EarthSafe i-1000 Ongrid Wind Turbine Instruction Manual
- July 12, 2024
- EarthSafe
Table of Contents
- i-1000 Ongrid Wind Turbine
- Specifications:
- Product Information:
- Product Usage Instructions:
- Requirements at the Place of Use:
- Unpacking and Assembly:
- Electrical Connections:
- Erection and Operation:
- Maintenance:
- Troubleshooting:
- Q: How do I know if my wind turbine system is operating
- Q: What should I do in case of an emergency shutdown?
i-1000 Ongrid Wind Turbine
“`html
Specifications:
- Product: Wind turbine system L-002QJULG
- Brand: EarthSafe
Product Information:
The EarthSafe wind turbine system is designed to harness wind
energy efficiently, helping you save energy and contribute to a
sustainable planet. It comes with components for easy installation
and operation.
Product Usage Instructions:
Requirements at the Place of Use:
Before installation, ensure the following requirements are
met:
-
Permissible wind class, footprint, and minimum clearances as
specified in the manual. -
Adequate tower foundation to support the wind turbine
system.
Unpacking and Assembly:
Follow these steps to assemble the wind turbine system:
- Unpack all components carefully.
- Assemble the wind turbine according to the provided
instructions.
Electrical Connections:
Make sure to connect the electrical components correctly
following the provided wiring diagram.
Erection and Operation:
Erect the wind turbine in a suitable location with proper
clearances. Follow the steps for switching on the system for normal
operation.
Maintenance:
Regular maintenance is essential for optimal performance. Follow
safety precautions during maintenance work and adhere to the
maintenance schedule provided in the manual.
Troubleshooting:
Refer to the troubleshooting and diagnostics section in case of
errors with or without LED indicators.
FAQ:
Q: How do I know if my wind turbine system is operating
efficiently?
A: You can monitor the performance using the provided
performance charts. Any deviations from expected output may
indicate a need for maintenance.
Q: What should I do in case of an emergency shutdown?
A: Follow the emergency shut-down procedure outlined in the
manual to ensure safety and proper handling of the wind turbine
system.
“`
TRANSLATION OF THE ORIGINAL INSTRUCTIONS
– Keep handy at the place of use –
Wind turbine system
L-002QJULG
SAVE
ENERGY
SAVE
PLANET
EarthSafe
1 Contents
1 2 2.1 2.1.1 2.1.2 2.1.3 2.2 2.2.1 2.2.2 2.3 2.4 2.5 3 3.1 3.2 3 3.4 4 5.1 5.1.1 5.1.2 6 6.1 6.2 6.3 7 7.1 7.1.1 7.1.2
Contents ……………………………………………………………………………………. 2 General………………………………………………………………………………………. 4 About this translation of the original instructions ………………………………… 4 Revision status of the original instructions ………………………………………….. 4 Conditions for installing and operating the wind turbine system ……………. 4 Availability of the instructions…………………………………………………………….. 4 Conventions used in this translation of the original instructions……………… 4 Other symbols used ………………………………………………………………………….. 5 Information ……………………………………………………………………………………… 5 Name and address of the manufacturer and his authorised representative 5 Warranty and liability ……………………………………………………………………… 6 Product feedback ……………………………………………………………………………. 6 Technical escription…………………………………………………………………… 6 Intended use …………………………………………………………………………………. 6 Reasonably foreseeable misuse………………………………………………………… 6 Main components……………………………………………………………………………. 7 Main components of the wind turbine ………………………………………………. 8 Technical ata……………………………………………………………………………. 9 Permissible operating and storage conditions…………………………………… 1 Storage ………………………………………………………………………………………… 1 Operation ………………………………………………………………………………………. 1 Safety /nformation ……………………………………………………………………… 1 Modifications or changes by the user ………………………………………………… 1 Residual risks…………………………………………………………………………………. 1 Personnel requirements…………………………………………………………………… 1 Preparing to use the ^ystem………………………………………………………….. 1 Shipping ………………………………………………………………………………………… 1 As-delivered condition …………………………………………………………………. 1 Scope of supply ……………………………………………………………………………… 1
2 of 2 Translation of the original instructions iSTA wind turbine system 2.0.201 I00
EarthSafe
7.2
Requirements at the place of use ……………………………………………………… 1
7.2.1 Permissible wind class, footprint and minimum clearances ………………… . 1
7.2.2
Tower foundation ………………………………………………………………………….. 1
7.3
Unpacking the components ……………………………………………………………… 1
7.4
Assembling the wind turbine………………………………………………………… 1
7.5
Electrical connections ……………………………………………………………………… 1
7.6
Erecting the wind turbine …………………………………………………………………. 1
8
Normal Kperation ………………………………………………………………………. 1
8.1
Switching on the wind turbine system………………………………………………… 1
8.2
Restart after an emergency ……………………………………………………………… 1
9
Shutting down the tind durbine ^ystem ……………………………………….. 1
9.1
Emergency shut-down ……………………………………………………………………. 1
10 Maintenance …………………………………………………………………………….. 1
10.1
Safety precautions during maintenance work……………………………………… 1
10.2
Inspection and maintenance schedule ………………………………………………. 1
10.3
Maintenance and cleaning by the user ………………………………………………. 1
11
Troubleshooting and iagnostics……….
11.1 Errors with LED……………………………………………………………………………….
11.2
Errors without LED…………………………………………………………………………..
12
Removal from ^ervice and isposal ……………………………………………….
12.1
Final decommissioning of the wind turbine system ………………………………
12.2
Disposal of the wind turbine system and components ………………………….
13
Declaration of onformity …………………………………………………………… 2
14
Index………………………………………………………………………………………… 2
15
Notes ………………………………………………………………………………………. 2
16
Performance Charts……………………………………………………………………………… 2
Translation of the original instructions iSTA wind turbine system 2.0.201 I00 3 of 2
EarthSafe
2
2.1
2.1.1 2.1.2
2.1.3
2.2
General
About this translation of the original instructions
Revision status of the original instructions
Revision date: ……………………………………………………………………………… ..201 Revision index:
……………………………………………………………………………… 00 Conditions for installing and operating the
wind turbine system
Please make sure that
· The wind turbine system has been erected correctly by a suitably trained
person.
· All operating personnel have read and fully understood this translation of
the original instructions
· The wind turbine system is properly maintained and repaired.
Availability of the instructions
Keep this translation of the original instructions handy at all times, so that
it can be referred to by all persons working on or with the wind turbine
system.
Conventions used in this translation of the original instructions
Safety information is always identified by a signal word and in some cases
also by a hazard-specific symbol.
DANGER!
Immediate danger! Non-observance of the safety instructions will result in
serious or fatal injury!
WARNING!
Potentially dangerous situation! Non-observance of the safety instructions can
result in serious or fatal injury!
CAUTION!
Potentially dangerous situation! Non-observance of the safety instructions can
result in minor or moderate injuries!
IMPORTANT!
Potentially dangerous situation! Non-observance of the safety instructions can
result in damage to property or pollution of the environment!
4 of 2 Translation of the original instructions iSTA wind turbine system 2.0.201 I00
EarthSafe
2.2.1
Other symbols used
The following symbols are used in this translation of the original
instructions as well as on the wind turbine system itself:
Warning signs
General warning!
Danger: High voltage!
May start without warning!
Environmental hazard!
Table 1 Warning signs
Mandatory signs Read manual before operating!
Isolate before opening!
2.2.2
2.3
Table 2 Mandatory signs
Information
Note Indicates general information and recommendations.
Name and address of the manufacturer and his authorised representative
Name
ALTINEL ENERJI DIS TIC. ELEK. ELEKTRONIK SAN.VE TIC. LTD. STI
Address
*|NHYOHU0DK6N1RG- (VHQXUW / Istanbul785.(<
Phone Internet
0090-212-8812235 www.altinelenerji.com
Table 3 Manufacturer
Name
)DVW7UDGLQJ/WG
Address 8O6WDQFÕRQQD1R(W%$WRV%8/$5,$
Phone
Internet www.istabreeze.com
Table 4 Authorised representative
Translation of the original instructions iSTA wind turbine system 2.0.201 I00 5 of 2
EarthSafe
2.4 Warranty and liability
The “General Terms of Sale and Delivery” of the manufacturer or his authorised
representative apply.
2.5 Product feedback
Please notify the manufacturer or his authorised representative about any of
the following · Accidents · Potential safety hazards associated with the wind
turbine system · Ambiguities in this translation of the original instructions
· Description of the wind turbine system
3 Technical ‘escription
3.1 Intended use
· The wind turbine system may only be used as a “small wind turbine system”
(SWTS) to generate power in accordance with EN 61400-2.
· The wind turbine system may only be operated in accordance with the ratings
and in the approved wind class (refer to the technical data).
· Observance of the original instructions and compliance with the maintenance
and repair instructions are essential preconditions of use for the intended
purpose.
3.2 Reasonably foreseeable misuse
All forms of use which deviate from or exceed the limits of use described
above are considered to be contrary to the intended purpose. The manufacturer
is not liable for any damage resulting from such use. No liability will be
accepted by the manufacturer if the equipment has been altered as well as in
the event of improper assembly, installation, start-up, operation, maintenance
or repair. Only original parts supplied by the manufacturer are approved as
spare parts or accessories. Any spare parts or accessories not supplied by the
manufacturer have not been tested for operation and could be detrimental to
reliability. No liability will be accepted by the manufacturer for any damages
which result from the use of non-approved spare parts or accessories.
Reasonably foreseeable misuse includes: · Operation outside the manufacturer’s
specification · All modifications or changes to the wind turbine system
without the
manufacturer’s written approval! · Use of parts other than iSTA Breeze
original parts. · Operation in non-approved SWTS classes. · Operation in
strong winds or hurricanes.
6 of 2 Translation of the original instructions iSTA wind turbine system
2.0.201 I00
EarthSafe
3.3 Main components 2QO 6DPSOH &RQQHFWLRQ ‘LDJUDP 2QO :LQG WXUELQH
ZLOOEHGHOLYHU
Fig. 1: Main components of the wind turbine system
No. Component 1 Wind turbine
Function Converts wind energy into electrical energy
ULG7LH,QYHUWHU Converts HQHUJIURPWXUELQH$FULG7LH
‘XPS/RDG,WDEVRUEVH[FHVVFXUUHQWIURPWKHLQYHUWHU ULG7LHULG7LHFRQQHFWLRQ
Table 5 Main components and their functions
Translation of the original instructions iSTA wind turbine system 2.0.201 I00 7 of 2
EarthSafe
3.4 Main components of the wind turbine
3
4
5
6 2
1 7
Fig. 2: Main components of the wind turbine No. Component
Quantity
1 1RVH
1
2 Rotor blade
3
3 Hub for holding the blades
1
4 Generator for producing electricity
1
5 %RRP IRU ZLQG GLUHFWLRQ IODJ
1
6 Tail vane for turning the blades into the wind
1
7
Adapter stud 37 mm for attaching the wind turbine to the tower
1
Table 6 Main components of the wind turbine and their functions
8 of 2 Translation of the original instructions iSTA wind turbine system 2.0.201 I00
EarthSafe
4 Technical ‘ata
DesignationL-002Q*ULG
Generator
7SH
Permanent magnet rotor, brushless, JHDUOHVV, maintenancefree
Weight [kg]
Max. power
V$&A
:
2SHQ FLUFXLW YROWDJH >9$&@ 0D[
9$&
C u r r e n t
3-phase$&
Start of charging
Approx. 3 m/s (wind speed)
Housing material
$OXPLQLXP
Direction of rotation Test standard Rotor blades Hub flange
$Q EN 61000-6-1 (electromagnetic compatibility VXVFHSWLELOLW) EN 61000-6-3
(electromagnetic compatibility emissions)
&DVW 6WHHO
Diameter, approx. [m] .
5RWRU %ODGHV SLHFHV RI SODVWLF ZLWK JODVV ILEHU PL[WXUH
$SSUR[ Z H URWRU EODGH
L
JK >J@
W
S H
U
%ODGH &RORU
%ODFN RU :KLWH
‘LUHFWLRQ RI 5RWDWLRQ IURP WKH IURQW LQ D FORFNZLVH GLUHFWLRQ
0D[ 6SHHG >USP@
Noise emissions [dB(A)] Table 7 Technical data
Translation of the original instructions iSTA wind turbine system 2.0.201 I00 9 of 2
EarthSafe
.1
.1.1
.1.2
Permissible operating and storage conditions
Storage
· Ambient temperature: to +40°C ·Storage location: Dry, frost-free
Operation
· Ambient temperature: -25 to +40°C · Place of use: Max. SWTS Class III acc.
to EN 61400-2
Safety ,nformation
.1 Modifications or changes by the user
The wind turbine system is in conformity with the European Machinery Directive
2006/42/EC provided only original iSTA Breeze components are used and subject
to proper erection. The use of components from other manufacturers as well as
modifications or changes to the wind turbine system by the user are prohibited
and could render the declaration of conformity invalid!
.2 Residual risks
Any residual risks which arise as a result of operation or maintenance are
described in the relevant sections of these instructions.
.3 Personnel requirements
All work on the wind turbine system must be carried out by authorised persons!
Such persons must be familiar with the safety devices and regulations prior to
carrying out the work.
Authorised persons are defined as follows:
Operating mode
Necessary qualifications
Erection
Suitably trained persons
Normal operation
Trained personnel
Cleaning
Trained personnel
Maintenance
Suitably trained persons
Repair
Manufacturer
Table 8 Personnel requirements
1 of 2 Translation of the original instructions iSTA wind turbine system 2.0.201 I00
EarthSafe
Preparing to use the 6ystem
.1
.1.1
.1.2
.2
.2.1
Shipping
As-delivered condition The wind turbine system is shipped disassembled. Scope
of supply Refer to the contract documentation for the scope of supply.
Requirements at the place of use
Permissible wind class, footprint and minimum clearances
WARNING!
Danger to life due to operation in non-approved wind classes! The wind turbine
system may only be operated at Class III wind sites.
For information on local wind classes, please contact the responsible authorities or your nearest meteorological office.
2 H H
2 H
20 H
Fig. 3: Footprint and minimum clearances
The place of use must be free of obstacles; alternatively, the wind turbine
must be erected with a sufficient height (refer to Fig. 3:). Obstacles are
defined as houses, hedges, trees, hills, etc.
When choosing the place of use, make sure adequate room is available to tilt the tower and blades if necessary.
Translation of the original instructions iSTA wind turbine system 2.0.201 I00 1 of 2
EarthSafe
.2.2 Tower foundation
.J0DVW6HW
1 of 2Translation of the original instructions iSTA wind turbine system 2.0.201 I00
EarthSafe
.3 Unpacking the components
Carefully open the packaging. Check the shipment for completeness (refer to
the shipping documents). Separate the packaging material and dispose of it in
an environmentally
responsible way.
.4 Assembling the wind turbine
WARNING!
Danger due to rotor imbalance! Always replace the complete set of rotor
blades.
Risk of injury in case of assembly at windy sites! Choose an assembly site
which is sheltered from the wind. The assembly process requires calm weather
conditions.
2
3
5
1
4
Fig. 6: Assembling the wind turbine
)RU LQVWDOODWLRQ VHOHFW VKHOWHUHG SODFH +ROG SURSHOOHU EODGH ZLWK IODW VLGH WR
KXE )DVWHQ ZLWK D 0[ EROW QXW DQG RQH 6FUHZ RQ IXUWKHU 0[ VFUHZV DQG WLJKWHQ E
KDQG $WWDFK ERRP URG ZLWK 0[ EROW WR DOWHUQDWRU KRXVLQJ 6FUHZ QRVH WR KXE ZLWK
0[ VFUHZ 6FUHZ ZLQG YDQH WR ERRP ZLWK 0[ EROW 3OXJ LQ SLQ PP DV PDVW
FRQQHFWLRQ
Translation of the original instructions iSTA wind turbine system 2.0.201 I00
1 of 2
EarthSafe
Fig. 7: Balancing the rotor (Y position) 0RYH URWRU WR < SRVLWLRQ VHH )LJ
&DUHIXOO UHOHDVH URWRU EODGH 2EVHUYH LQ ZKLFK GLUHFWLRQ WKH URWRU WXUQV WKH
KHDYLHU URWRU EODGH SXVKHV GRZQZDUGV 5HSHDW WKH SURFHVV IRU DOO WKUHH
SRVLWLRQV WR GHWHUPLQH ZKLFK URWRU EODGH LV LQ LPEDODQFH &KHFN UHSHOOHU IRU
EDODQFH 7LJKWHQ DOO VFUHZV WR 1P &KHFN EDODQFH DJDLQ 6HFXUH DOO VFUHZV ZLWK
ORFNLQJ YDUQLVK
1RWH 7KH UHSHOOHUV KDYH DOUHDG EHHQ WHVWHG IRU HTXDO ZHLJKW E WKH PDQXIDFWXUHU
.5 Electrical connections DANGER!
Danger: High voltage! All work on electrical equipment must be carried out by
a qualified
electrician with the power switched off!
Note: To ensure proper operation, you must use an original iSTA Breeze charge
controller.
Connect a three-wire cable with a suitable cross-section (refer to Table 9 /
Table 10) and the required length to the generator. Make the electrical
connections as shown in Fig. 1:. Connect the charge controller and the
transformer as shown in the
connection diagram (refer to the relevant documentation).
Distance between generator and charge controller [m]
< 11 11 18 18 29 20 44 44 68 68 110
Cable cross-section [mm] .5
1
Table 9 Cable cross-section with ZRQJULG generator voltage
1 of 2 Translation of the original instructions iSTA wind turbine system 2.0.201 I00
EarthSafe
Feed the three-wire cable through the tower right up to the top. Provide
suitable strain relief. Connect the wires to the generator.
Fig. 8: Connecting the three-wire cable to the generato 6KRUW FLUFXLW DOO
SKDVHV WR DFWLYDWH WKH JHQHUDWRU EUDNH.1 3XOO D VXLWDEOH VKULQN WXEH RYHU HDFK
ZLUH RI WKH FDEOH 7ZLVW DQG VROGHU HDFK ZLUH RI WKH FDEOH WR WKH ZLUH IURP WKH
JHQHUDWRU 3XOO KHDW VKULQN WXELQJ RYHU WKH VROGHU MRLQW DQG VKULQN :UDS HDFK
ZLUH ZLWK WH[WLOH LQVXODWLQJ WDSH
.6 Erecting the wind turbine WARNING!
Danger due to unsuitable tower constructions! 2QO XVH WHVWHG PDVW
FRQVWUXFWLRQV RU RULJLQDO L67$ %UHH]H PDVWV &KRRVH D PDVW GLDPHWHU PP VR WKDW
WKH URWRU EODGHV DUH QRW SUHVVHG DJDLQVW WKH PDVW GXULQJ D VWRUP Attach the
wind turbine to the tower. Be careful not to damage the cable. 6FUHZ ZLQG
JHQHUDWRU WR PDVW (UHFW WKH PDVW $OLJQ WKH PDVW YHUWLFDOO LQ DOO GLUHFWLRQV
%UDFH WKH YHUWLFDO PDVW VHH )LJ .XU]VFKOXVV DXIKHEHQ
1 :KHQ XVLQJ WKH L67$ %UHH]H FKDUJH FRQWUROOHU SUHVV WKH EUDNH EXWWRQ
Translation of the original instructions iSTA wind turbine system 2.0.201 I00
1 of 2
EarthSafe
Normal 2peration
For information on operating the iSTA Breeze charge controller, refer to the
separate instructions.
.1 Switching on the wind turbine system
Unlock the emergency stop button or release the brake button on the iSTA
Breeze charge controller.
The brake is released. The fast-blinking red LED on the iSTA Breeze charge
controller goes out. The wind turbine system supplies power.
.2 Restart after an emergency
Make sure the risk has been removed. Switch on the wind turbine system (
section 7.1)
Shutting down the :ind 7urbine 6ystem
.1 Emergency shut-down
RSWLRQDO3ress the emergency stop button between the wind turbine and the
RQJULGLQYHUWHU
The wind turbine is short-circuited via the (PHUJHQF 6WRSEXWWRQ . The wind
turbine is braked. Carefully tilt the wind turbine. Clean the wind turbine (
section 9.3)
1 of 2 Translation of the original instructions iSTA wind turbine system
2.0.201 I00
EarthSafe
Maintenance
.1 .2
Safety precautions during maintenance work
WARNING!
Risk of injury when carrying out maintenance work! Shut down the wind turbine
system prior to all maintenance work. Take steps to prevent the wind turbine
system from being switched on again
by unauthorised persons.
Shut down the wind turbine system ( section 8.2). Carefully tilt the tower.
Inspection and maintenance schedule
Interval
Part / component
Activity
Wind turbine
Check for abnormal noises
Daily
Rotor blades
Check that the blades turn freely
Tower
Yearly2 / at end of winter or after extreme weather events
Rotor blades Tower Wind turbine
Inspect for damage
Inspect for cracks / damage and
if necessary replace Treat with underbody protection
wax Are the rotor blades balanced? Check for vibration Check the guy wires Is
the tower still aligned
vertically? Inspect for damage
Check the bolts
Electrical wiring
Inspect the cables for damage
Table 11Inspection and maintenance schedule
WARNING!
Danger due to damaged parts! Shut down the wind turbine system immediately if
the rotor blades or the electrical wiring are damaged.
.3
Refer to the supplementary documents for information on maintaining supplier
components.
Maintenance and cleaning by the user
Coat the wind turbine and the rotor blades regularly with commercially
available underbody protection wax using a soft cloth.
A wax film protects the surfaces of the wind turbine and the rotor blades from
the weather and increases the efficiency of the blades.
2 Or every 6 months if situated close to sea
Translation of the original instructions iSTA wind turbine system 2.0.201 I00 1 of 2
EarthSafe
1 Troubleshooting and ‘iagnostics
1.1 Errors with LED
Error messages are displayed on the iSTA Breeze charge controller. Refer to
the separate instructions.
1.2 Errors without LED
Error
Possible cause
Possible actions
Wind turbine
Not enough wind
does not start up “Stop” switch pressed
Rotor blades incorrectly attached
Rotor blades not balanced
None
Release the “Stop” switch Attach the rotor blades
correctly Balance the rotor blades
Rotor turns too slowly
Bearing for wind alignment is stiff
Generator makes contact as it turns
Unfavourable location or tower too low
Rotor not balanced
Replace the bearing
Send the generator in to the manufacturer
Check and move to another location if necessary
Increase the height of the tower
Balance the rotor
Wind turbine
Tower not aligned vertically
vibrates on tower Tower bends in the wind
Tower foundation has too much clearance
Wind turbine or LQYHUWHU
Wind turbine
defective
system produces Cable cross-section does too little power not match installed cable
length
Align the tower vertically
Design a more robust tower
Reduce the clearance to a minimum
Contact the manufacturer or a specialist dealer
Match the cable crosssection correctly
Table 12Errors without an LED
Recommendation: Make a note of the relevant parameters at the site and have
them handy when you contact the manufacturer / specialist dealer.
1. What is the average / typical wind speed? 2. How high is the tower?
3. What are the characteristics of the countryside / built-up area in the
vicinity of the wind turbine?
4. What is the voltage between phases (measured by a qualified electrician
this voltage should be roughly identical in identical wind conditions)?
5. What is the battery voltage? How old is the battery or batteries? 6. Which
loads are connected to the battery? 7. Are solar panels also connected to the
charge controller? If so:
a. What is the no-load voltage3 [VDC]? b. What is the power [Wp]?
of 2 Translation of the original instructions iSTA wind turbine system 2.0.201 I00
EarthSafe
1 Removal from 6ervice and ‘isposal
1.1 1.2
Final decommissioning of the wind turbine system
WARNING!
Risk of injury due to unqualified dismantling, e.g.
· Persons without suitable training · Stored energy · Breakage during
dismantling
Important note on dismantling and disposal: The system must be dismantled in
the proper way by a suitably qualified person.
Shut down the wind turbine system ( section 8). Have the electrical systems
and equipment removed from service by a
qualified electrician. Make sure all rotors are braked. Carefully tilt the
tower. On the ground: Detach the rotor blades from the generator. Detach the
generator from the tower and disconnect the electrical wiring.
Disposal of the wind turbine system and components
Where necessary, dispose of the individual components in consultation with the
responsible local authorities.
Wind turbine system Wiring, electrical components Mechanical components
Table 13Disposal
Dispose of as electronic scrap Segregate prior to disposal
Translation of the original instructions iSTA wind turbine system 2.0.201 I00 1 of 2
EarthSafe
1 Index
A
Adapter stud…………………………………………. 8
P
Place of use …………………………………….1, 1
R
Rotor blade ………………………………… 8, ,
C
Cable cross-section …………………………. 1,
S
Strain relief ………………………………………….1
T
F
Foundation …………………………………………. 1
Tail vane……………………………………………..8 Transformer ……………………………………..
L
Load ……………………………………………….. , 1
W
Wind classes…………………………………………1
M
Main components………………………………. 7, 8
Translation of the original instructions iSTA wind turbine system 2.0.201 I00 2 of 2
EarthSafe
1 NotHV
2 of 2 Translation of the original instructions iSTA wind turbine system
2.0.201 I00
EarthSafe
3HUIRUPDQFH&KDUWV
Translation of the original instructions iSTA wind turbine system 2.0.201 I00
2 of 2
EarthSafe
&HUWLILFDWHV
2 of 2 Translation of the original instructions iSTA wind turbine system
2.0.201 I00
EarthSafe
SAVE
ENERGY
SAVE
PLANET
)DVW7UDGLQJ/7’ 8O6WDQFÕRQQD1R(W%$WRV%8/$5,$ www.istabreeze.com © ISTA Breeze
No part of this document may be copied or reproduced
7UDQVODWLRQ RI WKH RULJLQDO LQVWUXFWLRQV L67$ ZLQG WXUELQH VVWHP ..201 I00
References
- Altınel Enerji - IstaBreeze® Wind Turbines
- Istabreeze.store Versandhandel für Kleinwindkraftanlagen und Zubehör – istabreeze.store
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>