DECKED VNMB07SPRT65 Drawer System Instruction Manual
- June 14, 2024
- DECKED
Table of Contents
RETENTION CABLE
Installation Instructions Van:
VNMB07SPRT65
VNMB07SPRT65 Drawer System
SPRINTER LWB 170” WHEELBASE
2007-CURRENT
RETENTION CABLE INSTALLATION
This view is to orient yourself to the vehicle, the DECKED System installed using the installation procedures that came with your system, and how the van cables should appear when the cable installation process is complete.
Cable Installation – Step#1 –
- Center cable standoff to center vert and align top edge of standoff to bottom of drawer wheel channel.
- Run two #8 self-tapping screws, diagonally oriented as shown in image below, thru cable stand off and into center vert; BAG VAN CABLE KIT.
Cable Installation – Step#2 –
- Starting on the driver side of the vehicle, loop LH cable eye thru cargo tie down ring (shown in blue in assembled view) on the cab side of the J-hook; BAG VAN CABLE KIT.
- Assemble LH and RH cable ends in the order depicted in the exploded view image, i.e. bolt thru washer, then thru RH cable eye and then LH cable eye, then thru 1 1/2” steel spacer and the thru 3/4” nylon spacer, thru hole in C-channel end plate and into nut; BAG VAN CABLE KIT.
Enlargement of LH cable assembly attachment to cargo tie down loop.
Cable Installation – Step# 3 –
- On the passenger side of the vehicle, loop RH cable eye thru cargo tie down ring (shown in blue in assembled view) on the cabs ide of the J-hook; BAG VAN CABLE KIT.
- Assemble LH and RH cable ends in the order depicted in the exploded view image, i.e. bolt thru washer, then thru LH cable eye and then RH cable eye, then thru 1 1/2” steel spacer, thru nylon spacer, thru hole in C-channel end plate and into nut; BAG VAN CABLE KIT.
Enlargement of RH cable assembly attachment to cargo tie down loop.