Installation Procedure Lee Check Valve, 6 mm Zero Leak, Press-In, Forward Flow Orientation
Overview
This procedure is intended to provide process guidelines for proper installation of Lee Check Valve, 6 mm Zero Leak, and Press-In product in forward flow orientation. Section 2 provides an overview of the installation hole requirements. Section 3 contains the installation procedure and customer assembly process recommendations. Section 4 contains reference information on the installation hole and installation tool. Compliance with this installation procedure will ensure optimal product performance. Please contact your local Lee Company Sales Representative for questions concerning the installation of Lee Company products.
Installation Hole Requirements
The Lee Check Valve, 6 mm Zero Leak, Press-In product is designed for installation into plastic manifolds or fittings and to perform well under adverse conditions. Installation hole specifications, as found on Lee Installation Hole Drawing1INST129591S (Appendix A), will ensure proper operation of the Lee Check Valve, 6 mm Zero Leak, Press-In product. The hole should be clean, dry, and free of burrs/flash. The series of smoothly curved lands of the Lee Check Valve, 6 mm Zero Leak, Press-In product allow the valve to be pressed in while the plastic flows into the adjacent grooves. Some plastics with sufficient elongation, such as Polypropylene, Nylon, Acetal, Polyethylene and PEEK, cold flow into the grooves affecting retention and sealing. Rigid plastics, such as acrylic and polycarbonate, have the risk of cracking from the stress of the interference installation. For installation into these types of plastics contact your local Lee Company Sales Representative for more information.
Installation
Installation Overview for Forward Flow Installation
- For forward flow applications the Lee Check Valve, 6 mm Zero Leak, Press-In product is inserted into the installation hole oriented as shown.
- The installation tool (P/N: CCRT0068699S) is used to simply press the valve into a plastic installation hole until the valve is at a minimum flush with the top of the installation hole.
- The series of smoothly curved lands of the Lee Check Valve, 6 mm Zero Leak, Press-In seals and retains the product in the plastic installation hole.
Factory Best Practices
- Examine the condition of the installation tool at appropriate intervals and replace if damaged or chipped.
- Clean feed bowls once per day.
- Turn off vibratory feed bowl when the assembly station is idle, or if the feed rail is full of parts.
- Use the minimum vibration setting to advance valves in the feed bowl.
- If the check valve is blown into the assembly area from the feed rail, minimize the air pressure at which the check valve is blown into the assembly area to prevent possible damage.
Appendices
Appendix A Installation Hole Dimensions
DIMENSIONS IN MILLIMETERS
Note: Draft angle to fall within diameter tolerance Refer to Lee Drawing No. 1INST129591S
Appendix B Installation Tool Dimensions
DIMENSIONS IN MILLIMETERS AND INCHES
- Material : A2 Tool Steel
- Hardness : 55-60 Rc Marked with part number and revision. Refer to Lee Part No. CCRT0068699S