if your zappi has built-in tamper detection.

If no tamper detection is present, and it is before 30th December 2022 you do NOT need to retrofit a tamper board and you may follow the below steps for set-up. If no tamper detection is present and it is after 30th December 2022, you cannot install the zappi legally until you have fitted a Tamper Board. Contact our Sales Team for further information on ordering Tamper Board Retrofit Kits.

Step 1: Select “Yes” as Smart charging
Regulations apply.

Step 2: Read the screen carefully and check the date of the
install. If it is on or after the 30/12/2022 select “No” and carry on to step 3. If the install is taking place before 30/12/2022 OR it was previously installed prior to 30/12/2022 select “Yes” and jump to step 4.

Step 3: You answered “No” to the previous question which means zappi is
required to have a tamper switch before install. Abandon installation until rectified ensuring to leave the zappi in a safe state. Once tamper board has been fitted you may begin set-up again following section 9.1 of this document.
Step 4: Review settings and press + to confirm.
Note: Selecting “1st device installed” will configure your zappi as Master and enable vHub.
Selecting “Additional device” will configure zappi as Slave and disable vHub.

Step 5: If you are connecting to the internet via
WiFi please skip ahead to Step 7 If you inserted an Ethernet cable earlier (section 9.4) zappi will detect this and attempt connect to the home router automatically.

Step 6: Once zappi has secured an internet
connection via Ethernet the below screen will show.
Skip ahead to Step 14 for next steps.

Page 29 of 51

Step 7: The following steps are for zappi’s connecting to the internet via WiFi. If you have already made
a hard wired Ethernet connection jump ahead to step 14. Zappi will attempt to identify WiFi details. During this attempt you will see the first screen below. Once established the second screen will show.
NOTICE Make a note of the SSID and Password (P/W) now, for use in the next steps.
NOTICE If the step above is skipped, please see section 9.4 for details on retrospective WiFi set-up.
Step 8: Connect your smartphone or computer to the myenergi access point by entering your phone or
computer WiFi Settings and searching for the network displayed with the same name as the SSID you noted down above. Once displayed, select the network to connect.
Step 9: You will be prompted for a password.
Enter the password displayed on the zappi screen that you noted down at step 7.
Step 10: You will now be prompted to create a
new password to protect the WiFi settings from being changed by anyone else. The new password must be at least 8 characters long and consist of a combination of lowercase and uppercase letters and digits.
NOTICE If page doesn’t load, type 192.168.4.1 into your web browser of mobile phone browser to enter WiFi setup screen.
Step 11: Wait 5 seconds for your password to change and the webpage to reload.
Page 30 of 51

Step 12: Once connected, you will be directed to the webpage below where you will need to select your
home WiFi network from the list in the “Detected Networks” box and type in your home WiFi’s password to connect to your router.
NOTICE
In most cases you should leave the “Show IP Settings” option unticked. However, if you want to give your zappi a fixed IP address then tick the “Show IP Settings” box and fill in the extra information required.
NOTICE
Please be patient. It could take up to 15 seconds for the connection to take place.

Step 13: Once connected, you will see
this screen on your zappi display. Press + to continue.

Step 14: By this step zappi should now be internet
connected either via WiFi or hard wired Ethernet. zappi will now check for firmware updates. Please be patient. If no Firmware updates are available jump to Step 17.

Step 15: If Firmware updates are
available zappi will proceed to download these. Showing the progress percentage on the display.

Step 16: Once download reaches 100% zappi will proceed
to install updates. zappi may reboot during this process.

Step 17: If zappi has no updates available or after updates have been installed this screen will show on
your zappi display informing you that firmware is up to date and giving you the firmware version number. NOTICE If zappi has been installed alongside another myenergi device, refer to Linking Devices section for guidance on pairing. Also refer to the instruction documentation for the other devices.
Step 18: Jump to “9.5 Testing”.
Page 31 of 51

9.3 Installs outside of Great Britain
Before following the steps below, please ensure this zappi is not being installed in England, Scotland or Wales. If being installed in any of these countries, Smart Regulations must apply and you will need to follow either 9.1or 9.2 for Set-up instructions.
Step 1: Select “No” as Smart Regulations Step 2: Select timezone relevant to installation location.
don’t apply.

Step 3: Review settings and press + to confirm.
Note: Selecting “1st device installed” will configure your zappi as Master and enable vHub.
Selecting “Additional device” will configure zappi as Slave and disable vHub.

Step 4: If you are connecting to the
internet via WiFi please skip ahead to Step 6 If you inserted an Ethernet cable earlier (section 8.4) zappi will detect this and attempt connect to the home router automatically.

Step 5: Once zappi has secured an internet connection
via Ethernet the below screen will show.
Skip ahead to Step 13 for next steps.

Step 6: The following steps are for zappi’s connecting to the internet via WiFi. If you have already made
a hard wired Ethernet connection jump ahead to step 13. zappi will attempt to identify WiFi details. During this attempt you will see the first screen below. Once established the second screen will show.
NOTICE Make a note of the SSID and Password (P/W) now, for use in the next steps.
NOTICE If the step above is skipped, please see section 9.4 for details on retrospective WiFi set-up.

Page 32 of 51

Step 7: Connect your smartphone or computer to the myenergi access point by entering your phone or
computer WiFi Settings and searching for the network displayed with the same name as the SSID you noted down above. Once displayed, select the network to connect.
Step 8: You will be prompted for a password. Enter the
password displayed on the zappi screen that you noted down at step 6.
Step 9: You will now be prompted to create a new password
to protect the WiFi settings from being changed by anyone else. The new password must be at least 8 characters long and consist of a combination of lowercase and uppercase letters and digits.
NOTICE If page doesn’t load, type 192.168.4.1 into your web browser of mobile phone browser to enter WiFi setup screen.
Step 10: Wait 5 seconds for your password to change and the webpage to reload. Step 11: Once connected, you will be directed to the webpage below where you will need to select your
home WiFi network from the list in the “Detected Networks” box and type in your home WiFi’s password to connect to your router.
NOTICE In most cases you should leave the “Show IP Settings” option unticked. However, if you want to give your zappi a fixed IP address then tick the “Show IP Settings” box and fill in the extra information required. NOTICE Please be patient. It could take up to 15 seconds for the connection to take place.
Page 33 of 51

Step 12: Once connected, you will see this
screen on your zappi display. Press (+) to continue.

Step 13: By this step zappi should now be internet
connected either via WiFi or hard wired Ethernet. zappi will now check for firmware updates. Please be patient. If no Firmware updates are available jump to Step 16.

Step 14: If Firmware updates are available
zappi will proceed to download these. Showing the progress percentage on the display.

Step 15: Once download reaches 100% zappi will
proceed to install updates. zappi may reboot during this process.

Step 16: If zappi has no updates available or after updates have been installed this screen will show on
your zappi display informing you that firmware is up to date and giving you the firmware version number.
NOTICE If zappi has been installed alongside another myenergi device, refer to Linking Devices section for guidance on pairing. Also refer to the instruction documentation for the other devices.
Step 17: Go to section “9.5 Testing”.

Page 34 of 51

9.4 WiFi Connection (Retrospective)
If WiFi set-up was skipped during the start up wizard, due to no internet availability at the time of install, the customer will need to set this up themselves as soon as WiFi is available. The Firmware will also not be updated until an internet connection is made. Before you leave, ensure that the customer is aware of the actions they are required to take once WiFi is available and where they can find the step by step instructions for this. The instructions can be found below or within the User Manual which can be downloaded from the Download Centre on the myenergi website.
Step 1: Firstly, turn on the Access Point by navigating to Menu > Other Settings > Internet > WiFi > WiFi
Information on your zappi device display. If Access Point is showing as “Off”, turn to “On”.
Step 2: Once the Access Point is set to “On”, go back to the “WiFi” page by pressing the () button.
NOTICE Make a note of the SSID and Password (P/W) now, for use in the next steps.
Step 3: Connect your smartphone or computer to the myenergi access point by entering your phone or
computer WiFi Settings and searching for the network displayed with the same name as the SSID you noted down above. Once displayed, select the network to connect.
Step 4: You will be prompted for a
password. Enter the password displayed on the zappi screen that you noted down at step 2.
Step 5: You will now be prompted to create a
new password to protect the WiFi settings from being changed by anyone else. The new password must be at least 8 characters long and consist of a combination of lowercase and uppercase letters and digits.
NOTICE If page doesn’t load, type 192.168.4.1 into your web browser of mobile phone browser to enter WiFi setup screen.
Page 35 of 51

Step 6: Wait 5 seconds for your password to change and the webpage to reload. Step 7: Once connected, you will be directed to the webpage below where you will need to select your
home WiFi network from the list in the “Detected Networks” box and type in your home WiFi’s password to connect to your router.
NOTICE In most cases you should leave the “Show IP Settings” option unticked. However, if you want to give your zappi a fixed IP address then tick the “Show IP Settings” box and fill in the extra information required. NOTICE Please be patient. It could take up to 15 seconds for the connection to take place.
Step 8: Once complete, check WiFi is connected. Do this by navigating back to the WiFi Config Menu as
you did at Step 1. Check Status is showing as “Connected”.
9.5 Testing
Before leaving site, it is important that a few checks are carried out, ensuring the sensors have been correctly installed and are functional.
Step 1: Check that the time and date are correct and are displayed on the bottom left of the main screen. If
they are not present or are incorrect, set the correct time and date in the Other Settings/Time & Date menu option.
Step 2: Check that the EV will charge in FAST mode. Step 3: Check the Grid Power reading at the top right of the main screen is showing sensible readings and
the direction of power flow is as expected.
Step 4: With the EV plugged in, switch to ECO mode and check that the charge power is at minimum (about
1.4kW) OR that it is ‘tracking’ the surplus power (i.e. the Grid Power reading is 0.0kW)
Step 5: If a Generation CT has been installed, check that the generated power is shown in the top left of the
main screen. If the generation reading is missing, the most likely cause is the associated CT input is not enabled. NOTICE Remember ­ Only one CT (or three phase set of CTs) can be set to Grid.
Page 36 of 51

10. Pairing Devices
If zappi is being installed as a standalone myenergi device you can skip this section.

Up to 6 myenergi devices can be wirelessly linked together. The device you are using as your `hub’ will count as 2 of the 6 devices. By pairing devices, you can use more of your own energy or have more control and visibility. Devices available are:

eddi

A microgeneration energy diverter that uses surplus power to heat water or rooms rather than exporting to the grid.

zappi

An eco-smart electric vehicle charge point that can use surplus power to charge the car.

harvi

A self-powered wireless sensor that can be used along with myenergi load controlling devices such as libbi, eddi, zappi. It is able to detect grid import/export conditions as well as generation power and send this information wirelessly to devices such as the libbi, eddi or zappi. Using a harvi can greatly simplify installation.

libbi

A battery storage system that allows you to store your surplus self-generated energy for use when you need it most. It allows you to capture surplus PV or wind turbine generation. The libbi Controller enables you to integrate with your existing myenergi devices.

myenergi devices can be linked using either the built-in radio or with an Ethernet cable. If using an Ethernet connection all your myenergi devices simply need to be connected to the local network with an Ethernet cable running directly to the internet router.

NOTICE
If pairing zappi to another zappi or a libbi this must be done using a hardwired Ethernet cable via the router. This is to ensure the installation remains G100 compliant.

10.1 Master and Slave Devices
When two or more myenergi devices are wirelessly linked, one device will act as the master device. This device will control the other slave devices. Some settings can only be changed on the master device.
Your master/slave on your new device will be set during start-up however, if this ever needs to be changed you can set Master function in the Advanced Settings/Linked Devices menu. It’s a good idea to choose the device that is the most convenient to access should you wish to change settings.
· Note: harvi will only pair with the device which is set as the master · It is recommended that, where the Grid CT is directly connected to the eddi, that this device is chosen as
the master or vice versa. This ensures the fastest response to the grid power measurement.
10.2 Channels
On rare occasions it is possible that there are other appliances operating on the same frequency which could cause interference. If it is not possible to link devices or the connection seems poor, changing the RF Channel may help.
The channel can be changed on devices without having to re-pair them, just makes sure they are all set to the same channel.

Page 37 of 51

10.3 Pairing zappi Step 1 Go to your master’ device and in the device menu navigate to: Device Settings’ > Advanced’ >Linked Devices’ > Pairing Mode’ Your master’ will begin searching for slave’ devices’. NOTICE Identify your master device. This can be done by going into the menu of any myenergi device and navigating down to Linked Devices. The device listed in CAPITALS is set as the master. Step 2 Go to your zappi menu and navigate to: Device Settings’ > Advanced’ >Linked Devices’ > Pairing Mode’ Step 3 When you see your zappi device display on yourmaster’ device screen, select (+) or () on your
master device to confirm.
10.4 Device Settings
Most device types have settings which can only be changed via the Linked Devices menu. For example, libbi, eddi and zappi have a setting for priority and harvi has settings to configure its CT inputs. The device settings are accessed through the Linked Devices menu; select Devices then select the appropriate device and press (+) to bring up the device settings screen. Refer to the relevant device instruction document for more information regarding the actual device settings. After a device has been paired you will have to wait a few seconds for the device to update before the settings can be accessed. The screen will show DEVICES UPDATING when this is happening.
10.5 Device Priorities
The priority of each, load controlling linked device, can be set from any device with a display. The example below shows one eddi device, two zappi devices and one harvi on the same ‘network’. If you have a myenergi libbi, this will be shown in your Devices list.
1 The priority is shown on the left of each load controlling device with 1 being the highest priority. If two or more devices have equal priority, the available surplus (for that priority level) is shared between them.
2 The device shown in CAPITAL letters is the device currently being viewed. 3 The ~ symbol indicates which device has the grid CT attached/configured to
it . There should only be one in the system. 4 The serial number of each device is shown on the right. 5 If the ? symbol is shown alongside a device, it indicates that communication
has been lost from the device (the device cannot be `heard’)
Page 38 of 51

10.6 Removing Devices
A device can be removed by navigating to: Advanced Settings > Linked Devices > Device menu and then select Remove Device. If you want to remove ALL devices then go to: Advanced Settings > Linked Devices > Reset Settings
Page 39 of 51

11. Troubleshooting

Symptom Display is blank
In ECO+ mode, the charge does not start, the display is always showing Waiting for Surplus and the export power is 0W
In ECO+ mode, the charge does not start, the display is always showing Waiting for Surplus, yet the export power is showing correctly Generation power is always 0kW
Installation Limit ! displayed Display will show the phase(s) that is(are) overloaded and the prospective current that would be drawn if the zappi were allowed to start charge at the minimum current Installation Limit ! CT displayed

Cause · There is no power to
the unit · Grid Sensor
incorrectly installed · Faulty Grid Sensor · No signal from harvi
(if used)
· Export Margin set too high

Solution
· Check for correct supply voltage at the supply screw terminals (220 – 260V AC)
· Check the grid sensor is connected to a CT terminal in the zappi or any CT input in the harvi
· Check the Grid CT sensor is installed on the correct cable (see CT Sensor Installation)
· Check resistance of the sensor – it should be around 200 when not connected (remove the sensor from the cable before testing resistance)
· If using harvi, check that the CT input has been set to Grid in the harvi settings (under Linked Devices / Devices in the zappi Advanced Settings menu)
· Check Export Margin setting (default is 0W)

· Generation CT not installed
· The measured Grid Current is greater than the Grid Limit set in the zappi

· Install generation sensor and connect to one of the CT inputs
· Alternatively, if there is no Generation CT, the Generation and House consumption figures can be hidden on the main screen by changing the Icons setting in the Settings / Display & Sound menu
· Check the Grid Limit setting · Reduce the load in the property · In a three phase installation, consider rebalancing
the property load across the three phases

· The Grid CT has

· Check CT is installed correctly.

become disconnected

or is not clamped

correctly around the

grid supply cable

Page 40 of 51

12. Fault Codes
If any of the following fault messages are displayed, follow the action described.

Displayed Message Unknown Cable !
Pilot problem !
Lock Failure ! Fault code 23
Output Fault ! Fault code 24 PE Fault ! Fault code 25
Comms Fault ! Fault code 26 SelfTest Failed ! Fault code 27 Contactor Fault ! Fault code 28
PEN Fault! Fault code 29 Overload ! Fault code 30 Bad Voltage Range ! Over Voltage! Under Voltage! Fault code 31 Overheating!
Voltage Mismatch ! Fault code 32

Description zappi has detected an unknown EV cable (untethered units only) Make sure you are using genuine IEC 62196-2 compliant plugs. Range supported: 32A, 20A and 13A. zappi has detected an issue with the “Control Pilot” signal on the cable between the zappi and the EV.
The socket lock actuator couldn’t lock/unlock the inserted plug as expected (untethered units only).
zappi has detected a wrong output voltage. e.g. a voltage has been detected when it should be off. zappi has detected a problem with the main earth connection to the unit. The earth is either disconnected or the impedance of the earth connection is too high. zappi has detected an issue with the built- in protection components. The built-in protection devices couldn’t be tested or failed the test prior to a charge. The relay inside the zappi has a welded contact. The secondary relay is open to make sure that the supply to the EV is isolated. The internal protection against the loss of the PEN conductor on the electricity supply has tripped. The EV is drawing too much current ­ the output is switched off. zappi has detected that the supply voltage is too high/low and has disconnected the EV to protect it.

Action zappi will automatically retest the cable after 5 seconds. If the issue persists, unplug the cable check for dirt in the plug and try again.
zappi will automatically retest the cable after 5 seconds. If the issue persists unplug the cable, check for dirt in the plug and try again. This message can happen when the plug is not fully inserted or if it is twisted or pulled from the socket. Push the plug fully into the zappi to release the plug, then press and hold the button to reset the unit. Unplug the EV, press and hold the button to reset the unit.
Unplug the EV, check the earth connection to the zappi and then hold the button to reset the unit. If the electricity supply is “IT earthed” check the Supply Grid / Earthing menu setting. Unplug the EV, press and hold the button to reset the unit. Unplug the EV, press and hold the button to reset the unit.
Unplug the EV, press and hold the button to reset the unit.
Unplug the EV, make sure that the fault has been removed then press and hold the button to reset the unit. Unplug the EV, press and hold the button to reset the unit. Unplug the EV, make sure that the fault has been removed and hold the button to reset the unit.

The zappi unit is too hot ­ the output is switched off.
The output voltage detected by zappi and the built-in protection components is not the same.

Make sure that the zappi is properly ventilated (e.g. has not been covered). Charge will resume once the unit has cooled down again.
Unplug the EV, press and hold the button to reset the unit

If any of the above faults persist then stop using zappi and contact your supplier or myenergi Technical Support.

Page 41 of 51

13. Warranty
Full details of the myenergi product warranty are available on our web site or by using this QR code.
14. Product Registration
Please register your new myenergi devices at https://myaccount.myenergi.com/registration
Page 42 of 51

15. Technical Specifications

15.1 Performance

Mounting Location

Indoor or Outdoor (permanent mounting)

Charging Mode

Mode 3 (IEC 61851-1 compliant communication protocol)

Display

Graphical backlit LCD

Front LED

Multicolour, according to charge status, current and user setting

Charging Current

6A to 32A (variable)

Dynamic Load Balancing

Optional setting to limit current drawn from the unit supply or the grid

Charging Profile

3 charging modes: ECO, ECO+ or FAST. STOP is a further option

Connector Type

Type 2 tethered cable (6.5m) or type 2 socket with locking system

Compliance

LVD 2014/35/EU, EMC 2014/30/EU, EN 62196-2:2017, ROHS 2011/65/EU, CE

Certified, EN 61851-1:2019*

  • zappi complies fully with EN 61851-1:2019 with the exception of Clause 8.4 in order to meet the requirements of

BS 7671:2018 Amendment 1:2020 which requires the protective earth conductor to be switched in order to provide

protection against a damaged PEN conductor in a TN-C-S earthed electrical system.

15.2 Electrical Specifications

Rated Power

7kW (1-phase) or 22kW (3-phase)

Rated Supply Voltage

230V AC Single Phase or 400V AC 3-Phase (+/- 10%)

Supply Frequency

50Hz

Rated Current

32A max

Standby Power

3W

Consumption

Economy Tariff Sense

230V AC sensing (4.0kV isolated)

Input

Wireless Interface

868 MHz / 915 MHz (-A units) proprietary protocol for wireless sensor

and remote monitoring options

Grid Current Sensor

100A max. primary current, 16mm max. cable diameter

Supply Cable Entry

Rear / Bottom / Left side / Right side

15.3 Mechanical Specifications

Enclosure Dimensions

439 x 282 x 122mm

Protection Degree

IP65 (weatherproof)

Enclosure Material

ASA 6 & 3mm (UL 94 flame retardant) colours: white RAL 9016 and grey

RAL 9006

Operating Temperature -25°C to +40°C

Fixing Points

In-line vertical mounting holes

Weight

Single Phase Untethered: 3.0kg

Three Phase Untethered: 3.3kg

Single Phase Tethered: 5.5kg

Three Phase Tethered: 7.2kg

15.4 Connectivity
WiFi 2.4 GHz 802.11BGN Connection up to 150 Mbps

WiFi Frequency Range 2412-2484 MHz

Radio Frequency Range 868-870MHz

Radio Frequency (Australia) 915MHz

15.5 Max Transmitted Power

Radio

25mW

WiFi

100mW

Page 43 of 51

16. Model Variants

Model No. ZAPPI-2H07UW-G

Rating 7kW

ZAPPI-2H07TW-G

7kW

ZAPPI-2H07UB-G

7kW

ZAPPI-2H07TB-G

7kW

ZAPPI-2H22UW-G

22kW (3-Phase)

ZAPPI-2H22TW-G

22kW (3-Phase)

ZAPPI-2H22UB-G

22kW (3-Phase)

ZAPPI-2H22TB-G

22kW (3-Phase)

Connector Untethered Tethered Untethered Tethered Untethered Tethered Untethered Tethered

Colour White White Black Black White White Black Black

Designed to permit installations compliant with IET Wiring Regulations BS 7671:2018 Amendment 1:2020 and the Electricity Safety, Quality, and Continuity Regulations 2002 and BS 8300:2009+A1:2010.

17. Technical Support
If you experience any issues with your zappi during or post installation, please contact our Technical Support Team by scanning the QR Code below.

Please contact us directly for the quickest solution.

Page 44 of 51

Appendix A
Electric Vehicle (Smart Charge Points) Regulations 2021
As of 30th June 2022
Relevant to zappis INSTALLED from 30th June 2022
1. Electric Vehicles (Smart Charge Points) Regulations 2021
From 30th June 2022, any EV charger installed in a private setting i.e. home or workplace NOT public, in England, Scotland and Wales has to meet the Electric Vehicles (Smart Charge Points) Regulations 2021.
1.1 Purpose of the Regulations
The new smart charging regulations are a huge, positive forward-step by the UK Government in preparing our homes and businesses for a smart, connected and democratized energy system. Essential tools in driving down emissions and a core reason why myenergi exists. The regulations are focused around when you are charging an EV. The aim of the regulations is to prevent everyone charging at the same time and putting too much demand on the grid.
1.2 What’s changed with zappi
New features have been added to zappi to ensure our products remain compliant with UK Regulations. These include:
· Randomised Delay ­ At the start of a charge and end of a scheduled, Timed Boost there will be a delay of up to 10 minutes before your vehicle starts and stops charging. This could be a few seconds or it could be up to the full 10 minutes. This is necessary to ensure everyone does not overload the grid by starting to charge or ending a charge at the same time. The Randomised Delay can be overridden, if necessary (See 1.3.2 for further details).
· Smart Scheduling ­ To comply with the smart charging regulations your zappi will be set to charge in off-peak hours by default. This is between 00:00 ­ 08:00. You may change this schedule at any time if you would prefer to charge in peak hours or your electricity tariff off-peak hours differ from those set.
· Default to ECO+ mode ­ If Smart Regulations apply, zappi will default to ECO+ mode on first boot up. · Charging logs ­ You will now be able to view a record of charging logs from the past 13 months. See
Charge Logs section below for further information.
1.3 Randomised Delay: How it works
As mentioned above, Randomised Delay will put a completely random delay at the start of a charge and end of a scheduled, Timed Boost, for up to 10 minutes. This can be overridden by the customer in situations where they are in a hurry. 1.3.1 Delay Status You will be able to see if your charger is in a state of delay at any time as it will be displayed on both the zappi screen and in the myenergi app.
Page 45 of 51

1.3.2 Overriding the delay To override the delay simply press the +’ button on the zappi or press thecharge now’ button displayed in the pop-up message within the myenergi app. If the delay is overridden your charge will start/stop immediately.
You cannot permanently override the delay function. If you wish to override the delay each time you charge, you will need to follow the above instruction to override on every applicable charging session.
1.4 Smart Scheduling: How it works
As summarised under section 1.2 your zappi will be set to charge in off-peak hours by default from initial start-up. 1.4.1 Off-peak hours Off-peak hours are usually between 00:00 ­ 08:00, depending on your specific tariff, this is when your electricity will be at it’s cheapest. 1.4.2 Reason for Smart Scheduling Encouraging you to charge in off-peak hours prevents overloading the grid in peak times. 1.4.3 Benefits of Smart Scheduling Smart Scheduling will can help you spend less on your electricity. By charging in off-peak hours your electricity tariff may be cheaper. 1.4.4 Changing the set schedule If the default schedule does not suit your requirements, or your electricity tariff’s off-peak hours differ from the schedule set, you can amend your schedule at any time from the zappi menu or within the myenergi app. To adjust your schedule in the app navigate to the Set Boost Parameters’ option, select start time and set the number of hours you want your charger to boost for. To change the schedule on your zappi device navigate toCharge Settings > Boost Timer’ and amend the schedule as desired. For further information see the Timed Boost section of the User Manual. Alternatively, the schedule may be deleted altogether, if required. To do this ensure all inputs are set to 00:00 for each day of the week.
1.5 Defaulting to `ECO+’ Mode
As mentioned in section 1.2 if your zappi meets the Smart Regulation parameters it will default to ECO+ mode upon first start-up. This can be changed to ECO+ or FAST mode at any time by the customer. See Charging Modes section of the User Manual for further information on modes.
Page 46 of 51

1.5.1 Manual Boost If you choose to remain in ECO+ mode you can still charge from the grid at any time by doing a Manual Boost. Refer to Manual Boost section of the User Manual for further information on this existing feature.
1.6 Charging Logs
Providing your zappi is internet connected and you have registered your device in myaccount you will be able to view a record of charge logs for the last 13 month period. This function will begin from 30th June 2022 so the earliest time you will see the whole 13 months will be from July 2023 or 13 months from when your device was connected to the internet. The charge logs will tell you when the charge started, when the session ended and the duration of each session. To view your logs log into your account at https://myaccount.myenergi.com/login Navigate to “My Energi Usage” in the left hand menu. The charge logs will be displayed like to example below.
Page 47 of 51

Appendix B
Electric Vehicle (Smart Charge Points) Regulations 2021 As of 30th December 2022
Applies to all zappis Installed on or after 30th December 2022 2. Electric Vehicles (Smart Charge Points) Regulations 2021
In addition to the regulations explained in Appendix A, from 30th December 2022, any EV charger installed in a private setting i.e. home or workplace NOT public, in England, Scotland and Wales has to meet FURTHER conditions to the Electric Vehicles (Smart Charge Points) Regulations 2021.
2.1 Purpose of the Regulations
Every day cyber criminals make attempts to target individuals and organisations. With a cyber attack attempted every 39 seconds these regulations have been put in place to mitigate the risk of this and ensure your device and information is secure from increasingly sophisticated attacks.
2.2 What’s changed with zappi
The following features have been added to all zappis to comply with the Electric Vehicles (Smart Charge Points) Regulations 2021, Schedule 1, from 30th December 2022: Set-up Wizard ­ The set-up wizard at power up has been changed to ensure smoother initial set-up. This includes internet connection and firmware updates upon start up. Automatic Firmware Checking ­ zappi will regularly check for new software and will automatically display a message on your zappi screen to let you know in the myenergi app when updates are available. Tamper Detection ­ We have added built-in tamper detection to alert you if anyone has removed the front cover of your zappi. You will be alerted in the myenergi app when tamper activity is detected. Encryption ­ To protect your data from eavesdroppers zappi uses Advanced Encryption Standard (AES) to securely communicate throughout your home and across the internet.
Page 48 of 51

2.3 Automatic Firmware Checking
Being on the latest firmware is one crucial way to prevent security breaches. To ensure you are always on the most up-to-date firmware, your zappi will regularly check for new software and you will be notified in your myenergi app when updates are available. You then have the option to select “Install now” or “later”.
NOTICE Firmware updates can only be delayed up to 3 times.
2.4 Tamper Detection
A tamper detection feature has been added to our zappi devices. This ensures that any time the cover is removed from your zappi you will be alerted that it has been tampered with.
l
2.5 AES Encryption
To protect your data from eavesdroppers zappi uses Advanced Encryption Standard (AES) to securely communicate throughout your home and across the internet. Linked devices will communicate via AES and communication between your devices and the internet will also be via AES. For customers with older myenergi devices that don’t have the compatibility to communicate in encryption there is a new device menu setting which allows you to turn off encryption. If encryption is turned off this will only turn off encrypted communication locally between devices. Communication externally across the internet will still use encryption.
Page 49 of 51

2.6 Installer Requirements
It is the responsibility of the installer to ensure they are compliant with Electric Vehicles (Smart Charge Points) Regulations 2021. This includes, but is not limited to:
· Installing only compliant charge points in private installs from and including 30th December 2022. · Answering the start-up wizard questions accurately to reflect actual install parameters. · Having a Technical File and/or Declaration of Compliance available if requested by the customer
(myenergi’s Technical File and Declaration of Compliance is available at: https://myenergi.com/guides/smart-charge-point-regulations-explained/ The installer should ensure they are fully aware of and understand how the regulations affect them and what they are required to do to ensure they comply. These regulations should be monitored for any future updates. For further information or to view the current Electric Vehicles (Smart Charge Points) Regulations 2021 visit: https://www.legislation.gov.uk/ukdsi/2021/9780348228434 or https://www.gov.uk/guidance/regulations-electric-vehicle-smart-charge-points Further information can also be found by following the QR code below which will take you to myenergi’s Smart Regulations webpage which contains reference documents, FAQs and simplified explanations of the regulations.

Smart charge point regulations explained

Page 50 of 51

myenergi
Designed and manufactured in the UK by myenergi Ltd, Pioneer Business Park, Faraday Way,
Stallingborough, Grimsby, DN41 8FF T: +44 (0)333 300 1303 E: sales@myenergi.com W: myenergi.com
Page 51 of 51

References

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

Related Manuals