DOWELLESS C65 Batteries Parallel Instruction Manual
- June 15, 2024
- DOWELLESS
Table of Contents
DOWELLESS C65 Batteries Parallel Instruction Manual
1. Fasten the grounding wire to the terminal of the battery with M6 screw
2. Set up Communication between inverter and Battery.
- Please prefer to choose the communication cable ( between inverter and battery) provided by Inverter manufacture.
- Once you get it, connect PCS/hybrid inverter to Battery with t his cable.
3. Set up communication between Batteries in parallel.
- Buy network cable in the market or Do network cable. But what ever, please make sure that network cable adopts standard 8-core cable and ensure that the wire colors are pin to pin consistent at two ends.
For example if you want to do a network cable, follow instructions as below.
- Make network cables.
· Insert eight wires into RJ45 plug. Network cable adopts standard 8-core cable.
Ensure all wires stay well aligned. For Network Cable B that is used for parallel connection, ensure that the wire colors are pin-to-pin consistent at two en ds.
4、Plug network cable into PCS port of battery 1 and the other e nd into
inverter. Insert two crystal plug into Link-In port of battery 1 and Link-Out
port of battery n.
5、Connect Link-Out port of battery 1 and Link-In port of batter y 2 by network
cable.
The process goes on until the last battery is connected.
6. Plug all positive cables in positive junction box and negat ive cables in
negative junction box .
7. Connect DC Breakers with junction box and inverter .