MillerEdge RBand Wireless Sensing Edge System Instructions

June 3, 2024
MillerEdge

MillerEdge RBand Wireless Sensing Edge System

RBand Wireless Sensing Edge System Instructions

For Commercial Door Operators Using a T3/DC (red band) or T2 Edge (blue band)
WARNING
BE SURE ELECTRICAL POWER HAS BEEN DISCONNECTED FROM THE INPUT POWER LINES PRIOR TO REMOVING THE ELECTRICAL BOX COVER. AN APPROPRIATE LOCK-OUT/TAG-OUT PROCEDURE IS RECOMMENDED.

CAUTION: THIS PROCEDURE MUST BE PERFORMED WITH THE DOOR IN THE CLOSED POSITION ONLY.

Door Installation

Wireless Edge System:

  1. Move door to the fully closed position.
  2. Remove power from the unit. Use proper lock-out/tag-out procedures. (Refer to OSHA Standard 1910.147).
    NOTE: This instruction only applies to connecting the RBand Wireless Monitored Edge System to the operator, use instruction included with sensing edge system to install the edge and program the wireless system. Use the chart below to determine the appropriate wiring diagrams to use for the application

__

Edge Type & Operation

| __

Operator Series

| RB-P-K10

Receiver

Wiring

| RB-TX10

Transmitter

Wiring

| GT3C

Converter

Wiring

| Door Layout
---|---|---|---|---|---
T3 Monitored Safety Edge (red band)| X and Y-Series Counter, Light, Medium, Standard & Heavy-Duty| Fig. 1| Fig. 4| Fig. 4| Fig. 6
T3 Monitored Safety Edge (red band)| Light-Duty Jackshaft & Trolley| Fig. 2| Fig. 4| Fig. 4| Fig. 6
T2 Monitored Safety Edge (blue band)| X and Y-Series Counter, Light, Medium, Standard & Heavy-Duty| Fig. 1| Fig. 5| Not Used| Fig. 8
T2 Monitored Safety Edge (blue band)| Light-Duty Jackshaft & Trolley| Fig. 2| Fig. 5| Not Used| Fig. 8
T3 Non-Monitored Safety Edge (red band)| X and Y-Series Counter, Light, Medium, Standard & Heavy-Duty| Fig. 3| Fig. 4| Fig. 4| Fig. 7
T2 Non-Monitored Safety Edge (blue band)| X and Y-Series Counter, Light, Medium, Standard & Heavy-Duty| Fig. 3| Fig. 5| Not Used| Fig. 9

  1. Mount the RBand receiver near the operator powerhead in a dry area.
  2. Route wire from RBand receiver to operator powerhead and attach as shown below.
  3. Mount RBand RB-TX10 transmitter, GT3C converter (when required), transformer (when required) and edge sensor as shown in the manufacturers instructions.
  4. Wire safety edge, GT3C converter (when required) per application using table above.
  5. Insert batteries into the RB-TX10 transmitter and GT3C converter (when required)
  6. Apply power to operator.
  7. Follow RBand instruction sheet to learn the RB-P-K10 receiver to the RB-TX10 transmitter.
  8. Program operator ODC-STB to the ON status (see installation manual).
  9. Run full operational and safety function test.

**RBand Transmitter & Converter Wiring Installation for Wireless T3

Safety Edge**

MillerEdge-RBand-Wireless-Sensing-Edge-System-fig-1

RBand Transmitter Wiring Installation for Wireless T2 Safety Edge


MillerEdge-RBand-Wireless-Sensing-Edge-System-fig-3MillerEdge-RBand-Wireless-Sensing-Edge-System-
fig-4

MONITORED T3 or T2 Wireless Sensing Edge RBand Receiver Wiring

Installation

MillerEdge-RBand-Wireless-Sensing-Edge-System-fig-5

Light-Duty Commercial Trolley & JackshaftMillerEdge-RBand-Wireless-
Sensing-Edge-System-fig-6

NON-MONITORED T3 or T2 Wireless Sensing Edge RBand Receiver Wiring

InstallationMillerEdge-RBand-Wireless-Sensing-Edge-System-
fig-7

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

Related Manuals