EMERSON COPELAND H-Series Condensing Unit User Manual
- June 4, 2024
- Emerson
Table of Contents
H-Series Condensing Unit
User Manual
Introduction
Thank you for purchasing the EmersonTM H-Series Condensing Unit. We hope that
this product meets your intended refrigeration requirement. Please read
through this operation manual to familiarize yourself with the installation,
commissioning, and operation of this product. Please do read the following
information in this page before proceeding with the rest of the manual.
The EmersonTM H-Series scroll refrigeration condensing units should only be
installed by suitably qualified and experienced refrigeration technicians. No
responsibility can be accepted for damage caused by inexperienced or
inadequately trained site technicians or improper system design. All
instructions and procedures described in this manual are based on good
refrigeration trade practices as applicable to this particular product. The
installation contractor may prefer to use variations to these recommendations.
However, the methods described in this manual represent the minimum
requirements to avoid any subsequent warranty claims for this equipment and
its components. These instructions do not cover the fundamentals of good
electrical or refrigeration practice and are therefore intended for use only
by qualified and/or experienced personnel or technicians.
For any additional query, please consult your local sales office, quoting unit
model and serial number as shown on the nameplate. In case of ambiguity, the
wiring diagram supplied with each unit takes precedence over the diagram in
this manual.
Emerson H-Series Condensing Units are fitted with high efficient Copeland
Scroll Compressor and the Dual Temperature Condensing Units are fitted with
high efficient ZFI Copeland Scroll compressors with vapor injection
technology.
This document is designed to help the contractor and customer for the
installation, commissioning & operation of Emerson’s H-Series Condensing Unit.
Safety Information
-
Installation and commissioning work on CDU shall be carried out only by qualified, refrigeration personnel who have been trained and instructed.
-
H-Series condensing unit is manufactured according to the latest safety standards. Emphasis has been placed on the user’s safety. For relevant standards please refer to the manufacturer’s declaration, available on request. You are strongly advised to follow these safety instructions.
-
Icon explanation
-
Safety Statements
a. Only qualified and authorized refrigeration personnel are permitted to install, commission and maintain this equipment.
b. Electrical connections must be made by qualified electrical personnel.
c. All valid standards for connecting electrical and refrigeration equipment must be observed.
d. The national legislation and regulations regarding personnel protection must be observed.
Use personal safety equipment. Safety goggles, gloves, protective clothing, safety boots and hard hats should be worn where necessary. -
General Instructions
Warning
System breakdown! Personal injuries! Never install a system in the field and leave it unattended when it has no charge, a holding charge, or with the service valves closed without electrically locking out the system.
System breakdown! Personal injuries! Only approved refrigerants and refrigeration oils must be used.
Warning
High shell temperature! Burning! Do not touch the compressor until it has cooled down. Ensure that other materials in the area of the compressor do not get in touch with it. Lock and mark accessible sections.
Caution
Overheating! Bearing damage! Do not operate compressors without refrigerant charge or without being connected to the system.
Caution
Compressors contain oil & refrigerant under pressure. Release pressure from both high & low side of compressor before servicing.
Caution
Tube brazing & compressor operation can produce hot surfaces. To avoid burns, allow surfaces to cool. -
Safety Refrigerants/Lubricant
a. Please use correct refrigerant as designed to work in safe operating envelope.
b. Compressor is supplied with an initial oil charge. The standard oil charge for use with HFC refrigerant is polyol ester (POE) lubricant Emkarate RL 32 3MAF.
Nomenclature
Models
Mechanical data
Condensing Unit| Compressor model| Receiver
Capacity (I)| Air Flow (m³/s)| Dimensions
Depth/Width/Height
(mm)| Suction
Size| Liquid
Size| Net Weight
---|---|---|---|---|---|---|---
HMXA-015-TFM-511| ZS11KAE-TFD-600| 4.6| 2922| 1029 x 424 x 840|
3/4″| 1/2″| 81
HLXA-015-TFM-511| ZF06KAE-TFD-618| 4.6| 2922| 1029 x 424 x 840|
3/4″| 1/2″| 81
HMXA-020-TFM-511| ZB15KQE-TFD-558| 4.6| 2922| 1029 x 424 x 840|
3/4″| 1/2″| 85
HLXA-020-TFM-511| ZF09KAE-TFD-618| 4.6| 2922| 1029 x 424 x 840|
3/4″| 1/2″| 82
HDXA-030-TFM-513| ZFI09KQE-TFD-550| 4.6| 2922| 1029 x 424 x 840|
3/4″| 1/2″| 85
HDXA-040-TFM-513| ZFI13KQE-TFD-550| 4.6| 2922| 1029 x 424 x 840|
3/4″| 1/2″| 91
HDXA-050-TFM-513| ZFI17KQE-TFD-550| 6.7| 5910| 1029 x 424 x1242|
7/8″| 1/2″| 106
HDXA-065-TFM-513| ZFI21KQE-TFD-550| 6.7| 5910| 1029 x 424 x1242|
7/8″| 1/2″| 120
HDXA-075-TFM-513| ZFI23KQE-TFD-550| 6.7| 5910| 1029 x 424 x1242|
7/8″| 1/2″| 125
Electrical data
densing Unit| Compressor model| Unit MOC| Compressor|
Total Fan
---|---|---|---|---
LRA| MOC| RLA
HMXA-015-TFM-511| ZS11KAE-TFD-600| 4.2| 27| 3.3| 4.3| 0.9
HLXA-015-TFM-511| ZF06KAE-TFD-618| 5.1| 28| 4.2| 3.8| 0.9
HMXA-020-TFM-511| ZB15KQE-TFD-558| 5.8| 26| 4.9| 5| 0.9
HLXA-020-TFM-511| ZF09KAE-TFD-618| 6.2| 41.6| 5.3| 4.9| 0.9
HDXA-030-TFM-513| ZFI09KQE-TFD-550| 6.2| 23.5| 5.3| 4.9| 0.9
HDXA-040-TFM-513| ZFI13KQE-TFD-550| 7.5| 40| 6.6| 6.4| 0.9
HDXA-050-TFM-513| ZFI17KQE-TFD-550| 9.8| 50| 8.1| 6.9| 1.7
HDXA-065-TFM-513| ZFI21KQE-TFD-550| 12.6| 64| 10.9| 8.9| 1.7
HDXA-075-TFM-513| ZFI23KQE-TFD-550| 14.1| 74| 12.4| 10.6| 1.7
Features and Benefits
Features | Benefits |
---|---|
Efficiency | High efficiency Copeland™ ZFI Vapor injection compressors for Dual |
temperature application.
Vapor injection technology improves system capacity by up to 30% and
efficiency by up to 20%.
New valving technology adjusts the scroll compression ratio based on operating
condition, significantly
improving performance.
Specially designed condenser.
Reliability| Compressor is provided with Emerson EVI CoreSense™ kits to
control superheat of vapor injection and to maintain safe discharge
temperature in dual temperature application.
Fully featured options such as filter drier, sight glass, oil separator and
suction accumulator available as
standard scope of supply in dual temperature models.
Compressors are supplied with internal thermal protectors that safeguards
against motor overheating
and high current.
Envelope| Unique operating envelope (-40°C to 7°C evaporating temperatures)
and up to 49°C ambient, providing
a broad range of selection (dual temp application).
Smooth Operation| Scroll compressor has an inbuilt check valve that isolates
high pressure gas, allowing the compressor to
start unloaded with low inrush currents.
Less vibration.
Inventory| Same units for both medium and low-temperature requirements for
majority of the capacities resulting
in rationalization of unit inventory.
Maintenance| Optimal layout of components for easy serviceability.
Pre-wired electric junction box, liquid receiver, HP safety cartridge switch
and adjustable LP control
switch.
Multi-evaporator| One condensing unit could be connected to two evaporators.
The lowest load operation should be
more than 35 of the total load.
Condenser
Internally grooved copper tubes with hydrophilic coated aluminum fins.
Fan Motors
Thermally protected, single-phase fans. Option to have fan speed controller.
Physical Layout of the Dual Temperature Unit
Dimensional drawings
Scope of supply
511 (HL & HM Units) Filter drier, Moisture Indicator, Liquid receiver,
Suction & Liquid Line Service Valves, HP Cutout, Adjustable LP Cutout.
513 (HD Units) Filter drier, Moisture Indicator, Liquid receiver, Suction
& Liquid Line Service Valves, HP Cutout, Adjustable LP Cutout, Oil separator,
Suction accumulator, CoreSense / Injection Management Module, Sub cooler,
Vapour injection Expansion valve.
Electrical connections
EVI CoreSenseTM control kits and LED Indications
EVI CoreSense control kits
The EVI CoreSense control kit of Dual Temperature H-Series unit is intended to
control vapor injection, maintain a safe discharge temperature, and provide
intelligent diagnosis and protection. The kit includes a printed circuit board
(PCB), an electronic expansion valve (EXV), and three sensors, as well as
containing a transformer and an EXV filter. In vapor injection application,
the valve is driven by sensors mounted near the heat exchanger and attempts to
maintain the vapor outlet sensor 5K higher than the vapor inlet. The system
will switch to discharge line temperature control if vapor injection is
insufficient to maintain a safe discharge temperature. If the discharge
temperature becomes dangerously high, the system will stop the compressor,
turn on an LED alarm, and trigger a voltage free alarm relay contact. The
compressor can auto-reset, but not lockout.
Printed circuit board
Wear a ground strap when working with the PCB to avoid the risk of damage from
static discharges. General PCB layout, input and output ports are shown in the
image below, the ports to EXV, DLT, as well as the vapor in and vapor out
sensors are done with Poka-yoke connector design. Connect sensors, EXV, and
system wiring as shown in wiring diagram. The PCB is supplied power through a
transformer with a power input of 50/60 Hz, 220VAC, and an output of 12VAC to
the PCB board.
DIP Switch Setting
SW1| | |
---|---|---|---
Bit 1| Bit 2| DLT Control Point| Default
OFF| OFF| 95 deg C|
OFF| ON| 100 deg C|
ON| OFF| 105 deg C|
ON| ON| 110 deg C|
COM PRESSOR SHUTD OWN SAT 125 DEG CDLT
SW3| |
---|---|---
Bit 1| Compressor Time Delay| Default
ON| 2 minutes|
OFF| 0|
Bit 2| Injection Mode|
ON| Vapour Injection|
OFF| Liquid Injection|
SW2| |
---|---|---
Bit 1| Reset Mode| Default
ON| Lockout After 5 trips in 1 hr|
OFF| Auto Reset|
Bit2 ON| Vapour Injection Superheat 10 deg K
OFF| 5 deg K|
LED Indications
LED1 (yellow-green)
LED1 will light up during initialization after power on, after that, blinking
lights will indicate the sensor status.
LED Number | Color | LED Flash Code | Compressor / Sensor Status |
---|---|---|---|
LED1 | Yellow -Green | 1 | Compressor waiting to start |
2 | DLT overheat protection | ||
3 | DLT sensor failure | ||
4 | Vapor-in sensor failure | ||
5 | Vapor-out sensor failure | ||
LED Number | Color | LED Flash Code | EXV Status |
LED2 | Yellow -Green | 1 | EXV Opening |
Constant ON | EXV Fully Open | ||
LED Number | Color | LED Flash Code | EXV Status |
LED3 | Yellow -Green | 1 | EXV Closing |
Constant ON | EXV Fully Closed | ||
LED Number | Color | LED FlashCode | Compressor / Sensor Status |
LED4 | Red | Constant On | DLT overheat protection |
DLT sensor failure
Vapor-in sensor failure
Vapor-out sensor failure
Installation, system processing and commissioning
Utmost care must be taken while handling the H-Series condensing unit. Please go through the contents below to ensure proper handling.
a. Inspection
Inspect the condensing unit and any accessories shipped with them for damages
or shortages before and during unloading. All items on bill of lading should
be accounted for prior to signing the shipping receipt. Note any shortages or
damage on delivery receipt (specify the extent and type of damage found). Unit
should be inspected carefully for concealed damage. Notify Emerson
sales/application personnel of the damage immediately. Request an immediate
joint inspection and do not repair the unit until inspected by Emerson’s
representative.
The system is shipped with a holding charge of dry nitrogen. Check to see that
pressure is still in the unit upon receipt. Report lack of pressure
immediately to the Emerson’s application/sales representative.
b. Location and Fixing
The unit should always be installed in a location that ensures clean air flow.
It is recommended that a clearance of 300 mm from the wall (or the next unit)
be maintained from the unit’s left and rear panels whereas a clearance of 500
mm must be maintained from the unit’s right, top and front panels (seen facing
the front of the unit). Both service access and airflow have been considered
in making these recommendations. Where multiple units are to be installed in
the same location, the contractor needs to consider each individual case
carefully. There can be many variations of unit quantities and available space
and it is not the intention of this manual to go over these. Ideally, the unit
should be mounted on a solid concrete slab with anti-vibration pads between
unit feet and concrete. However, the H-Series condensing unit has also been
designed for wall mounting on suitable brackets. Wall mounting brackets are
not included. Another factor to consider in finding a good installation site
is the direction of the prevailing wind. For example if the air leaving the
condenser faces the prevailing wind, the air flow through the condenser can be
impeded, causing high condensing temperatures ultimately resulting in reducing
unit life. A baffle is a remedy for this situation.
c. Refrigeration Piping Installation
All interconnecting pipes should be of refrigeration grade, clean, dehydrated
and must remain capped at both ends until installation. Even during
installation, if the system is left for any reasonable period (say two hours),
pipes should be re- capped to prevent moisture and contaminants from entering
the system.
Do not assume that the service connection sizes on the unit (at the service
valves) are the correct size to run your interconnecting refrigeration pipes.
The service valve sizes have been selected for convenience of installation and
in some cases (larger units) these may be considered too small. However, for
the very short pipe run within our units, these service connection sizes are
adequate.
The pipe should be sized to ensure optimum performance and proper oil return.
The sizing must also consider the full capacity range through which this
particular unit will need to operate.
Pipe runs should be kept as short as possible, using the minimum number of
directional changes. Use large radius bends and avoid trapping of oil and
refrigerant. This is particularly important for the suction line. The suction
line should ideally slope gently towards the unit. Recommendation slope is
1/200~1/250. P traps, double risers and reduced pipe diameters may be required
for suction lines where long vertical risers cannot be avoided. All pipes
should be adequately supported to prevent sagging which can create oil traps.
The recommended pipe clamp support distance is shown in the table.
Tube Dia | Max distance between 2 clamp support |
---|---|
1/2 inch | 1.2 M |
5/8 inch | 1.5 M |
7/8 inch | 1.8M |
1 1/8 inch | 2.1M |
1-5/8 | 2.3 |
d. Refrigerant line insulation
-
Insulate suction lines from the evaporators to the condensing unit with
minimum 1″ thickness closed-cell type insulation on low temperature circuits. -
Liquid lines of Dual temperature systems to be insulated with minimum of ¾” insulation.
-
Long liquid lines run in areas exposed to high temperatures should be fully insulated with minimum 1/2″ insulation.
-
Suction and liquid lines should never be taped or soldered together.
e. Electrical
- All electrical work must be done in accordance with the National Electrical Code and existing local codes.
- Power supply must be the same as specified on the unit’s name plate.
- Voltage fluctuations in excess of 10 percent must be corrected.
- Before starting the unit, ensure that all protective devices are in place and that all wiring is secure.
f. Brazing Recommendation
Maintain a flow of oxygen-free nitrogen through the system at a very low
pressure during brazing. Nitrogen displaces the air and prevents the formation
of copper oxides in the system. If copper oxidization is allowed to form, the
copper oxide material can later be swept through the system and block screens
such as those protecting capillary tubes, thermal expansion valves, and
accumulator oil return holes. This minimizes any entry of contaminants and
moisture.
- Remove the liquid line connection cap.
- Then remove the suction connection cap.
- Open both valves midway.
- Care should be taken to avoid the holding charge from releasing too quickly.
- Be sure tube fitting inner diameter and tube outer diameter are clean prior to assembly.
- Since both tubes are extended from the condensing unit housing, we recommend insulating the housing by using a wet cloth on the copper tubing.
- Recommended brazing materials: a copper / phosphorous or copper / phosphorous / silver alloy rod should be used for joining copper to copper whereas to join dissimilar or ferric metals, use a silver alloy rod, either flux coated or with a separate.
- Use a double tip torch.
g. Start-up & Operation
Initial pressure test (by vacuum and nitrogen) – Step-by-step:
- Use a 4-port gauge manifold with 3/8″ hose and connections to the vacuum pump. The vacuum gauge does not have to be connected for this part of the process.
- Connect the gauges to service ports provided on receiver valve and suction tube. In order to remove any non-condensable that may have entered the system during installation, follow these steps:
- Start the vacuum pump. The evaporator fan should be running and the compressor crankcase heater is energized at this point. This will involve powering up the unit so it is important to disconnect the live feed wire to the compressor contactor (so the compressor cannot run and the crankcase heater can be energized).
- Open both valves on the manifold and then open the main vacuum valve on the pump. Run the system until the vacuum level of -0.85 bar (as read on manifold gauge) is achieved.
- Shut off the main vacuum pump valve. Check for vacuum rise using the manifold compound gauge. A rise would indicate a large leak.
- If vacuum holds for 10 minutes, break vacuum with Nitrogen. Check the nameplate of the unit/compressor for allowable leak test pressure. Ensure that pressure regulators are installed on the Nitrogen cylinders. Check for leaks and repair leakage.
Leak Check
The success of all the subsequent commissioning depends on a leak free system,
free of contaminants, free of oxides, free of non-condensable’ s, that has
been evacuated to a low vacuum and charged with the prescribed refrigerant.
Leak test is particularly important for field-connected systems. Typically,
field systems lose as much as 20%30% of their refrigeration charge annually.
This is not only an unnecessary expense but also damages the environment.
Compressor oil can be lost at the same time as refrigerant and eventually lead
to compressor failure. (Time spent on leak test will eventually reduce the
time spent on the evacuation process).
Ensure that all service valves are open during the leak test process. It is
important to recheck all joints within the unit as well as the external
joints.
- The unit is shipped with a holding charge of dry nitrogen and should be leak free.
- Ensure that the test pressure do not exceed the system design pressures.
- Do not expose system pressure control LP to test pressures above the design pressure. This can damage the pressure controls.
- Using an approved, calibrated electronic gas leak detector, leak test the entire system paying attention to all joints (you might have to charge small quantity of refrigerant before charging the Nitrogen to enable this procedure).
- Periodically check functionality of the electronic leak detector during this process.
- To further check system integrity, spray a soapy water solution over joins then visually inspect for bubbles.
- Leave the system under pressure for a designated period (24 Hours).
- Check and record the ambient temperatures and the system pressure with calibrated approved instruments. This process is to be carried out every 8-12 hours during the pressure testing process.
- If the test pressures cannot be maintained, repeat the leak testing process employing the isolation of sections of the system to determine the source of leaks. Repair the leak and repeat the leak testing process until system can be signed off as leak free and approved by authorized personnel.
- Record findings and confirm pressure testing process completion.
Evacuation
- After the system is leak checked, connect approved dual stage vacuum pump sized to application with preferably fresh oil to evacuate the system.
- Ensure all inline system shut-off valves and solenoid valves are fully open.
- Evacuate the system to 300 microns.
- A triple evacuation is recommended in case of using analog gauges as we might not know the exact vacuum level being achieved
Charging and commissioning
Reminder:
- The scroll compressor design requires system charging with liquid refrigerant into the liquid line.
- Do not vapor charge the H-Series Scroll unit. After ensuring all valves are opened and system is evacuated properly, only then start the refrigerant charging process. Also ensure that LP cutout is not by-passed during the charging process.
Step-by-step:
- Ensure that there is no power supply to the H-Series unit. The Liquid Line solenoid needs to be kept open for the charging process and this may require a temporary power feed to it.
- Connect the refrigerant cylinder to main service hose and purge line at the manifold end.
- Ensure correct orientation of the refrigerant cylinder. Follow cylinder labeling/instructions so that liquid refrigerant can be charged into the system. This will be charged through the high-pressure side of the manifold and H-Series unit liquid service valve. Ensure that at least 70-80% of the required refrigerant charging is done by this method.
- The compressor can then be started, and the unit continued to be charged (with the controlled liquid refrigerant through the suction service valve). The quantity of charge should always be measured. See note.
- The system needs to be operated down to its design evaporating temperature before you can be sure the charge is correct. It is at this point that the normal refrigeration operational checks can be carried out – such as checking the liquid line sight glass for bubbles and the operating pressures.
Refrigerant charging is regarded full/complete when the operating temperature of the system has been stable for some time and the liquid line sight glass is clear.
h. Maintenance
Condenser Fins
Condenser fins become dirty over time as ambient air is induced to the
condenser. Dirty coil surfaces result in high condensing temperatures and poor
unit performance. Regular cleaning is recommended with frequency depending on
the installation and the surrounding environment. As a general guide, it is
advisable to do this at least once every two months. Fins should be cleaned
with liquid detergent diluted with clean water. Before washing, a light brush
downward (in the direction of the fins) should be done to remove heavy
deposits.
Electrical Connections
Check tightness of electrical connections occasionally.
Routine Leak Test
All joints should be checked for leaks during site visits. All joints should
be leak tested once a year. Condenser Fan(s) and Motor(s), an annual
inspection of these items is recommended. Fastenings may loosen, bearings may
wear, and fans may require cleaning of solid deposits which can cause
imbalance.
TURN OFF OR DISCONNECT THE ELECTRICAL POWER SOURCE BEFORE CLEANING THE CONDENSER COIL OR DOING MAINTENANCE.
System Start-Up and Operational Check Sheet
Client Details
Facility/Customer Name :|
---|---
Address :|
Contact Details :|
Installer :|
Installation Date :|
Condensing Unit Info
CDU Model :|
---|---
Serial Number :|
CDU Location :|
Indoor Unit Make/Model :|
System Details
Room/Case ID :|
---|---
Pipe Length (approx.) :|
OAT @ Start-Up/Check :|
PSI Leak Test :| PSIG
Duration :| Hours
System is Leak Tight :| Y / N
Triple Evacuation :| Y / N
Micron Gauge Reading :| microns
Total Evacuation :| PSIG @ # of Hrs
Refrigerant :|
Total Charge :| Kg.
Sight Glass Clear :| Y / N
Evap Fans Running :| Y / N
Liquid Line Insulation :| Y / N
Sound and Vibration|
System Operation
COMP Voltage : | V |
---|---|
COMP Current : | A |
Suction Pressure : | PSIG/Bar |
Liquid Line Pressure : | PSIG/Bar |
COMP Suction Temp : | °C |
COMP Disch Temp : | °C |
Liquid Line Temp : | °C |
Compressor SH : | K |
Subcooling : | K |
Adjustable LP Setpoint : | PSIG |
Design/Operating Temp: | °C |
Actual Room/Case Temp : | °C |
Condenser Fins : |
Comments
Prepared by: _
Date: ___
Disclaimer
Technical data given was correct at the time of printing. Products,
specifications and data in this literature are subject to change without prior
notice. Updates will be done periodically. Should you need clarification of a
specific data, value or information, kindly contact Emerson representative.
Contact list
United Arab Emirates
Jebel Ali Free Zone P.O. Box 26382, Dubai United Arab Emirates Toll Free: 8000
441 3428 Tel: +971 4 8118100 Fax: +971 4 8865465
Saudi Arabia
P.O. Box 34332 – 3620 2nd Industrial City, 67 St. Dammam, Saudi Arabia Toll
Free: 8008 443 426 Tel: +966 3 8147560 Fax: +966 3 8147570
South Africa
11 Quark Crescent Linbro Business Park Sandton 2065, South Africa Toll Free:
0800 980 3711 Tel: +27 11 451 3700 Fax: +27 11 451 3800
Egypt
P.O.Box 11799 11 Mustafa Refaat Street Sheraton, Heliopolis Cairo, Egypt Tel:
+20 2 226 5854
EmersonMEA
EmersonMiddleEastAfrica
EmersonClimateMEA.com
2201/MEA/R/3/CDU/104/50 User Manual
CONSIDER IT SOLVED™
Documents / Resources
|
EMERSON COPELAND H-Series Condensing
Unit
[pdf] User Manual
H-Series Condensing Unit, H-Series, Condensing Unit, COPELAND H-Series
Condensing Unit
---|---
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>