VERSA LINE JVA-S14 Commercial Finned Tube Radiation Installation Guide

June 11, 2024
VERSA-LINE

STS11-II-2

INSTALLATION INSTRUCTIONS

VERSA-LINE

COMMERCIAL FINNED TUBE RADIATION JVA-S11, 14

1. Determine quantities of enclosure and accessories required per wall or run. If installation is wall-to-wall, run backplate to within ½” of adjoining wall(s). If run ends with end cap, extend backplate beyond end of required enclosure 1-1/2″ for 3″ end and 6″ for 8-3/8″ end.

2. Mount backplate (full or partial) to wall at prescribed height (Refer to Submittal Drawing) making sure it is straight and level. If valve compartments are being used, make sure an equivalent amount of backplate is installed.

3A. Hot Water Systems: Water brackets are used to support the enclosure and a single tier of element. Water brackets do not provide pitch for the element. Install two (2) water brackets per enclosure length up to 6′-0″ of length. Three (3) water brackets per cover 6′-6″ up to 8′-0″of length. Valve compartments should have a minimum of one (1) water bracket (Accessories do not require brackets). Insert top of the bracket into `V’ bend of backplate (Full or Partial) and insert onto horizontal flange of the Partial backplate. Secure brackets to wall using fasteners (as specified) by others. Supply/Return Pipe hangers (if required) can be mounted to the wall adjacent to the water bracket (every other one).

3B. Steam Systems (Two Pipe): (Limited application for 11″ High Enclosure – Ensure room to pitch element at rate of 1/2″ per 20 feet.) Attach bracket-mounted hangers to steam bracket with 5/16-18 carriage bolt and nut supplied before the installation of the steam brackets to the wall. Install two (2) brackets per enclosure length up to 6′-0″ of length. Three (3) brackets per cover 6′-6″ up to 8′-0″of length. Valve compartments should have a minimum of one (1) bracket (Accessories do not require brackets). Insert top of the bracket into `V’ bend of backplate (Full or Partial) and insert onto horizontal flange of the Partial backplate. Secure brackets to wall using fasteners (as specified) by others. Valve compartments should have minimum of one (1) steam bracket (Accessories do not require brackets). Supply/Return Pipe hangers (if required) can be mounted to the wall adjacent to the steam bracket (every other one).

4. Lay out heating element as required. Place slide cradle onto the bottom of element at each bracket location. The element cradle has two legs that angle out slightly. Position the legs between the fins so there is tension against the legs. This holds the cradle in position. For Two Pipe Steam systems, adjust element pitch by raising the bracket mounted hanger and tightening nut to secure hanger into position. Second tier elements mounted on the bracket- mounted hangers can be adjusted up or down. Check submittal drawing for correct position of element fin. For copper tube elements, flush the loop or series with system water after soldering to neutralize the remaining flux material and prevent corrosive action and resulting pinhole leaks.

5. The enclosure can now be installed unless damper assembly is required (see damper installation sheet packed with damper blades). Start enclosure at left end of run, working clockwise. The enclosure back bend mounts directly into the `V’ bend of backplate. Firmly push next piece of cover into slip joint tabs of piece on left until run is completed. Secure bottom of enclosure into brackets. Tighten the posi-loc clamps to secure the enclosure.

6. Install overlapping accessories as indicated on room schedule. All accessories are overlapping. Valve Compartments are installed the same as enclosure. The top back bend is slipped between the wall and the backplate. The accessory bottom returns to the wall and is secured with fasteners by others.

MAINTENANCE

Before each heating season, remove accessories and enclosure panel to inspect finned tube elements for accumulation of dust or other debris that may accumulate and block airflow between fins. Remove dust and debris from coil fins with a vacuum cleaner or compressed air. Inspect for leaks or areas of corrosion. It should not be required, but if necessary, place a drop of lubricant (machine oil) onto each ball bearing (where applicable) located in the water brackets or bracket mounted hangers. Replace cover and accessories.

260 North Elm St., Westfield, MA 01085 Tel:413-564-5535 Fax: 413-564-5661 www.sterlingheat.com

MADE IN THE USA

GENERAL LAYOUT

CAT-52047E

Documents / Resources

| VERSA LINE JVA-S14 Commercial Finned Tube Radiation [pdf] Installation Guide
JVA-S14 Commercial Finned Tube Radiation, JVA-S14, Commercial Finned Tube Radiation, Finned Tube Radiation, Tube Radiation, Radiation
---|---

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

VERSA-LINE User Manuals

Related Manuals