nox-crete Tigerloc Attachment for Embed Concrete Building Installation Guide

June 5, 2024
nox-crete

nox-crete Tigerloc Attachment for Embed Concrete Building

nox-crete Tigerloc Attachment for Embed Concrete
Building

How To  Install

  1.  Install wall forms as per standard construction practicenox-crete Tigerloc Attachment for Embed Concrete Building 1
  2. Install TigerLoc to window or door openings as specified  Underside of TigerLoc should line up to the top of your architectural wythe pour. It is recommended to use galvanized brad nails or adhesive for fastening Tigerloc. Install TigerLoc with the channel facing upwards in order to allow the concrete to fill and lock it into place (Fig. 1). NOTE: In some applications, TigerLoc is specified thicker than the insulation layer. In this case, refer to the architectural details for placement height of TigerLoc.nox-crete Tigerloc Attachment for Embed Concrete Building 2
  3. Pour concrete for architectural wythe If TigerLoc is the same thickness as specifi ed insulation layer, the underside of TigerLoc can be used as a reference point for a consistent thickness of the architectural wythe. Around openings where TigerLoc has been installed. It is recommended to vibrate the formworknox-crete Tigerloc Attachment for Embed Concrete Building 3
  4. Install reinforcement to architectural wythe as specifi ed by project engineernox-crete Tigerloc Attachment for Embed Concrete Building 4
  5. Install insulation sheets and wythe connectors as per industry standard practices and/or the recommendation of the connector pin suppliernox-crete Tigerloc Attachment for Embed Concrete Building 5
  6. Complete the construction and pour sequence of your insulated concrete assembly as per industry standard practices Similar to the architectural wythe, it is recommended to vibrate the formwork near the locations where TigerLoc is installed to promote further consolidation with the keyway groove.nox-crete Tigerloc Attachment for Embed Concrete Building 6
  7. Strip formwork as per industry standard Any stubborn or galvanized brad nails can be easily pulled or snipped upon completion of the formwork removal.nox-crete Tigerloc Attachment for Embed Concrete Building 7
  8. After the erection of the insulated concrete panel Any TigerLoc that will remain exposed (overhead door, etc.) can be cleaned by lightly scraping away any concrete left on the surfacenox-crete Tigerloc Attachment for Embed Concrete Building 8
  9. For openings that will receive a man door or glazing frame Install frame to industry standard practicenox-crete Tigerloc Attachment for Embed Concrete Building 9

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

nox-crete User Manuals

Related Manuals