JESCO MEMDOS SMART LB / LD Stepper Motor Driven Diaphragm Dosing Pump User Manual
- June 9, 2024
- JESCO
Table of Contents
MEMDOS SMART LB / LD Stepper Motor Driven Diaphragm Dosing Pump
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB /
LD
The MEMDOS SMART LB / LD is a stepper motor-driven diaphragm
dosing pump designed for dosing liquids and conveying gases. It
comes with a control system that provides password protection to
ensure secure operation. The pump has maintenance intervals that
need to be followed to ensure optimal performance. Troubleshooting
instructions are also provided in case of any faults. Spare parts,
including diaphragm spare parts kits and dosing head spare parts
kits, are available for replacement.
Technical Data
The pump has a delivery capacity of up to 30 liters per hour and
operates within certain conditions and limits. Electrical
specifications include a voltage range of 100-240VAC, 50/60Hz, and
power consumption of up to 20W. Other data related to the pump is
also provided in the manual.
Dimensions
The MEMDOS SMART LB / LD comes in two sizes, 2, 5, 10 and 15,
20, 30, each with specific dimensions that are listed in the
manual.
Installation
The dosing pump needs to be installed according to the set-up
information provided in the manual. Installation examples are also
given to help with the process.
Electrical Installation
The pump’s electrical installation is explained in detail,
including principles and descriptions of connection sockets.
Usage Instructions
-
Read the operating manual thoroughly before installing and
operating the pump. -
Ensure that you follow the set-up information provided during
installation. -
Maintain the pump at regular intervals as specified in the
manual. -
In case of any faults, refer to the troubleshooting section and
follow the instructions provided. -
Use only recommended spare parts for replacement.
Please note that the user is responsible for any mistakes made
during installation and operation. Password protection is provided
to ensure secure operation of the pump.
Stepper motor-driven diaphragm dosing pump
MEMDOS SMART LB / LD
Operating instructions
Read the operating manual! The user is responsible for installation and operation related mistakes!
Original operating instructions © Lutz-Jesco GmbH 2016
BA-10110-02-V01
Dosing Liquids Conveying Gases
Control Systems
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
Table of Contents
1 Notes for the Reader …………………………………………………. 4 1.1 General non-
discrimination………………………………………………4 1.2 Explanation of the signal words
…………………………………………4 1.3 Explanation of the warning signs ……………………………………….4 1.4
Identification of warnings…………………………………………………4 1.5 Instruction for action
identification …………………………………….4
2 Safety ……………………………………………………………………… 5 2.1 General
warnings……………………………………………………………5 2.2 Hazards due to non-compliance with the
safety instructions …..6 2.3 Working in a safety-conscious manner
……………………………….6 2.4 Personal protective equipment ………………………………………….6 2.5
Personnel qualification…………………………………………………….6
3 Intended use …………………………………………………………….8 3.1 Notes on product warranty
……………………………………………….8 3.2 Intended purpose……………………………………………………………8 3.3 Device
revision ………………………………………………………………8 3.4 Principles
……………………………………………………………………..8 3.5 Prohibited dosing
media…………………………………………………..8 3.6 Foreseeable misuse ………………………………………………………..8
4 Product description …………………………………………………10 4.1
Properties……………………………………………………………………10 4.2 Scope of delivery
………………………………………………………….10 4.3 Structure of the dosing pump ………………………………………….10
4.4 Function description ……………………………………………………..11 4.5 Rating plate
…………………………………………………………………11 4.6 Conveying characteristics ………………………………………………12
10 Control……………………………………………………………………27 10.1 Operating elements of the control
LB………………………………27 10.2 Operating elements of the control LD………………………………27 10.3
Password protection ……………………………………………………28
11 Operation………………………………………………………………..30 11.1 Commissioning the dosing
pump……………………………………30 11.2 MEMDOS SMART LD: Operating modes …………………………..31 11.3
External On / Off via Release input ………………………………….33 11.4 Decommissioning the
dosing pump………………………………..33 11.5 Shutting down in an emergency
…………………………………….33 11.6 Storage …………………………………………………………………….33 11.7
Transportation…………………………………………………………….33 11.8 Disposal of old equipment
…………………………………………….33
12 Maintenance ………………………………………………………….. 34 12.1 Maintenance
intervals………………………………………………….34 12.2 Tighten up dosing head
bolts…………………………………………34 12.3 Change the diaphragm…………………………………………………35 12.4
Clean suction and discharge valves ………………………………..35
13 Troubleshooting ………………………………………………………36 13.1 Type of fault
……………………………………………………………….36
14 Spare parts……………………………………………………………..39 14.1 Diaphragm spare parts kits
…………………………………………..39 14.2 Dosing head spare parts kits including valves
…………………..39
15 Delivery characteristic curves…………………………………..40
5 Technical data…………………………………………………………13 5.1 Delivery capacity
data……………………………………………………13 5.2 Operating conditions and limits
……………………………………….13 5.3 Electrical specifications …………………………………………………14 5.4
Other data …………………………………………………………………..14
6 Dimensions ……………………………………………………………. 15 6.1 MEMDOS SMART LB / LD 2, 5, 10
…………………………………….15 6.2 MEMDOS SMART LB / LD 15, 20, 30 …………………………………16
16 EC Declaration of Conformity…………………………………….41 17 Declaration of no objection……………………………………….42 18 Warranty claim………………………………………………………..43 19 Index………………………………………………………………………44
7 Installing the Dosing Pump……………………………………….17 7.1 Set up information ………………………………………………………..17 7.2 Installation examples …………………………………………………….17
8 Hydraulic installations……………………………………………..18 8.1 Design of the system……………………………………………………..18 8.2 System piping………………………………………………………………19 8.3 Aligning the dosing head ………………………………………………..19 8.4 Hydraulic connections……………………………………………………19 8.5 Connecting a leakage drain …………………………………………….21 8.6 Connecting the dosing head venting facility ……………………….21 8.7 Hydraulic accessories ……………………………………………………21
9 Electrical installation……………………………………………….24 9.1 Principles ……………………………………………………………………24 9.2 Description of connection sockets ……………………………………25
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Table of Contents 3
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
1 Notes for the Reader
These Operating instructions contain information and behaviour rules for safe
and designated operation of the dosing pump MEMDOS SMART LB / LD.
Observe the following principles:
n Read the entire operating manual prior to starting-up the device. n Ensure
that everyone who works with or on the dosing pump has read
the operating instructions and follows them. n Keep the operating instructions
for the entire service life of the dosing
pump. n Pass on the operating instructions to any subsequent owner of the
dosing pump.
1.1 General non-discrimination
In this operating manual, only the male gender is used where grammar allows
gender allocation. The purpose of this is to make the text easy to read. Men
and women are always referred to equally. We would like to ask female readers
for understanding of this text simplification.
1.2 Explanation of the signal words
Different signal words in combination with warning signs are used in this
operating manual. Signal words illustrate the gravity of possible injuries if
the risk is ignored:
Signal word
Meaning
DANGER
Refers to imminent danger. Ignoring this sign may lead to death or the most serious injuries.
WARNING
Refers to a potentially hazardous situation. Failure to follow this instruction may lead to death or severe injuries.
CAUTION
Refers to a potentially hazardous situation. Failure to follow this instruction may lead to minor injury or damage to property.
NOTE
Refers to a danger which, if ignored, may lead to risk to the machine and its function.
Table 1: Explanation of the signal words
1.3 Explanation of the warning signs
Warning signs represent the type and source of a danger:
Warning sign
Type of danger
Danger point
Danger from electrical voltage
Danger from corrosive substances
Danger from potentially-explosive substances
Danger from automatic startup
Danger of damage to machine or functional influences
Table 2: Explanation of the warning signs
1.4 Identification of warnings
Warnings are intended to help you recognise risks and avoid negative
consequences.
This is how warnings are identified:
Warning sign
SIGNAL WORD
Description of danger.
Consequences if ignored. ð The arrow signals a safety precaution to be taken
to eliminate
the danger.
1.5 Instruction for action identification
This is how pre-conditions for action are identified:
ü Pre-condition for action which must be met before taking action.
@A resource such as a tool or auxiliary materials required to perform the
operating instructions.
This is how instructions for action are identified:
è Separate step with no follow-up action. 1. First step in a series of steps.
2. Second step in a series of steps.
4Result of the above action.
ü Action completed, aim achieved.
4 Notes for the Reader
Instruction for action identification
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
2 Safety
2.1 General warnings
The following warnings are intended to help you to eliminate the dangers that
can arise while handling the dosing pump. Risk prevention measures always
apply regardless of any specific action. Safety instructions warning against
risks arising from specific activities or situations can be found in the
respective sub-chapters.
DANGER
Mortal danger from electric shock! Wrongly connected or located cables or
damaged ones can injure you. ð Connect the device only to a SCHUKO socket
outlet protected by a
ground fault circuit interrupter (GFCI). ð Replace damaged cables without
delay. ð Do not use extension cables. ð Do not bury cables. ð Secure cables to
avoid being damaged by other equipment.
DANGER
Danger to life through explosions! The use of dosing pumps without ATEX
certification in a potentially explosive atmospheres can result in
potentially-fatal explosions. ð Never use the dosing pump in potentially
explosive areas.
WARNING
Danger from unsuitable materials The materials of the dosing pump and
hydraulic parts of the system must be suitable for the dosing medium that is
used. Should this not be the case, the dosing media may leak. ð Make sure that
the materials you are using are suitable for the
dosing medium. ð Make sure that the lubricants, adhesives, sealants, etc. that
you
use are suitable for the dosing medium.
WARNING
Caustic burns or other burns through dosing media! While working on the dosing
head, valves and connections, you may come into contact with dosing media. ð
Use sufficient personal protective equipment. ð Rinse the dosing pump with a
liquid (e.g. water) which does not
pose any risk. Ensure that the liquid is compatible with the dosing medium. ð
Release pressure in hydraulic parts. ð Never look into open ends of plugged
pipelines and valves.
WARNING
Danger of automatic start up! After connecting the mains supply, residual
dosing media in the dosing head can spray out. ð Before connecting the mains
supply, connect the dosing lines. ð Check that all the screw connections have
been tightened
correctly and are leak-proof.
CAUTION
Danger when changing the dosing medium. Changing the dosing media can provoke
unexpected reactions, damage to property and injury. ð Clean the dosing pump
and the system parts in contact with the
media thoroughly before changing the dosing medium.
CAUTION
Increased risk of accidents due to insufficient qualification of personnel!
Dosing pumps and their accessories may only be installed, operated and
maintained by personnel with sufficient qualifications. Insufficient
qualification will increase the risk of accidents. ð Ensure that all action is
taken only by personnel with sufficient and
corresponding qualifications. ð Prevent access to the system for unauthorised
persons.
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Safety 5
General warnings
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
2.2 Hazards due to non-compliance with the safety instructions
Failure to follow the safety instructions may endanger not only persons, but
also the environment and the device.
The specific consequences can be: n failure of vital functions of the dosing
pump and the system, n failure of required maintenance and repair methods, n
danger for individuals through dangerous dosing media, n danger to the
environment caused by substances leaking from the
system.
2.3 Working in a safety-conscious manner
Besides the safety instructions specified in this operating manual, further
safety rules apply and must be followed: n accident prevention regulations, n
safety and operating provisions, n safety provisions for handling dangerous
substances (mostly the
safety data sheets to dosing media), n environmental protection provisions, n
applicable standards and legislation.
2.4 Personal protective equipment
n working on the dosing pump while running, n shutdown, n maintenance work, n
disposal.
2.5 Personnel qualification
Any personnel who work on the dosing pump must have appropriate special
knowledge and skills.
Anybody who works on the dosing pump must meet the conditions below:
n attendance at all the training courses offered by the owner, n personal
suitability for the respective activity, n sufficient qualification for the
respective activity, n training in handling of the dosing pump, n knowledge of
safety equipment and the way this equipment functions, n knowledge of this
operating manual, particularly of safety instructions
and sections relevant for the activity, n knowledge of fundamental regulations
regarding health and safety
and accident prevention.
All persons must generally have the following minimum qualification:
n training as specialists to carry out work on the dosing pump unsupervised,
n sufficient training that they can work on the dosing pump under the
supervision and guidance of a trained specialist.
Based on the degree of risk posed by the dosing medium and the type of work
you are carrying out, you must use corresponding protective equipment. Read
the Accident Prevention Regulations and the Safety Data Sheets to the dosing
media find out what protective equipment you need.
You will require the minimum of the following personal protective equipment:
Personal protective equipment required
Protective goggles
Protective clothing
Protective gloves
Table 3: Personal protective equipment required
Wear the following personal protective equipment when performing the following
tasks: n commissioning,
6 Safety
Personnel qualification
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
These operating instructions differentiate between these user groups:
2.5.1 Specialist staff
Thanks to their professional training, knowledge, experience and knowledge of
the relevant specifications, specialist staff are able to perform the job
allocated to them and recognise and/or eliminate any possible dangers by
themselves.
2.5.2 Trained persons
Trained persons have received training from the operator about the tasks they
are to perform and about the dangers stemming from improper behaviour.
In the table below you can check what qualifications are the pre-condition for
the respective tasks. Only people with appropriate qualifications are allowed
to perform these tasks!
Qualification
Activities
Specialist staff
n Assembly n Hydraulic installations n Electrical installation n Maintenance n Repairs n Commissioning n Taking out of operation n Disposal n Fault rectification
Trained persons
n Storage n Transportation n Control n Fault rectification
Table 4: Personnel qualification
Operating instructions
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Safety 7
Personnel qualification
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
3 Intended use
3.1 Notes on product warranty
Any non-designated use of the product can compromise its function or intended
protection. This leads to invalidation of any warranty claims!
Please note that liability is on the side of the user in the following cases:
n The dosing pump is operated in a manner which is not consistent with these
operating instructions, particularly the safety and handling instructions and
the chapter 3 ,,Intended use” on page 8.
n If people operate the product who are not adequately qualified to carry out
their respective activities.
n No original spare parts or accessories of Lutz-Jesco GmbH are used. n
Unauthorised changes are made to the device by the user. n The user uses
different dosing media than those indicated in the
order. n The user does not use dosing media under the conditions agreed with
the manufacturer such as modified concentration, density, temperature,
contamination, etc.
3.2 Intended purpose
The dosing pump MEMDOS SMART LB / LD is intended for the following purpose:
the conveying and dosing of liquids.
dependence on the temperature of the media and the operating pressure.
i Information on the suitability of materials combined with different dosing
media can be found in the Compatibility Chart of Lutz-Jesco GmbH. The
information in this resistance list is based on information from the material
manufacturers and on expertise obtained by Lutz-Jesco from handling the
materials. As the durability of the materials depends on many factors, this
list only constitutes initial guidance on selecting material. In all cases,
test the equipment with the chemicals you use under operating conditions.
n The dosing pump is not intended for outdoor use unless appropriate
protective measures have been taken.
n Avoid leaks of liquids and dust into the casing and avoid direct exposure to
sunlight.
n You must never operate dosing pumps in a potentially explosive atmosphere if
they do not have corresponding nameplates or an appropriate EU Declaration of
Conformity for potentially explosive atmospheres.
3.5 Prohibited dosing media
3.3 Device revision
This operating manual applies to the following devices:
Device
MEMDOS SMART LB MEMDOS SMART LD
Table 5: Device revision
Month / year of manufacture 08/2016 onwards
08/2016 onwards
Firmware From 01:59
3.4 Principles
n Before delivery, the manufacturer inspected the dosing pump and operated it
under specific conditions (with a specific dosing medium with a specific
density and temperature, with specific pipe dimensions, etc.) Since these
conditions differ at every location of usage, the delivery capacity of the
dosing pump should be measured by gauging it at the operating company’s
installation. For details on the approximate values and the capacity of the
dosing pump, refer to the chapter 15 ,,Delivery characteristic curves” on page
40.
n Comply with the information regarding the operating and environmental
conditions (see chapter 5 ,,Technical data” on page 13).
n Any restrictions regarding the viscosity, temperature and density of dosing
media must be followed. You must only use dosing media at temperatures above
freezing point or below the boiling point of the respective medium.
n The materials of the dosing pump and hydraulic parts of the system must be
suitable for the dosing medium that is used. In this connection, note that the
resistance of these components can change in
The dosing pump must not be used for these media and substances:
n Gaseous media, n radioactive media, n solid substances, n combustible media,
n all other media that are not suitable for delivery using this dosing
pump.
3.6 Foreseeable misuse
Below, there is information about the applications of the dosing pump or
associated equipment that are not considered to be intended use. This section
is intended to allow you to detect possible misuse in advance and to avoid it.
8 Intended use
Foreseeable misuse
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
Foreseeable misuse is assigned to the individual stages of the product
lifetime:
3.6.1 Incorrt assembly
n Unstable or unsuitable bracket n Dosing pump bolted wrongly or loosely
3.6.2 Incorrect hydraulic installation
n Suction and pressure lines dimensioned incorrectly n Unsuitable connection
of the pipes due to wrong material or
unsuitable connections. n Suction and pressure lines mixed-up n Damage to
threads due to them being tightened too much n Bending of pipelines n No free
return flow of the pressure relief valve n Excessive demand due to the
pressure differences between the
suction and discharge valves n Through-suction at installation without back-
pressure valves n Damage due to undamped acceleration mass forces n Exceeding
the admissible pressure on the suction and discharge sides n Using damaged
parts
3.6.3 Incorrect electrical installation
n Connecting the mains voltage without a protective earth n Unsecured mains or
one that does not conform to standards n Not possible to immediately or easily
disconnect the power supply n Wrong connecting cables for mains voltage n
Dosing pump accessories connected to wrong sockets n Diaphragm monitoring not
connected or defective n Protective earth removed
3.6.4 Incorrect start-up
n Start-up with damaged system n Shut-off valves closed at commissioning n
Closed suction or pressure line, e.g. due to blockages n Personnel was not
informed before the start-up n System was recommissioned after maintenance
without all the
protective equipment and fixtures, etc. being reconnected n Inadequate
protective clothing or none at all
3.6.5 Incorrect operation
n Protective equipment not functioning correctly or dismantled n Modification
of the dosing pump without authority n Ignoring operational disturbances n
Elimination of operational disturbances by personnel without
adequate qualifications n Deposits in the dosing head due to inadequate
purging, particularly
with suspensions n Bridging the external fuse n Operation made more difficult
due to inadequate lighting or machines
that are difficult to access n Operation not possible due to dirty or
illegible display of the dosing
pump
n Delivery of dosing media for which the system is not designed n Delivery of
particulate or contaminated dosing media n Inadequate protective clothing or
none at all
3.6.6 Incorrect maintenance
n Carrying out maintenance during ongoing operation n Carrying out work that
is not described in the operating manual n No adequate or regular inspection
of correct functioning n No replacement of damaged parts or cables with
inadequate
insulation n No securing against reactivation during maintenance work n Using
cleaning materials that can cause reactions with the dosing
media n Inadequate cleaning of the system n Unsuitable purging medium n
Unsuitable cleaning materials n Detergents left in system parts n Using
unsuitable cleaning equipment n Using the wrong spares or lubricants n
Contaminating the dosing medium with lubricant n Installing spare parts
without following the instructions in the
operating manual n Blocking venting orifices n Pulling off sections of the
plant n Contamination at installation without a dirt trap n Mixing up the
valves n Mixing up the sensor lines n Not reconnecting all the lines n
Damaging or not installing all the seals n Not renewing seals n Not paying
attention to safety data sheets n Inadequate protective clothing or none at
all
3.6.7 Incorrect decommissioning
n Not completely removing the dosing medium n Dismantling lines while the
dosing pump is running n Device not disconnected from the power supply n Using
the wrong dismantling tools n Inadequate protective clothing or none at all
3.6.8 Incorrect disposal
n Incorrect disposal of dosing media, operating resources and other materials
n No labelling of hazardous substances
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Intended use 9
Foreseeable misuse
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
4 Product description
4.1 Properties
4.3 Structure of the dosing pump
The MEMDOS SMART is a stepper motor-driven diaphragm dosing pump 4.3.1 General
Overview that is used when precise dosing results are required.
b
They are characterized by the following properties:
n Output range from 2 30 l/h, up to 20 bar
c
n Power supply 110–240 V, 50/60 Hz, IP65, 25 W
n Microprocessor-controlled drive
n Integrated dosing head ventilation (only MEMDOS SMART LB / LD 2, LB / LD 5 and LB / LD 10 with plastic dosing head)
n Suitable for wall and floor mounting
a
n Material finishes PVC, PP, PVDF and stainless steel
n Release input for external start/stop
Also with MEMDOS SMART LD:
n Pulse input (increase and reduction) n Level input with early warning and main alarm n Stroke frequency can be precisely adjusted via the keyboard n Graphic display n Calculation wizard for pulse operation available online
Fig. 1: General Overview
No. 1 Dosing head
Description
4.2 Scope of delivery
Please compare the delivery note with the scope of delivery. The following
items are part of the scope of delivery:
2 Drive unit 3 Control box
Table 6: General Overview
n Dosing pump MEMDOS SMART LB / LD, n One set each of hose clamping
connections for the suction and
discharge sides for hoses with diameters of 4/6 mm, 6/9 mm and 6/12 mm (made
of PVC, PP and PVDF), n Covering caps electrical connections: 1 for MEMDOS
SMART LB 3 for MEMDOS SMART LD, n Conductive rubber band for electrical
contacts: 1 for MEMDOS SMART LB (in connection port 1) 2 for MEMDOS SMART LD
(in connection ports 1 and 3), n Mains cable, n Operating instructions, n
Inspection report and test certificate (optional), n Accessory kit (optional).
4.3.2 Dosing head
a b c
d
Fig. 2: Dosing head
No.
Description
1 Valve and connection on the discharge side
2
Integrated dosing head ventilation (only MEMDOS SMART LB / LD 2, LB / LD 5 and LB / LD 10 with plastic dosing head)
3
Arrow indicating the direction of throughflow of the dosing medium (plastic version only)
4 Valve and connection on the suction side
Table 7: Dosing head
10 Product description
Structure of the dosing pump
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
4.3.3 Control element of the LB
a
b c
d e
Fig. 3: Dosing pump control MEMDOS SMART LB
No.
Description
1 Stroke frequency setting
2 Power LED
3 Alarm LED
4 Release input for external start/stop
5 Mains cable for power supply
Table 8: Designation of components
4.3.4 Control element of the LD
4.4 Function description
Dosing pumps are positive displacement pumps. They are used if precisely
defined delivery of a medium is necessary. A constant volume per stroke or
time is delivered.
The system delivers or meters the dosing medium by means of a repeated
sequence of suction strokes followed by pressure strokes. This results in a
pulsing flow.
If the dosing pump is in the suction stroke phase, the diaphragm is pulled
into the rear final position. Due to the resulting vacuum in the dosing head,
the discharge valve closes, the suction valve opens and dosing medium flows
from the suction line into the dosing head.
If the dosing pump is in the pressure stroke phase, the diaphragm is moved
into the front final position. Due to the pressure in the dosing head, the
suction valve closes and the dosing medium flows through the discharge valve
from the dosing head into the pressurised pipe.
4.5 Rating plate
There is information on the equipment about safety or the product’s way of
functioning. The information must stay legible for the duration of the service
life of the product.
1
Lutz-Jesco GmbH 30900 Wedemark
Am Bostelberge 19 Germany 2
MEMDOS SMART
13 XX/XXXX
3
Material:
Max. XXX l/h bei XX bar
4
Max. XXX l/h bei XX bar
IP XX, XXX V AC, XXXX Hz, XX kW
12
5 6
102A12345678
P/N: S/N:
XXXXXXXXXX
12345678012345
Made in Germany
11
a b
c d
Fig. 4: Dosing pump control MEMDOS SMART LD
No. 1 Graphic display
Description
2 Multifunction keys on the contol unit for operator inputs
3 Connection ports for external operation
4 Mains cable for power supply
Table 9: Designation of components
78
9
10
Fig. 5: Rating plate MEMDOS SMART LB / LD
No.
Description
1 Product, type, nominal size
2 Material of the dosing head / seals
3 Maximum delivery capacity at average pressure
4 Maximum delivery capacity at maximum pressure
5 Protection class
6 Voltage supply
7
Label showing conformity with applicable European directives
8 WEEE label
9 Frequency
10 Power consumption
11 Serial number
12 Part number
13 Month / year of manufacture
Table 10: Rating plate
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Product description 11
Rating plate
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
4.6 Conveying characteristics
The design of the dosing pump enables it to perform the pressure and suction
stroke at different speeds. For low supply rates, for example, the dosing pump
performs the suction stroke at the maximum speed and adjusts the speed of the
pressure stroke to match the desired supply rate. This produces a constant
supply stream, which gives you a low-pulsation, smooth dosing.
Settings
100 % delivery rate
Time
50 % delivery rate
Time
10 % delivery rate
Fig. 6: Selecting available dosing programs
Time
Pressure stroke Suction stroke
12 Product description
Conveying characteristics
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
5 Technical data
5.1 Delivery capacity data
Please note that some of this data only represents guide values. The actual
capacity of a dosing pump depends on various factors. For approximate values
of the delivery capacity at different pressures, refer to chapter 15
,,Delivery characteristic curves” on page 40.
Information
Value 2
MEMDOS SMART LB / LD Size
5
10
15
20
30
Delivery capacity at max. backpressure
l/h
2.4
5.1
10.7
13.7
20.4
30.7
ml/stroke
0.22
0.57
1.19
1.52
2.27
3.41
Max. delivery pressure
bar
20 (16*)
16
10
6
5
3
l/h
2.6
5.7
11.3
14.4
21.2
31
Delivery capacity at average backpressure
ml/stroke
0.28
0.63
1.26
1.60
2.36
3.44
Average delivery pressure
bar
10
8
5
3
2.5
1.5
Max. stroke frequency
min-1
150
Suction lift for non-gassing media
mWS
3
Table 11: Output data
- with a PVC design.
5.2 Operating conditions and limits
Information
Value
MEMDOS SMART LB / LD Size 2 30
Approved ambient temperature
°C
5 45 (with PVC components 5 40)*
Relative humidity
%
max. 90
Max. sound pressure level
dB(A)
51 56
Max. supply pressure
mbar
800
Viscosity limits
mPas
300** / 1000***
Adjustable dosing range
%
Table 12: Operating conditions and limits
0 100
- Use of the dosing pump at ambient temperatures below 5 °C must be checked individually. In such cases, please contact the manufacturer.
** With a viscosity of ~300 mPas and above, you must use spring-loaded valves.
*** If the viscosity of the medium is larger than 1000 mPa·s, the use of the dosing pump must be checked individually. In such cases, please contact the manufacturer.
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Technical data 13
Operating conditions and limits
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
5.2.1 Approved media temperature
Information Dosing head made of PVC Dosing head made of PP Dosing head made of
PVDF Dosing head made of stainless steel (1.4571)
Table 13: Approved media temperature
Value °C °C °C °C
5.3 Electrical specifications
Information Voltage supply Power consumption
Table 14: Electrical specifications
Value W
5.4 Other data
Information
Value 2
Weight (with dosing head made of PVC, PP, PVDF)
kg
Weight (with dosing head made of stainless steel (1.4571))
kg
Diameter of diaphragm
mm
33
Electrical cable
m
Protection class
Insulation class
Valve connection
Valve size
DN3
Table 15: Other data
Operating instructions
MEMDOS SMART LB / LD (all sizes) 0 35 0 60 0 80 0 80
MEMDOS SMART LB / LD (all sizes) 110 240 V AC, -10% / +5%, 50/60 Hz
25
MEMDOS SMART LB / LD Size
5
10
15
20
30
2.2 approx.
3.3 approx.
39
54
1.8 m (with mains plug)
IP65 (with covering caps on the connections)
F
G5/8 male
DN4
14 Technical data
Other data
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
6 Dimensions
6.1 MEMDOS SMART LB / LD 2, 5, 10
~ 260 ~ 205
Operating instructions
L
120
Ø 80 100 116
~ 180
L
~ 59
~ 43
~ 76
Ø 6,5 70
Fig. 7: Dimensioned drawing of MEMDOS SMART LB / LD 2, 5, 10 with dosing head
made of PVC, PP or PVDF (all dimensions in mm)
~ 237 ~ 202
L
Ø 80 100 116
~ 120
~ 176
Ø 6,5 70
L
~ 56
~ 17
~ 81
Fig. 8: Dimensioned drawing of MEMDOS SMART LB / LD 2, 5, 10 with dosing head made of stainless steel (1.4571) (all dimensions in mm)
Hose clamp connector
Material
Scale
Nominal width
L
LB / LD 2
PVC / PP / PVDF
4/6 mm
DN4
31
Stainless steel
4/6 mm
DN4
50
4/6 mm
DN4
31
LB / LD 5, 10
1/4×3/8″
1/4″
34
PVC / PP / PVDF
6/9 mm
DN6
34
6/12 mm
DN6
15
4/6 mm
DN4
50
Stainless steel (1.4571) /
PVDF
6/9 mm
DN6
54
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Dimensions 15
MEMDOS SMART LB / LD 2, 5, 10
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
6.2 MEMDOS SMART LB / LD 15, 20, 30
~ 237 ~ 202
Operating instructions
L
Ø 84 100 116
~ 132 (stainless steel)
~ 130 (plastic)
~ 181
L
~ 53
~ 17,5
~ 84
Ø 6,5 70
Fig. 9: Dimensioned drawing of MEMDOS SMART LB / LD 15, 20, 30 with dosing head made of PVC, PP, PVDF or stainless steel (1.4571) (all dimensions in mm)
Hose clamp connector
Material
Scale
Nominal width
L
4/6 mm
DN4
31
LB / LD 15, 20, 30
1/4×3/8″
1/4″
34
PVC / PP / PVDF
6/9 mm
DN6
34
6/12 mm
DN6
15
Stainless steel (1.4571) /
4/6 mm
DN4
50
PVDF
6/9 mm
DN6
54
16 Dimensions
MEMDOS SMART LB / LD 15, 20, 30
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
7 Installing the Dosing Pump
DANGER
Mortal danger from electric shock!
Electrically conductive liquid can enter pump housings, cable screw
connections and mains connectors. ð Make sure that all protective measures
comply at least with the
requirements of protection class IP65. ð Always set up the dosing pump such
that water cannot enter the
housing.
7.2 Installation examples 7.2.1 Installation on a wall console
Operating instructions
CAUTION
Danger of personal injury and material damage!
A dosing pump that is difficult to access represents a danger due to incorrect
operation and faulty maintenance. ð Install the dosing pump such that it is
accessible at all times.
Especially the oil level glass, the oil inlet and the oil drain.
7.1 Set up information
When installing, follow the basic principles below:
n The valves must be vertical: Discharge valve at top, suction valve at
bottom. in this connection, pay attention to the arrow on the dosing head. The
dosing head must be aligned such that the arrow points vertically upwards.
n You should install the dosing pump at a convenient height for operation.
n It must not be installed under the ceiling. n The frame of foundation for
fixing the dosing pump must not be
subjected to jolts. The pump must be vibration-free and stable. n There must
be enough free space in the area of the dosing head and
the suction and discharge valves for these parts to be easily dismantled if
required. The entire space requirement for installation and maintenance is
approximately 1 m². n The distance from the sides of the dosing pump to the
wall or other dosing pumps or equipment must be at least 3 cm. There must be a
guaranteed flow of circulating air. n The maximum ambient temperature must be
complied with, see chapter 5.2 ,,Operating conditions and limits” on page 13.
If necessary, radiant heat from surrounding equipment must be screened. n
Avoid exposure to direct sunlight. n The dosing pump is not intended for use
out of doors unless appropriate protective measures have been taken to prevent
dust and water from entering the housing. n For the dimensions of the
fastening holes, refer to chapter 6 ,,Dimensions” on page 15. n The tightening
torque for the fastening bolts is 1.5 2 Nm.
Fig. 10: Installation on a wall console
To reduce the structure-borne noise, the dosing pump is bolted to the wall
bracket using rubber elements. The materials necessary for this are included
with the wall bracket. 7.2.2 Installation on the wall
Fig. 11: Installation on the wall
The dosing pump can be mounted to the floor or directly to the wall without
the need for additional elements. Turn the dosing head appropriately to ensure
the flow direction of the medium through the dosing head.
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Installing the Dosing Pump 17
Installation examples
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
8 Hydraulic installations
In this chapter, you will find information about the hydraulic parts of a
system that you should install or that can install additionally. In many
cases, you must install hydraulic accessories to be able to use all the
functions that the dosing pump offers, to guarantee functional safety or to
achieve a high level of dosing precision.
WARNING
Caustic burns or other burns through dosing media! A diaphragm rupture,
blocked pressure lines or the use of material not suitable for the dosing
medium can result in the discharge of dosing medium. Depending on the type and
hazardousness of the dosing medium, this can result in injury. ð Wear the
recommended personal protective equipment. ð Make sure that the materials you
are using are suitable for the
dosing medium. ð Make sure that the lubricants, adhesives, sealants, etc. that
you
use are suitable for the dosing medium. ð Install a leakage drain. ð Install
pressure relief valves.
CAUTION
Danger of personal injury and material damage! High peak pressures can lead to
piping vibrating and cause them to snap. This can result in injury from piping
or escaping dosing media. ð Install pulsation dampeners.
NOTE
NOTE
Locking of threads
Stainless steel and plastic parts (particularly those made of PVC) that are
bolted together in a detachable connection (e.g. the dosing head and the
valves) can lock. This makes them difficult to release. ð Before bolting,
grease the corresponding parts with a lubricant
(e.g. PTFE spray). Ensure that the lubricant is compatible with the dosing
medium.
8.1 Design of the system
n The dosing pumps technical data (see chapter 5 ,,Technical data” on page 13)
must be taken into account and the plant s layout must be set up appropriately
(e.g. pressure loss when rating the lines with regard to their nominal
diameter and length).
n The entire system and its integrated dosing pump must be designed in such a
way that an escaping dosing medium (due to the failure of wearing parts such
as the diaphragm, or burst hoses) does not lead to permanent damage to system
parts or the premises.
n The leakage opening of the dosing head must be visible so that you can
detect a diaphragm rupture. It must be possible for the outflow from the
leakage drain to be on a free downwards gradient.
n If you use hazardous dosing media, the installation must be designed such
that no disproportionately high consequential damages arise due to dosing
media escaping.
n To avoid dosing errors after the end of the process, the dosing pump must be
locked hydraulically.
n To allow you to easily inspect the pressure conditions in the system, you
should provide connections for pressure gauges close to the suction and
discharge valves.
Damage to drives due to overloading
The pressure conditions between the suction and discharge sides must be
balanced; otherwise, overloading can result. This can lead to uncontrolled
dosing processes, damage to the piping and to the dosing pump. ð Ensure that
the pressure on the discharge side is at least 1 bar
than on the suction side.
18 Hydraulic installations
Design of the system
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
8.2 System piping
n The system piping must not exert any force on the connections and valves of
the dosing pump.
n This means that steel piping should be connected to the dosing pump by means
of flexible pipe sections.
n The nominal diameters of the pipework and the installed fittings should be
rated the same as or greater than the nominal diameters of the dosing pump’s
suction and discharge valves.
n The suction line should be kept as short as possible. n You should avoid
intertwined hoses. n Avoid loops, since air bubbles can collect.
8.3 Aligning the dosing head
a
8.4 Hydraulic connections
8.4.1 Connecting hose clips
Choose the hose connection according to the condition of the hose (material,
inner diameter, wall thickness) in order to ensure maximum pressure
resistance.
8.4.1.1 Size 4/6 and 6/9
4/6
a
6/9
a
b b
c
c
d
d
b
e
e
c
Fig. 12: Aligning the dosing head
When connecting the dosing lines to the dosing pump, you must observe the
direction of through-flow (see arrow 2). The dosing head must be aligned
vertically. The alignment can be changed in 90° intervals. The suction valve
(3) must always point downwards. Accordingly, arrow (2) and pressure valve (1)
always point upwards. This is irrespective of the positioning of the dosing
head to the drive.
Fig. 13: Hose clips 4/6 and 6/9 (internal and external diameters in mm)
Perform the following working steps:
1. Cut the hose (1) to the appropriate length neatly and at an exact right
angle.
2. Place a gasket that is suitable for the dosing medium between the
connection (5) and the valve.
3. Screw the connecting piece to the dosing pump’s valve using the union nut
(2).
4. Thread the union nut (3) and the clamping ring (4) onto the hose. 5. Plug
the hose all the way in to the grommet of connection piece. 6. Push the
clamping ring onto the grommet of connection piece and
screw it to the union nut. 7. Carry out the same procedure with the connection
to the dosing
pump’s other valve.
ü Hose clip connected.
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Hydraulic installations 19
Hydraulic connections
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
8.4.1.2 Size 6/12
a b
c
8.4.2 Making the glue-in connection
a
b
d
Fig. 15: Glue-in connection
Fig. 14: Hose clip 6/12 (internal and external diameter in mm)
Size 6/12 hose clips only have a union nut. It clamps the hose onto the
grommet of the connection piece and at the same time fastens on the dosing
pump’s valve.
Perform the following working steps:
1. Cut the hose (1) to the appropriate length neatly and at an exact right
angle.
2. Place a gasket that is suitable for the dosing medium between the
connection (4) and the valve.
3. Push the union nut (2) and the cutting ring (3) over the hose. Press the
end of the hose onto the grommet of connection piece. You can do this more
easily by moistening the end of the hose on the inside or applying some
lubricant to the grommet in the cone area. You should push at least two thirds
of the hose onto the grommet of the connection piece.
4. Push the cutting ring over the hose into the cone area on the grommet of
connection piece.
5. Screw the union nut onto the valve of the dosing pump.
ü Hose clip connected.
Perform the following working steps: 1. Cut the PVC tube to length. 2. Push
the union nut (1) onto the tube. 3. Stick the bonded coupling sleeve (2) to
the tube (follow the
instructions of the adhesive manufacturer). 4. Screw the union nut onto the
valve of the dosing pump. Use a gasket
that is suitable for the dosing medium.
ü Glue-in connection made.
8.4.3 Making the cemented connection
a
b
Fig. 16: Cemented connection
Perform the following working steps:
1. Cut the tube to length. 2. Cut the thread (2) onto the end of the tube. 3.
Push the union nut (1) onto the tube. 4. Seal the thread. When choosing your
sealing material, take into
account its resistance to material, temperature and pressure. 5. Screw the
union nut onto the valve of the dosing pump. Use a gasket
that is suitable for the dosing medium.
ü Cemented connection made.
i Under normal conditions, you only need to screw the hydraulic connections finger-tight. However, due to the material settling, the pre-tension of the screw connection can slacken. This means that you must re-tighten the screw connection before carrying out commissioning.
20 Hydraulic installations
Hydraulic connections
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
8.5 Connecting a leakage drain
8.6 Connecting the dosing head venting facility
Lutz-Jesco GmbH dosing pumps are produced to the highest of quality standards
with a long service life. However, some parts are subject to operational wear.
This is the case particularly with the diaphragms that are continuously
subjected to forces during the suction and discharge strokes and to the
effects of the dosing medium.
If a diaphragm ruptures, the dosing medium starts to leak. This leakage is
drained via the leakage opening. On the flange of the dosing head, there are
three openings for this purpose. Depending on the alignment of the dosing
pump, the leakage is drained via the downward opening.
The dosing heads of the MEMDOS SMART LB / LD 2, 5 and 10 have an integrated
dosing head venting unit (except for dosing heads made of stainless steel).
For the procedure when venting, refer to chapter 11.1.1 ,,Venting the dosing
pump” on page 30.
Fig. 17: Openings of the leakage drain
Fig. 18: Dosing head venting facility with hose connection
Perform the following working steps:
1. Connect a 4/6 hose to the dosing head venting facility. 2. Route the other
end of the hose into the dosing tank or a collecting
tank.
ü Dosing head venting facility connected.
NOTE
Damage to drives due to effervescent media
If a hose is connected to the leakage drain and it is routed back into the
dosing tank, effervescent media can enter the drive and damage it. ð Collect
the leakage in a collecting pan. ð As an alternative, you can route the
leakage back to to the dosing
tank using a funnel. You should install the funnel at an adequate distance
from the leakage opening.
8.7 Hydraulic accessories
The following chapter is intended to give you an overview of installation
options.
Please note that these operating instructions are no substitute for the
instructions supplied with the accessories in each case. The corresponding
documentation supplied with the product applies to safety information and
provides exact instructions on assembly.
8.7.1 Injection nozzle
If the pressure line enters a main line, it is advisable to install an
injection nozzle.
Injection nozzles have three main functions: n Dosing the medium into a main
line, n Preventing flowback into the pressure line through a non-return valve.
Notes on assembly:
n Double-ball injection nozzles must be installed into the main line
vertically from the bottom. You can install hose and spring-loaded injection
nozzles any way you like.
n With dosing media that tend to crystallize, it is advisable to carry out
installation into the main line from the bottom. This prevents air bubbles
from being trapped.
n Many dosing media tend to contaminate the injection nozzles, which can lead
to blockages. In cases like this, it is advisable to install an injection
nozzle that is easy to dismantle and block off.
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Hydraulic installations 21
Hydraulic accessories
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
8.7.2 Contact-type water meter
The contact-type water meter measures the throughflow in a pipe and sends a
pulse to the dosing pump, which then starts dosing. This means that ideal
proportional dosing is also possible with large throughflow fluctuations.
The contact water meter is connected to connection port 2 (see chapter 9.2.2
,,Connection socket 2″ on page 25).
The ratio of throughflow to executed strokes of the dosing pump is determined
in “Pulse input” mode (see chapter “Water meter” on page 24).
8.7.3 Pressure-relief valve
Pressure relief valves have an important safety function for protecting the
dosing pump and the associated pipes and fittings. The dosing pump can
generate a pressure that is many times the rated one. A blocked pressure line
can lead to dosing medium escaping.
An improperly high pressure can occur if:
n the shut-off valves are closed even though the dosing pump is running,
n pipes block. At an appropriate pressure, a pressure relief valve opens a
bypass line and protects the system in this way from damage caused by over-
pressure.
Notes on assembly:
n The line for returning dosing medium from the pressure relief valve must be
routed to the dosing tank or to a collecting pan.
n The pressure in the dosing tank must not be too high so that it is possible
to accommodate the returned dosing medium.
n As an alternative, the system can return dosing medium into the suction line
in front of the dosing pump. In this case, there must not be a non-return
valve or a foot valve in the suction line.
n You should install the pressure relief valve as close as possible to the
dosing head.
8.7.4 Back-pressure valve
Back-pressure control valves are necessary if:
n There are considerably fluctuating system pressures, n the pressure on the
suction side is higher than on the discharge side
or if you intend to carry out dosing into depressurized lines. In cases like
this, if you do not use a back-pressure valve, imprecise dosing results will
occur or overloading will result. The back-pressure valve solves these
problems by generating a defined, constant backpressure.
In some circumstances, a back-pressure valve is unnecessary if you use a hose
injection nozzle and if the backpressure that it generates is adequate.
8.7.5 Pulsation dampener
Pulsation dampeners have the following functions:
n Damping pulsating delivery flows for processes that require low-pulsation
dosing,
n reducing the throughflow resistance with long pipelines.
When installed on the suction side:
n Damping of acceleration mass forces and with this reduction of wear on the
dosing pump.
n Preventing cavitation (pull-off of the liquid column) due to too high
acceleration.
However, pulsation dampeners also have important safety functions, since they
prevent pressure peaks from arising that lead to piping vibrating and cause
them to snap.
This problem can occur:
n With the high amplitudes of the vibrations, n when using long pipes (the
severity of the pulsation increases with the
length of the pipe), n when using rigid piping instead of elastic hoses.
Notes on assembly:
n You should carry out assembly in the direct vicinity of the location where
you want to damp the pressure peaks (directly in front of the suction valve or
directly behind the discharge valve).
n Pulsation dampeners should be installed with throttle valves or back-
pressure valves installed directly behind them. By setting the valves
appropriately, you can further-optimise damping of the pulsations.
n To prevent unnecessary pipe friction losses, you should lay the connecting
line straight and in accordance with the rated width of the pulsation
dampener.
n You must separately fasten relatively large pulsation dampeners and ones
with hose connections.
n Pipelines must not transfer any mechanical tensions onto the pulsation
dampener.
8.7.6 Priming aid
Priming aids are particularly advisable:
n In the case of dosing pumps with small volumetric displacements per stroke
or with low stroke length settings,
n with high suction hights, n with highly dense dosing media, n at priming for
the first time due to dry valves and air in the suction line
and the dosing head, n in dosing systems with frequent downtimes.
Further advantages resulting from priming aids:
n Preventing cavitation in the suction line, n gas removal, n optical dosing
control with small amounts, n smoothing of the suction flow.
8.7.7 Level monitoring
Only for LD: Level monitoring of suction-side feeding of the dosing medium to
prevent the tank being sucked dry and to ensure that it can be topped up again
in good time.
22 Hydraulic installations
Hydraulic accessories
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
8.7.8 Dosing of suspensions
When dosing suspensions, the dosing head must be rinsed regularly to prevent
depositing. To do this, you install a feed line for the rinsing medium (water)
in the suction side installation.
8.7.9 Suction pressure regulator
A suction pressure regulator may be necessary if the suction-side installation
of the system demonstrates a varying suction pressure or supply pressure:
n Dosing pumps that are installed above dosing tanks deliver less as the tank
empties, since the suction head increases.
n Dosing pumps that are installed below dosing tanks deliver less as the tank
empties, since the positive delivery pressure reduces.
Further problems that can occur:
n Greater wear on the dosing pump, e.g. diaphragm rupture due to the effects
of heavy forces with particularly high tanks and high-density dosing media.
n Idling of the dosing tank in the case of a diaphragm rupture or pipe
breakage.
n Impermissibly high forces in the pump transmission that occur when dosing
pumps receive the dosing medium directly from the pressure line.
n Reduced performance or destruction of fittings due to cavitation with long
suction lines.
Installing a suction pressure regulator is a remedy for the problems above.
The suction pressure regulator is opened by the dosing pump’s suction
pressure. This ensures that no dosing medium can flow if the dosing pump is
not running or no vacuum can be generated following a pipe fracture.
Notes on assembly:
n When using a large suction pressure regulator, you should provide a
pulsation dampener on the suction side.
Operating instructions
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Hydraulic installations 23
Hydraulic accessories
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
9 Electrical installation
Operating instructions
DANGER
Mortal danger from electric shock! If there is an electrical accident, you
must disconnect the dosing pump from the mains as quickly as possible. ð
Install an emergency stop switch or integrate the dosing pump into
the plant safety concept.
CAUTION
Danger of automatic start up! The dosing pump does not have an ON/OFF switch
and may start to pump as soon as it is connected to the mains supply. ð
Install an emergency stop switch or integrate the dosing pump into
the plant safety concept.
NOTE
Damage due to incorrect mains voltage The dosing pump can be damaged if you
connect it to the wrong mains voltage. ð Observe the information on the mains
supply that is given on the
rating plate.
9.1 Principles
n The dosing pump has a 110 240 V AC 50/60 Hz wide-range power supply unit.
n The electrical connection comply with local regulations. n The dosing pump
must be plugged into a grounded power outlet. n To avoid dosing errors at the
end of the process, the dosing pump
must be locked electrically. n The dosing pump must not be operated by
switching the mains
voltage on or off. n Signal cables must not be laid parallel to high-voltage
current lines or
mains cables. You must route supply and signal lines in separate channels. An
angle of 90° is required at line crossings.
NOTE
Compromised functions due to open contacts
The dosing pump is supplied with conductive rubber bands installed in the
connection ports 1 (LB) or 1 and 3 (LD). The conductive rubber bands conduct
electricity and ensure that the contacts in the connection sockets remain
closed when no cables are connected. If the conductive rubber bands in
connection sockets are missing or not correctly installed and there are no
cables connected to the sockets, it is not possible to start the dosing pump.
ð Insert the conductive rubber bands in connection sockets if you do
not wire up the connection sockets. ð Ensure that the conductive rubber bands
are installed on the
correct contacts (see instructions in following section).
NOTE
Insufficient electromagnetic compatibility
When you connect the dosing pump to a socket without an attached protective
earth, it is not possible to guarantee the interference radiation and
interference immunity according to EMC regulations. ð Only connect the dosing
pump to sockets with an attached
protective earth.
Fig. 19: Removing the conductive rubber bands
24 Electrical installation
Principles
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
9.2 Description of connection sockets
Removing the conductive rubber band
Operating instructions
Fig. 20: Connection sockets 1 3
Inputs Release input (LB and LD) Pulse input (only LD) Level input (only LD)
Table 16: Inputs of the control unit
Connection socket 1 2 3
9.2.1 Connection socket 1
9.2.1.1 Release input
Using the Release input, it is possible to start or stop the dosing pump
externally. n Potential-free contact n Connection M12x1 cable with plug
connector, A-coded n Assignment of pin 3, 4
Pin M12x1 Assignments (A-coded)
1-
–
2-
–
3
Ground (GND)
Connection Cable colour*
–
Brown BN
–
White WH
3
Blue BU
4
External On/Off
4
Black BK
Table 17: Connection socket 1
- Applies to cable colours of cables from Lutz-Jesco GmbH. No liability is accepted for cables from other manufacturers.
For setting the External On/Off function, see chapter 11.3 ,,External On / Off via Release input” on page 33.
Fig. 21: Conductive rubber band in connection socket 1
Remove the conductive rubber band before inserting the cable in the connection
socket. After the cable has been removed, the conductive rubber band must be
reinserted in the connection socket. Insert it between pins 1 and 2 and 3 and
4 as shown in Fig. 21.
9.2.2 Connection socket 2
9.2.2.1 Pulse input
The pulse input makes it possible to control the delivery capacity by means of
pulses. The system regulates the delivery capacity by means of the dosing
pump’s stroke frequency and number of strokes in dependence on the number of
pulses and the pulse spacing.
n Provided potential-free contact n For potential-free NO contact, e.g. a
contact-type water meter n Pulse length min. 4 ms n Connection M12x1 cable
with plug connector, A-coded n Assignment of pin 1, 3 For information on
setting the External operating mode, see chapter 11.2.2 ,,External operation”
on page 31.
Pin M12x1 Assignments Connection Cable colour* (A-coded)
1
Pulses
1
Brown BN
2
–
White WH
3
Ground (GND)
3
Blue BU
4
–
–
Table 18: Connection socket 2
–
Black BK
- Applies to cable colours of cables from Lutz-Jesco GmbH. No liability is accepted for cables from other manufacturers.
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Electrical installation 25
Description of connection sockets
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
9.2.3 Connection socket 3
9.2.3.1 Level input
Connection for level monitoring of a dosing tank (e.g. a suction line with a
float switch). n Alert and main alarm n Potential-free contact n NO contact n
Connection M12x1 cable with plug connector, A-coded n Assignment of pin 1, 2,
3 For more details on installing the level monitoring system, see on page 22.
i A matching connection cable with A-coded plug connector is integrated in the
suction lines / level monitoring systems of Lutz-Jesco GmbH. An adapter is
required if using older suction lines with a 3.5 mm jack plug. You can find
this adapter and additional cables in the Lutz-Jesco GmbH price list.
Pin M12x1 Assignments Connection Cable colour* (A-coded)
1
Pre alarm
1
Brown BN
2
Main alarm
2
White WH
3
Ground (GND)
3
Blue BU
4-
–
–
Black BK
Table 19: Connection socket 3
- Applies to cable colours of cables from Lutz-Jesco GmbH. No liability is accepted for cables from other manufacturers.
Removing the conductive rubber band
Fig. 22: Conductive rubber band in connection socket 3
Remove the conductive rubber band before inserting the cable in the connection
socket.
After the cable has been removed, the conductive rubber band must be
reinserted in the connection socket. Insert it between pins 1 and 2 and 3 and
4 as shown in Fig. 22.
26 Electrical installation
Description of connection sockets
BA-10110-02-V01
Operating instructions
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
10 Control
10.1 Operating elements of the control LB
The desired delivery rate of the dosing pump is set using the stroke frequency
setting (3).
The stroke frequency can be adjusted while the pump is running or while it is
turned off (in depressurized condition).
The scale of the stroke frequency setting shows the value of the setting in
percent from 0% (stopped) to 100% (maximum possible stroke frequency).
10.2 Operating elements of the control LD a
a b
c
Fig. 23: Stroke frequency setting
Direction of rotation Clockwise Counter -clockwise
Table 20: Rotation direction and impact
Effect
Stroke frequency decreases, delivery capacity decreases Stroke frequency
increases, delivery capacity increases
Indicator lights
The Power LED (1) is lit permanently when the dosing pump is connected to the
power supply. The Power LED flashes when the dosing pump performs a pressure
stroke.
The Alarm LED (2) is lit when a fault has occurred (see chapter 13.1.1 ,,Alarm
LED illuminates (MEMDOS SMART LB)” on page 36).
b
Fig. 24: Operator controls of the control unit
No.
Explanation
1 Graphic display
2 Four multifunction keys
Table 21: Operator controls of the control unit
You operate the dosing pump MEMDOS SMART LD using the four keys below the
display. The system shows the respective functions of the keys at the bottom
of the display.
The + and – selection keys as well as the and Ø keys have a repeat function,
i.e. if you keep them pressed down, the system automatically repeats the key
function.
The display brightness reduces 45 seconds after your last input.
i The dosing pump does not have an ON/OFF switch. After being disconnected from the power supply, the dosing pump starts in the operating mode and configuration that you selected last.
10.2.1 Explanation of the menu icons
10.2.1.1 Dosing status display
Symbol
Meaning
Diaphragms stationary (no dosing stroke)
Diaphragms in stroke phase (dosing stroke)
Table 22: Explanation of the menu symbols Dosing status display
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Control 27
Operating elements of the control LD
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
10.2.1.2 Level monitoring
Symbol Dosing tank full
Meaning
Dosing tank at minimum (alert)
Dosing tank empty (main alarm)
Table 23: Explanation of the menu symbols Level monitoring
10.2.1.3 Operating modes
Symbol
Meaning
Internal (manual operation)
External (operation via pulse signals)
Table 24: Explanation of the menu symbols Operating modes
10.2.1.4 Release input
Activating the password protection
If password protection is activated, the dosing pump is protected against
unauthorized access. Settings can only be changed after alteration of the
password.
WARNING
Caustic burns or other burns through dosing media! If the password protection
is activated, operation of the dosing pump is blocked. The only way to stop a
dosing pump without entry of the password is via the power supply. In
unfavourable cases, if the password protection has been inadvertently
activated or the user has forgotten the password, the dosing pump cannot be
stopped in time. This can result in injury. ð Install an emergency stop switch
or integrate the dosing pump into
the plant safety concept.
You can set any password you like from 0001 to 9999. 1. Press – and +
simultaneously.
4The dosing pump displays the password protection menu.
Symbol
Meaning
Contact open (dosing pump stops)
Contact closed (dosing pump starts)
Table 25: Explanation of the menu symbols Release input
10.3 Password protection
Symbol
Meaning
Password protection active
Password protection inactive
Table 26: Explanation of the menu symbols – password protection
4 3 2 1
OK –
Fig. 25: Activating the password protection
2. Use the+ and – keys to set a value from 0 to 9 for the first digit of the
code and then press .
3. Proceed as described under point 2 for the other digits.
4. Choose the last point and press +.
5. Press OK.
4The dosing pump displays the corresponding symbol:
0%
Fig. 26: Start screen with activated password protection
i The factory setup before the first change of the pass word is: 4321.
ü Password protection activated.
28 Control
Password protection
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Entering the password
Once you press any key, you must enter the password. If you enter the code
correctly, you have 120 seconds in which to operate the dosing pump. The
password must be re-entered after the end of the 120 seconds, even if this
runs out during entry.
4 3 2 1
OK –
Fig. 27: Entering the password
1. Use the+ and – keys to set a value from 0 to 9 for the first digit of the
code and then press .
2. Proceed as described under point 1 for the other digits.
3. After entering all the digits, press OK.
4If your input is correct, the dosing pump displays the start screen.
i If you have forgotten the code, please contact Lutz-Jesco GmbH.
10.3.1.1 Deactivating the password protection
1. Press – and + simultaneously. 2. Press until is selected. 3. Press -. 4.
Press OK.
ü Password protection deactivated.
Operating instructions
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Control 29
Password protection
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
11 Operation
WARNING
4. LB: Turn the stroke frequency setting slowly counter-clockwise until the dosing pump draws in enough and dosing starts.
Caustic burns or other burns through dosing media!
After connecting the mains supply, residual dosing media in the dosing head
can spray out. ð Before connecting the mains supply, connect the dosing lines.
ð Check that all the screw connections have been tightened
correctly and are leak-proof.
CAUTION
Danger of automatic start up!
The dosing pump does not have an ON/OFF switch and may start to pump as soon
as it is connected to the mains supply. This means that dosing medium can
escape. Depending on the type and hazardousness of the dosing medium, this can
result in injury. ð Stop the dosing pump before disconnecting it from the
mains
supply. ð Ensure that the dosing pump has been installed correctly before
connecting it to the mains supply.
11.1 Commissioning the dosing pump
Precondition for action:
ü The dosing pump has been assembled and installed in accordance
with chapter 7 ,,Installing the Dosing Pump” on page 17, chapter 8 ,,Hydraulic
installations” on page 18 and chapter 9 ,,Electrical installation” on page 24.
ü All the mechanical fastenings have been inspected to ensure
adequate load-bearing capacity.
ü The dosing head screws have been tightened with the correct torque
(see chapter 12.2 ,,Tighten up dosing head bolts” on page 34).
ü All the hydraulic sections have been inspected to ensure they are
adequately leak-proof and that the through flow direction is correct.
LD: Select an operating mode and start the dosing pump in accordance with the
instructions in the chapter 11.2 ,,MEMDOS SMART LD: Operating modes” on page
31.
4The dosing pump primes. If it does not prime enough, use a priming
aid (see chapter 8.7.6 ,,Priming aid” on page 22).
i At initial commissioning, it is advisable to prime the pump without
backpressure. For this purpose, we recommend installing a relief valve on the
discharge side of the dosing pump.
ü The dosing pump is commissioned.
11.1.1 Venting the dosing pump
Size 2, 5 and 10 plastic dosing heads are fitted with a vent screw. Gas
bubbles can be removed from the dosing head using vent screws, in order to
improve the performance of the pumps / to remedy faults.
CAUTION
Danger of personal injury and material damage! Dosing medium can escape if you
loosen connections on the dosing head (e.g. for venting) during operation. ð
Use sufficient personal protective equipment. ð Follow the safety data sheet
of the dosing medium. ð Clean the dosing pump if dosing medium escapes. ð
Dispose of the dosing medium correctly.
i For initial commissioning, it is advisable to use water as the dosing medium
to check that the system is leak-proof and that the dosing pump is functioning
correctly. Check first whether undesirable reactions could occur between the
actual dosing medium and the water.
Perform the following working steps:
1. Open the shut-off valves on the suction and discharge sides if present.
2. Plug in the dosing pump’s mains plug to the power supply. 3. If the dosing
head is fitted with a vent screw, vent the dosing pump
(see section 11.1.1 ,,Venting the dosing pump” on page 30).
Fig. 28: Dosing head venting facility with vent screw
Precondition for action:
ü The dosing head venting facility connected has been connected in
accordance with the chapter 8.6 ,,Connecting the dosing head venting facility”
on page 21.
30 Operation
Commissioning the dosing pump
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
Venting the MEMDOS SMART LB
11.2.1 Internal operation
Perform the following working steps:
1. Open the vent screw by one complete turn (looking onto the dosing head,
anti-clockwise).
2. Start the pump. To this end, set the stroke frequency to 100%. 3. Stop the
pump as soon as there is a continuous throughflow from the
dosing head venting facility with no air bubbles. Turn the stroke frequency
setting to 0% to stop the pump. The dosing pump stops delivery. 4. Close the
vent screw.
ü The dosing pump is vented.
11.2.1.1 Selecting the operating mode 1. Press the Int key to select the
operating mode.
4The dosing pump displays the start screen of Internal operating
mode with the symbol .
0%
Ext – + Start
Fig. 29: Start display internal operation
Venting the MEMDOS SMART LD
Perform the following working steps:
1. Select the Internal.operating mode. 2. Press Stop. 3. Keep + depressed
until 100% delivery capacity is achieved. 4. Open the vent screw by one
complete turn (looking onto the dosing
head, anti-clockwise). 5. Press Start.
4The dosing pump starts delivery at the highest stroke frequency.
6. Press Stop, as soon as there is a continuous throughflow from the dosing
head venting facility with no air bubbles.
4The dosing pump stops delivery.
7. Close the vent screw.
ü The dosing pump is vented.
i If you are using strongly effervescent dosing media, allow them to flow out
continuously. Open the vent screw such that about one drop per 1 3 strokes
escapes, then close the discharge.
11.2 MEMDOS SMART LD: Operating modes
The MEMDOS SMART LD dosing pump has the following operating modes: n Internal
– Manual setting of the delivery capacity, n External – Controlling the stroke
frequency and number of strokes in
dependence on the number of pulses and the pulse spacing.
11.2.1.2 Starting the dosing pump
1. Use the + and – keys to set the desired stroke frequency. Adjustment
range: 0 100%.
i Pressing the + and – keys increases/decreases the stroke frequency by 1%. If
you keep the key depressed, the stroke frequency increases/decreases
increasingly in intervals of 2, 5 and 10.
2. Press Start.
ü Dosing pump has started.
11.2.1.3 Stopping the dosing pump
è Press Stop.
4The system displays the “Stop” signal and Stop changes to
Start.
ü Dosing pump has stopped.
11.2.2 External operation
The stroke frequency and consequently the delivery capacity of the dosing pump
MEMDOS SMART LD in the External operating mode is determined by the quantity
and interval of the incoming pulses in connection with the set transmission
factor.
11.2.2.1 Selecting the operating mode
è Press Ext to start the device.
4The dosing pump displays the start screen of the External
operating mode with the symbol .
100%
Int – + Start
Fig. 30: Start display external operation
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Operation 31
MEMDOS SMART LD: Operating modes
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
11.2.2.2 Setting the transmission and reduction
The transmission and reduction factors can be set in 1% intervals of 1% to
1000%. A set value of 100% means that the dosing pump executes one dosing
stroke per incoming pulse signal. For values above 100%, the dosing pump
executes more dosing strokes per pulse signal accordingly. For values below
100%, the dosing pump executes less than one dosing stroke per pulse signal,
meaning that several pulse signals are required before a dosing stroke is
executed. The number of pulse signals required for a dosing stroke is
displayed on the dosing pump display for values below 100%.
50% (2)
The dosing pump has a dynamic stroke buffer which includes the interval
between the pulses in the calculation and adjusts the distribution of the
dosing strokes accordingly.
11.2.2.3 Calculating the transmission factor
The dosing pump MEMDOS SMART LD has a defined stroke volume per dosing stroke.
If a certain dosing quantity is required per pulse, the corresponding
transmission factor can be calculated for the external operating mode.
i You can find a simple means of performing the necessary calculations on the
Lutz-Jesco GmbH homepage. To do so, click on the following link or enter it in
your browser: http://www.lutz-jesco.com/online-helfer-memdos-SMART-ld
Int – + Start
Fig. 31: Number of pulse signals required (here: 2)
Examples for transmission / reduction
Number of pulses
Setting
Dosing strokes
4
25%
1
2
50%
1
1
100%
1
2
100%
2
4
125%
5
1
1000%
10
Table 27: Examples for transmission / reduction of pulse signals
In cases of sequences of sequential pulses, it must be noted that the number
of dosing strokes corresponding to the pulses does not always follow the
pulses immediately in certain settings. This is due to the fact that only
entire dosing strokes are executed, e.g. not half or quarter dosing strokes.
Depending on the transmission or reduction factor and the number of pulses,
however, there is a possibility of uneven results with “pending” pulse
signals. In theses cases, the required number of dosing strokes is only
achieved after a number of pulse cycles.
Examples:
The dosing pump receives pulses with a reduction factor of 30%. For the first
stroke, it requires 4 pulses in this setting (4 x 30% = 120%), as 3 pulses (3
x 30% = 90%) are insufficient for one dosing stroke (= 100%). However, the
second dosing stroke is executed after just 3 more pulses, as the stroke
buffer of the dosing pump still has 20% pending from the first 4 pulses (120%
– 100% = 20%) and this is added to the 3 pulses (90% + 20% = 110%). The third
dosing stroke also only requires 3 additional pulses (90% + 10% = 100%). A
further 4 pulses are then required for the fourth dosing stroke.
If pulses are transferred to the dosing pump with a transmission factor of
125%, a dosing stroke is executed for each of the first 3 pulses. With the 4th
pulse, it executes 2 dosing strokes (3x 25% pending from the first 3 pulses +
125% = 200%).
11.2.2.4 Starting the dosing pump
Precondition for action:
ü The dosing pump has been connected in accordance with the
chapter 9.2.2 ,,Connection socket 2″ on page 25.
1. Press Start. 2. Supply pulses to the pulse input of the dosing pump.
ü Dosing pump has started.
11.2.2.5 Stopping the dosing pump
è Stop the incoming pulses or press Stop.
ü Dosing pump has stopped.
11.2.2.6 Operation with contact-type water meter
The dosing pump MEMDOS SMART LD is prepared for operation with a contact-type
water meter. The contact sequence of the water meter and the size of the
dosing pump must be matched to each other (calibrated).
i You can find a simple means of performing the necessary calculations on the
Lutz-Jesco GmbH homepage. To do so, click on the following link or enter it in
your browser: http://www.lutz-jesco.com/online-helfer-memdos-SMART-ld
32 Operation
MEMDOS SMART LD: Operating modes
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
11.3 External On / Off via Release input
11.3.1 MEMDOS SMART LB The dosing pump MEMDOS SMART LB can be started or
stopped via an open or closed switching contact at the release input.
11.3.2 MEMDOS SMART LD Regardless of the selected operating mode, you can
start or stop the dosing pump MEMDOS SMART LD by means of the closed switching
contact on the Release input.
100%
Int – + Start
Fig. 32: Start screen of external operation with symbol for closed contact in
centre
For the significance of the menu symbols, see chapter 10.2.1 ,,Explanation of
the menu icons” on page 27.
11.3.2.1 Starting the dosing pump è Close the switching contact on the Release
input.
ü Dosing pump has started.
11.3.2.2 Stopping the dosing pump è Open the switching contact on the Release
input.
ü Dosing pump has stopped.
11.4 Decommissioning the dosing pump
Perform the following working steps: 1. Stop the dosing pump in accordance
with the selected operating
mode. 2. Unplug the dosing pump’s mains plug from the power supply. 3.
Disconnect all electrical connections. 4. Depressurize all the hydraulic parts
in the system. 5. Unplug all the hydraulic connections on the dosing pump. 6.
Empty the dosing head. 7. Remove any residual dosing medium from the dosing
head by
flushing the system with a washing agent. Ensure that the washing agent is
compatible with the dosing medium.
ü Dosing pump is decommissioned.
hydraulic connections or locked to prevent dosing medium from escaping. n You
must follow the safety data sheet of the dosing medium.
11.6 Storage
Storing the dosing pump correctly extends its service life. You should avoid
negative influences such as extreme temperatures, high humidity, dust,
chemicals, etc.
Ensure ideal storage conditions where possible:
n The storage place must be cold, dry, dust-free and generously ventilated.
n Temperatures between + 2 °C and + 40 °C (for PP and PVDF dosing heads,
between + 2 °C and + 60 °C).
n Relative air humidity must not exceed 90 %.
11.7 Transportation
Perform the following working steps:
n The unit should be thoroughly cleaned. Any dangerous dosing media must be
additionally neutralised and decontaminated.
n All accessories should be dismantled. n All openings should be closed, so
that no foreign objects can get into
the system. n The dosing pump must be suitably packed, preferably in the
original
packing, for transportation. If the device is sent back to the manufacturer,
please follow chapters 17 ,,Declaration of no objection” on page 42 and 18
,,Warranty claim” on page 43.
11.8 Disposal of old equipment
n The waste unit must be thoroughly cleaned. Any dangerous dosing media must
be additionally neutralised and decontaminated.
n Any residual dosing media must be removed in a professional manner. n The
dosing pump must be disposed of in accordance with applicable
local laws and regulations. The device does not belong to household waste! n
As the disposal regulations may differ from country to country, please consult
your supplier if necessary. In Germany, the manufacturer must provide free-of-
charge disposal provided the unit has been sent in a safe manner.
11.5 Shutting down in an emergency
n In an emergency, you must immediately disconnect the dosing pump from the
mains supply or activate the Emergency Stop switch installed in the system.
n Depending on the type of incident, you must depressurized the
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Operation 33
Disposal of old equipment
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
12 Maintenance
Dosing pumps by Lutz-Jesco are manufactured to the highest quality standards
and have a long service life. Nevertheless, some of their parts are subject to
wear due to operation (e.g. diaphragms, valve seats, valve balls). This means
that regular visual inspections are necessary to ensure a long operating life.
Regular maintenance will protect the dosing pump from operation interruptions.
DANGER
Mortal danger from electric shock! Live parts can inflict fatal injuries. ð
Before carrying out any maintenance work, always disconnect the
dosing pump from the power supply. ð Secure the dosing pump from accidental
power-up.
WARNING
Caustic burns or other burns through dosing media! While working on the dosing
head, valves and connections, you may come into contact with dosing media. ð
Use sufficient personal protective equipment. ð Rinse the dosing pump with a
medium (e.g. water) which does not
pose any risk. ð Release pressure in hydraulic parts. ð Never look into open
ends of plugged pipelines and valves.
WARNING
Caustic burns or other burns through dosing media! After connecting the mains
supply, residual dosing media in the dosing head can spray out. ð Before
connecting the mains supply, connect the dosing lines. ð Check that all the
screw connections have been tightened
correctly and are leak-proof.
12.1 Maintenance intervals
This table gives you an overview of maintenance work and the intervals at
which you must carry it out. The next few sections contain instructions for
carrying out this work.
Maintenance work to be carried out
Frequency
Check that piping is seated firmly Regularly
Check that suction and discharge Regularly valves are seated firmly
Clean suction and discharge valves Regularly
Check that electrical connections Regularly are not damaged
Tighten up dosing head bolts
n Regularly n Before initial commissioning n After each diaphragm
change
Check diaphragm for leakage due Regularly (as long as no leak
to rupture
monitoring system is installed)
Check that the installed accesso- Regularly ries are functioning correctly
Check the dosing pump for unusual Regularly noises during operation, unusual temperatures or smells
Replace parts that are subject to wear (diaphragms, valves, seals, etc.)
When unacceptable levels of wear are detected
Rinse out and clean the dosing pump
Before changing diaphragms Before taking out of service for a long period of time After feeding aggressive, sticky, crystallising or contaminated liquids
CAUTION
Danger of personal injury and material damage! The dosing pump can generate a
pressure that is many times the rated one. The dosing medium can escape in the
case of material failure or wear on the dosing head, the connection pipe or
the seals that are used. ð Carry out maintenance work at the recommended
intervals.
Table 28: Maintenance information and maintenance intervals
12.2 Tighten up dosing head bolts è Tighten the dosing head bolts in
diagonally opposite sequence with a
torque wrench. The necessary torque is 180 Ncm.
34 Maintenance
Tighten up dosing head bolts
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
12.3 Change the diaphragm
a
b
c
d
e
i It may be necessary to gauge the delivery capacity after replacing the
diaphragm or other dosing pump spare parts.
12.4 Clean suction and discharge valves
Contaminated valves affect the dosing preceision and this means that you
should clean the valves on a regular basis. With dosing heads made of plastic,
when replacing a valve you must replace the complete dosing head (see chapter
14 ,,Spare parts” on page 39).
Fig. 33: Exploded view of the diaphragm and dosing head
12.3.1 Remove the old diaphragm
Precondition for action:
ü You have disconnected the dosing pump from the mains supply. ü You have
depressurised the hydraulic sections of the plant. ü You have rinsed the
dosing pump using a safe medium (e.g. water).
Perform the following working steps:
1. Screw out the four screws (5) on the dosing head using a suitable tool (SW
3 Allen key) and take off the dosing head (4).
2. Use pliers to bend the edge of the diaphragm (3) slightly upwards and
screw it out counter-clockwise.
12.3.2 Install a new diaphragm
Precondition for action:
ü You have thoroughly cleaned the diaphragm rod (2) and the
diaphragm flange (1) so that the new diaphragm is not affected by dosing
medium residues.
ü The diaphragm (3) thread was lightly greased (e.g. Molycote
Longterm W2).
1. Screw the diaphragm manually in the clockwise direction until it safely
contacts into the diaphragm rod.
2. Bring the dosing head into position and insert the screws. First tighten
the screws finger-tight. After this, tighten the bolts on the diagonal, e.g.
top left bottom right top right bottom left.
NOTE
Damage to the dosing head/diaphragm leaks
If you tighten the screws too much, this can lead to the dosing head being
damaged. However, not tightening the screws enough leads to the diaphragm
being leaky and correct functioning being affected. ð Tighten the screws to a
torque of 180 Ncm.
ü Diaphragm change finished.
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Maintenance 35
Clean suction and discharge valves
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
13 Troubleshooting
See below for information about how to rectify faults on the device or the
system. If you cannot eliminate the fault, please consult with the
manufacturer on further measures or return the dosing pump for repair.
13.1 Type of fault 13.1.1 Alarm LED illuminates (MEMDOS SMART LB)
Possible cause
Remedy
System backpressure too high (measured at discharge connection of dosing
pump).
Driving belt torn.
è Clean blocked injection nozzle.
è Install pulsation dampeners to reduce pressure peaks if pipes are too long.
è Check function of safety valves.
è Contact the manufacturer.
Table 29: Type of fault: Alarm LED illuminates (MEMDOS SMART LB)
13.1.2 Dosing pump not delivering or output too low
Possible cause Wrong type of dosing pump selected.
Valve leaking or blocked.
Valve installed incorrectly.
Remedy
è Check the dosing pump’s technical data and if necessary select a type with a
higher delivery capacity.
è Clean the valve and vent the dosing pump.
è Tighten the screw connections.
è Reassemble the valve. Ensure that the valve balls are located above the
valve seats.
Valve damaged (e.g. valve balls).
è Remove the damaged parts or install a new valve.
Suction line is leaking.
è Seal the leak locations or replace the parts.
Suction line is blocked (e.g. screen in foot valve).
è Clean the suction line.
Shut-off valves closed.
è Open the shut-off valves. Inspect the dosing pump for possible damage.
Suction head too high.
è Set the dosing pump to feed or reduce the suction head.
è Install a priming aid.
Table 30: Type of fault: Dosing pump not delivering or output too low
Possible cause Viscosity too high.
Current supply interrupted.
Remedy
è Possibly reduce the concentration of the dosing medium or increase the
temperature.
è Install spring-loaded valves. è Increase the pipe diameter.
è Reconnect the current supply.
The dosing pump’s electrical data does not match that of the mains supply.
System backpressure too high (measured at discharge connection of dosing
pump).
è Check the electrical installation.
è Clean blocked injection nozzle. è Install pulsation dampeners to
reduce pressure peaks if pipes are too long. è Check function of safety
valves.
Table 30: Type of fault: Dosing pump not delivering or output too low
13.1.3 Dosing pump does not prime
Possible cause Valve leaking or blocked.
Valve installed incorrectly.
Remedy
è Clean the valve and vent the dosing pump.
è Tighten the screw connections.
è Reassemble the valve. Ensure that the valve balls are located above the
valve seats.
Valve damaged (e.g. valve balls).
è Remove the damaged parts or install a new valve.
Suction line is leaking.
è Seal the leak locations or replace the parts.
Suction line is blocked (e.g. screen in foot valve).
è Clean the suction line.
Shut-off valves closed.
è Open the shut-off valves. Inspect the dosing pump for possible damage.
Suction head too high.
è Set the dosing pump to feed or reduce the suction head.
è Install a priming aid.
Table 31: Type of fault: Dosing pump does not prime
36 Troubleshooting
Type of fault
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
Possible cause Viscosity too high.
Current supply interrupted.
Remedy
è Possibly reduce the concentration of the dosing medium or increase the
temperature.
è Install spring-loaded valves. è Increase the pipe diameter.
è Reconnect the current supply.
Dry the valves.
è Dampen the dosing head and the valves
è Vent the dosing head.
Air in the suction line with
è Vent the dosing head or the lines.
simultaneous pressure on the
discharge valve.
Table 31: Type of fault: Dosing pump does not prime
13.1.4 Delivery rate varies
Possible cause Valve leaking or blocked.
Valve damaged (e.g. valve balls). Suction line is leaking.
Remedy
è Clean the valve and vent the dosing pump.
è Tighten the screw connections.
è Remove the damaged parts or install a new valve.
è Seal the leak locations or replace the parts.
Suction line is blocked (e.g. screen in foot valve).
è Clean the suction line.
Viscosity too high.
è Possibly reduce the concentration of the dosing medium or increase the
temperature.
è Install spring-loaded valves.
è Increase the pipe diameter.
The dosing pump’s electrical data does not match that of the mains supply.
è Check the electrical installation.
Suction side pressure too high è Install a back-pressure valve in
(pump siphoning).
the pressure line.
Pressure peaks due to
è Install a suction pressure
acceleration with long suction
regulator.
lines.
Table 32: Type of fault: Delivery rate varies
Possible cause
Imprecise dosing due to changeable positive and negative suction heads.
System backpressure too high (measured at discharge connection of dosing
pump).
Remedy
è Install a suction pressure regulator.
è Clean blocked injection nozzle. è Install pulsation dampeners to
reduce pressure peaks if pipes are too long. è Check function of safety
valves.
Table 32: Type of fault: Delivery rate varies
13.1.5 No stroke movement observed
Possible cause
Diaphragm return spring broken. Current supply interrupted.
Remedy è Contact the manufacturer.
è Reconnect the current supply.
The dosing pump’s electrical data does not match that of the mains supply.
è Check the electrical installation.
Pressure peaks due to
è Install a suction pressure
acceleration with long suction
regulator.
lines.
System backpressure too high (measured at discharge connection of dosing pump).
è Clean blocked injection nozzle.
è Install pulsation dampeners to reduce pressure peaks if pipes are too long.
è Check function of safety valves.
Table 33: Type of fault: No stroke movement observed
13.1.6 Dosing pump delivery rate too high
Possible cause
Remedy
Suction side pressure too high è Install a back-pressure valve in
(pump siphoning).
the pressure line.
Pressure peaks due to
è Install a suction pressure
acceleration with long suction
regulator.
lines.
Table 34: Type of fault: Dosing pump delivery rate too high
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Troubleshooting 37
Type of fault
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
13.1.7 Diaphragm is torn or tears too often
Possible cause
Remedy
Shut-off valves closed.
è Open the shut-off valves. Inspect the dosing pump for possible damage.
Pressure peaks due to
è Install a suction pressure
acceleration with long suction regulator.
lines.
The materials are not suitable è Check the resistance of the
for the dosing medium being
materials.
used.
Diaphragm not screwed up to è Screw a new diaphragm up to the
the end stop on the dia-
end stop.
phragm rod.
System backpressure too high (measured at discharge connection of dosing pump).
è Clean blocked injection nozzle.
è Install pulsation dampeners to reduce pressure peaks if pipes are too long.
è Check function of safety valves.
Media sediment in dosing head.
è Clean the dosing head.
Table 35: Type of fault: Diaphragm is torn or tears too often
Operating instructions
38 Troubleshooting
Type of fault
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
14 Spare parts
Operating instructions
b
c a
Fig. 34: Spare parts set for MEMDOS SMART LB / LD 2, 5, 10 (plastic dosing head)
a
b
c
Fig. 35: Spare parts set for MEMDOS SMART LB / LD 2, 5, 10 (stainless steel
dosing head (1.4571))
a b
d c
Fig. 36: Spare parts set for MEMDOS SMART LB / LD 15, 20, 30 (plastic or
stainless steel dosing head (1.4571))
Required sets for a complete service: n 1 diaphragm spare parts kit, n 1
dosing head spare parts set including valves.
14.1 Diaphragm spare parts kits
Diaphragm spare parts set containing:
n 1 Diaphragm (item 1) n 1 set of dosing head screws (item 3), n 1 set washers
(item 4) (only MEMDOS SMART LB / LD 15, 20, 30).
Diaphragm kit
Size 2 5, 10 15, 20, 30
Part No. 39122 39123 40607
14.2 Dosing head spare parts kits including valves
Spare parts set: dosing head including screws consisting of:
n Dosing head (item 2), n Valves, n 1 set of dosing head screws (item 3), n 1
set washers (item 4) (only MEMDOS SMART LB / LD 15, 20, 30).
PVC
Glass/PVDF/FPM (ball/seat/seals)
Size 2 5, 10 15, 20, 30
Part No. 41192 38983 40571
PP
Glass/PVDF/FPM (ball/seat/seals)
Size 2 5, 10 15, 20, 30
Part No. 41193 38980 40572
PVDF
PTFE/PVDF/FPM (ball/seat/seals)
Size 2 5, 10 15, 20, 30
Part No. 41194 38986 40573
Stainless steel (1.4571)
Stainless steel / stainless steel / FPM (ball/seat/seals)
Size 2 5, 10 15, 20, 30
Part No.
41195 39944 40574
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Spare parts 39
Dosing head spare parts kits including valves
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
15 Delivery characteristic curves
This Chapter is intended to give you an idea of the delivery capacity that the
dosing pump can achieve at specific back pressures. These delivery capacities
were determined on the manufacturer’s test stands. They apply at 20 °C (68 °F)
for water, at 100 % stroke frequency. The delivery capacity depends on the
medium (density and viscosity) and temperature. Since these conditions vary at
every installation location, you should calibrate the dosing pump.
35,00 l/h
30
30,00 l/h
Delivery capacity [l/h]
25,00 l/h 20,00 l/h 15,00 l/h 10,00 l/h
5,00 l/h
20
15 10 5
0,00 l/h 0 bar
5 bar
10 bar
15 bar
Fig. 37: Delivery characteristic curves MEMDOS SMART LB / LD 2 30
Operating instructions
2
20 bar
25 bar
Pressure [bar]
40 Delivery characteristic curves
Dosing head spare parts kits including valves
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
16 EC Declaration of Conformity
Operating instructions
(DE) EU-Konformitätserklärung Hiermit erklären wir, dass das nachfolgend
bezeichnete Gerät aufgrund seiner Konzipierung und Bauart sowie in der von uns
in Verkehr gebrachten Ausführung den einschlägigen grundlegenden Sicherheits-
und Gesundheitsanforderungen der aufgeführten EG-Richtlinien entspricht. Bei
einer nicht mit uns abgestimmten Änderung am Gerät verliert diese Erklärung
ihre Gültigkeit.
(EN) EC Declaration of Conformity We hereby certify that the device described
in the following complies with the relevant fundamental safety and sanitary
requirements and the listed EC regulations due to the concept and design of
the version sold by us. If the device is modified without our consent, this
declaration loses its validity.
(FR) Déclaration de conformité CE Nous déclarons sous notre propre
responsabilité que le produit ci-dessous mentionné répond aux exigences
essentielles de sécurité et de santé des directives CE énumérées aussi bien
sur le plan de sa conception et de son type de construction que du modèle que
nous avons mis en circulation. Cette déclaration perdra sa validité en cas
d’une modification effectuée sur le produit sans notre accord explicite.
(ES) Declaración de conformidad CE Por la presente declaramos que, dados la
concepción y los aspectos constructivos del modelo puesto por nosotros en
circulación, el aparato mencionado a continuación cumple con los requisitos
sanitarios y de seguridad vigentes de las directivas de la U.E. citadas a
continuación. Esta declaración será invalidad por cambios en el aparato
realizados sin nuestro consentimiento.
(NL) EU-overeenstemmingsverklaring Ondergetekende Lutz-Jesco GmbH, bevestigt,
dat het volgende genoemde apparaat in de door ons in de handel gebrachte
uitvoering voldoet aan de eis van, en in overeenstemming is met de EU-
richtlijnen, de EU-veiligheidsstandaard en de voor het product specifieke
standaard. Bij een niet met ons afgestemde verandering aan het apparaat
verliest deze verklaring haar geldigheid.
Bezeichnung des Gerätes: Description of the unit: Désignation du matériel:
Descripción de la mercancía: Omschrijving van het apparaat:
Typ: Type:
EU-Richtlinien: EC directives:
Harmonisierte Normen: Harmonized standards: Dokumentationsbevollmächtigter:
Authorized person for documentation:
Schrittmotor-Membrandosierpumpe Stepper Motor-driven Diaphragm Dosing Pump
Pompe doseuse à membrane entraînée par moteur pas à pas Bomba dosificadora de
membrana con motor paso a paso Stappenmotor-Membraandoseerpomp
MEMDOS SMART 2 30
2006/42/EG, 2014/30/EU Die Schutzziele der Niederspannungsrichtlinie
2014/35/EU wurden gemäß Anhang I, Nr. 1.5.1 der Maschinenrichtlinie 2006/42/EG
eingehalten. The protective aims of the Low Voltage Directive 2014/35/EU were
adhered to in accordance with Annex I, No. 1.5.1 of the Machinery Directive
2006/42/EC.
DIN EN ISO 12100:2011-03, DIN EN 809:2012-10, DIN EN 61000-6-2:2005, DIN EN
61000-6-3:2007 + A1:2011 Lutz-Jesco GmbH
Heinz Lutz Geschäftsführer / Chief Executive Officer Lutz-Jesco GmbH Wedemark, 01.08.2016
Lutz-Jesco GmbH Am Bostelberge 19 30900 Wedemark Germany
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
EC Declaration of Conformity 41
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
17 Declaration of no objection
Please copy the declaration, stick it to the outside of the packaging and
return it with the device.
Operating instructions
Declaration of no objection
Please fill out a separate form for each appliance!
We forward the following device for repairs: Device and device type: ………………………………………………………. Order No.:………………………………………………………………………….
Part-no.:……………………………………………………………………….. Date of delivery: ……………………………………………………………..
Reason for repair: ……………………………………………………………………………………………………………………………………………………………….. ………………………………………………………………………………………………………………………………………………………………………………………… …………………………………………………………………………………………………………………………………………………………………………………………
Dosing medium Description: ………………………………………………………………………. Properties: …………………………………………………………………………
Irritating: Corrosive:
Yes No Yes No
We hereby certify, that the product has been cleaned thoroughly inside and
outside before returning, that it is free from hazardous material (i.e.
chemical, biological, toxic, flammable, and radioactive material) and that the
lubricant has been drained.
If the manufacturer finds it necessary to carry out further cleaning work, we
accept the charge will be made to us.
We assure that the aforementioned information is correct and complete and that
the unit is dispatched according to the legal requirements.
Company / address:……………………………………………………………. ……………………………………………………………………………………….. ……………………………………………………………………………………….. Customer No.:…………………………………………………………………….
Phone:………………………………………………………………………….. Fax:……………………………………………………………………………… Email:…………………………………………………………………………… Contact person: ………………………………………………………………
Date, Signature:………………………………………………………………….
42 Declaration of no objection
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
18 Warranty claim
Operating instructions
Warranty claim
Please copy and send it back with the unit! If the device breaks down within
the period of warranty, please return it in a cleaned condition with the
complete warranty claim.
Sender Company: ………………………………………………………………………………………………… Phone: …………………………….
Date: …………………….. Address:
……………………………………………………………………………………………………………………………………………………………………………. Contact
person: …………………………………………………………………………………………………………………………………………………………………..
Manufacturer order no.: ……………………………………………………………………………… Date of
delivery:………………………………………………… Device type: ………………………………………………………………………………………………
Serial number: ………………………………………………….. Nominal capacity / nominal pressure:
……………………………………………………………………………………………………………………………………… Description of
fault:……………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
Service conditions of the device Point of use / system
designation:……………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
Accessories used (suction line
etc.):…………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………………………………………………………….
Commissioning (date):
………………………………………………………………………………………………………………………………………………………….. Duty period
(approx. operating hours):
……………………………………………………………………………………………………………………………………..
Please describe the specific installation and enclose a simple drawing or
picture of the chemical feed system, showing materials of construction,
diameters, lengths and heights of suction and discharge lines.
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Warranty claim 43
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
Operating instructions
19 Index
A
Accessories ………………………………………………………………………….21 Approved media temperature
…………………………………………………..14
B
Back-pressure valve ………………………………………………………………22
C
Cemented connection …………………………………………………………….20 Clean suction and discharge
valves ………………………………………….35 Commissioning the dosing pump ……………………………………………..30
Connection sockets ………………………………………………………………..25 Contact water meter
………………………………………………………………22 Control …………………………………………………………………………………27 Control
elements …………………………………………………………………..11 Conveying characteristics
……………………………………………………….12
D
Declaration of no objection ……………………………………………………..42 Decommissioning the
dosing pump ………………………………………….33 Delivery capacity data
…………………………………………………………….13 Delivery characteristic curves
………………………………………………….40 Design of the system ……………………………………………………………..18 Device
revision ……………………………………………………………………….8 Diaphragms
Replace …………………………………………………………………………..35 Spare parts set
…………………………………………………………………39 Dimensioned drawings …………………………………………………………..15
Dimensions …………………………………………………………………………..15 Disposal of old equipment
……………………………………………………….33 Dosing head Alignment ………………………………………………………………………..19
Design …………………………………………………………………………….10 Spare parts
………………………………………………………………………39 Dosing head venting facility
…………………………………………………….21 Dosing media Approved media temperature
……………………………………………..14 Prohibited dosing media ………………………………………………………8
E
Electrical installation ………………………………………………………………24 Electrical specifications
………………………………………………………….14 EU Declaration of Conformity …………………………………………………..41
External On / Off via Release input ……………………………………………33 External operation
………………………………………………………………….31
F
Foreseeable misuse …………………………………………………………………8 Function description
………………………………………………………………11
G
General warnings …………………………………………………………………….5 Glue-in connection
…………………………………………………………………20
H
Handling instructions Marking …………………………………………………………………………….4
Hazards due to non-compliance with the safety instructions …………..6 Hydraulic
accessories …………………………………………………………….21 Hydraulic connections
…………………………………………………………….19 Hydraulic installations …………………………………………………………….18
I
Injection nozzle ……………………………………………………………………..21 Inputs of the control unit
…………………………………………………………25 Installation ……………………………………………………………………………17
electrical …………………………………………………………………………24 hydraulic
…………………………………………………………………………18 Installing the Dosing Pump
……………………………………………………..17 Intended purpose …………………………………………………………………….8
Intended use …………………………………………………………………………..8 Internal operation
…………………………………………………………………..31
L
Leakage drain ……………………………………………………………………….21 Level input
Connection ………………………………………………………………………26 Level monitoring
……………………………………………………………………22
M
Maintenance …………………………………………………………………………34 Maintenance intervals
…………………………………………………………….34
N
Notes for the Reader ………………………………………………………………..4
O
Operating conditions and limits ………………………………………………..13 Operating modes (MEMDOS
SMART LD) ……………………………………31
Explanation of the icons ……………………………………………………..28 External operation
…………………………………………………………….31 Internal operation ……………………………………………………………..31
Operation ……………………………………………………………………………..30 Operation with contact-type water
meter …………………………………..32 Operator controls of the control unit Operator
controls of the control unit LB ………………………………..27 Operator controls of the
control unit LD ………………………………..27
P
Password protection ………………………………………………………………28 Personnel qualification
……………………………………………………………..6 Pressure-relief valve ………………………………………………………………22
Priming aid …………………………………………………………………………..22 Product description
………………………………………………………………..10 Product warranty …………………………………………………………………….8
Prohibited dosing media …………………………………………………………..8 Pulsation dampener
……………………………………………………………….22 Pulse input
Connection ………………………………………………………………………25
44 Index
BA-10110-02-V01
© Lutz-Jesco GmbH 2016
Stepper motor-driven diaphragm dosing pump MEMDOS SMART LB / LD
R
Rating plate ………………………………………………………………………….11 Release input
Connection ………………………………………………………………………25
S
Safety ……………………………………………………………………………………5 Scope of delivery
…………………………………………………………………..10 Setting the transmission and reduction
……………………………………..32 Set up information …………………………………………………………………17 Shutdown
…………………………………………………………………………….33 Shutting down in an emergency
……………………………………………….33 Signal words
Explanation ………………………………………………………………………..4 Spare parts
…………………………………………………………………………..39 Specialist staff
………………………………………………………………………..7 Start-up ……………………………………………………………………………….30
Storage ………………………………………………………………………………..33 Structure of the dosing pump
…………………………………………………..10 Suction pressure regulator ………………………………………………………23
Suspensions …………………………………………………………………………23 System piping
……………………………………………………………………….19
T
Technical data ………………………………………………………………………13 Temperatures
Approved ambient temperature …………………………………………..13 Approved media temperature
……………………………………………..14 Tighten up dosing head bolts …………………………………………………..34
Trained persons ………………………………………………………………………7 Transportation
……………………………………………………………………….33 Troubleshooting …………………………………………………………………….36
V
Venting ………………………………………………………………………………..30 Venting the dosing pump
………………………………………………………..30
W
Wall bracket …………………………………………………………………………17 Wall mounting
……………………………………………………………………….17 Warnings
General warnings ……………………………………………………………….5 Marking
…………………………………………………………………………….4 Warning sign Explanation
………………………………………………………………………..4 Warranty claim ……………………………………………………………………..43
Water meter ………………………………………………………………………….22 Working in a safety-conscious
manner ……………………………………….6
© Lutz-Jesco GmbH 2016 Subject to technical changes. 161020
BA-10110-02-V01
Operating instructions Index 45
Product Range
Lutz Pumpen GmbH P.O. Box 1462 · D-97864 Wertheim www.lutz-pumpen.com
Product Range
Lutz-Jesco GmbH P.O. Box 100164 · D-30891 Wedemark www.lutz-jesco.com
Barrel and Container Pumps
Dosing Pumps
Measuring and Control Equipment
Flow Meters
Chlorinators
Disinfection
Double Diaphragm Pumps
Chemical Centrifugal Pumps
Standard Plus
Centrifugal Pumps
Products for the disinfection of swimming pool water based on salt water electrolysis and domestic water technology
The Lutz-Jesco App for iPads and iPhones is available from the iTunes App Store. Additional information can be found at www.lutz-jesco.com
Headquarters Lutz-Jesco GmbH Am Bostelberge 19 30900 Wedemark Germany
Hungary Lutz-Jesco Üzletág Vasvári P. u. 9. 9024 Györ Hungary
Tel.: +49 5130 5802-0 Fax: +49 5130 580268
Tel.: +36 96 419813 Fax: +36 96 419814
E-mail: info@lutz-jesco.com E-mail: info@lutz-jesco.hu Website: www.lutz- jesco.de Website: www.lutz-jesco.hu
Austria Lutz-Jesco GmbH Aredstraße 7/2 2544 Leobersdorf Austria
Tel.: +43 2256 62180 Fax: +43 2256 6218062
E-mail: info@lutz-jesco.at Website: www.lutz-jesco.at
Netherlands Lutz-Jesco Nederland B.V. Nijverheidstraat 14 C 2984 AH Ridderkerk
Netherlands
Tel.: +31 180 499460 Fax: +31 180 497516
E-mail: info@lutz-jesco.nl Website: www.lutz-jesco.nl
Great Britiain Lutz-Jesco (GB) Ltd. Gateway Estate West Midlands Freeport Birmingham B26 3QD Great Britain
USA Lutz-JESCO America Corp. 55 Bermar Park Rochester, N.Y. 14624 USA
East Asia Lutz-Jesco East Asia Sdn Bhd 6 Jalan Saudagar U1/16 Hicom Glenmarie Industrial Park 40150 Shah Alam/ Selangor Malaysia
Middle East Lutz-Jesco Middle East FZE P.O. Box 9614 SAIF-Free Zone Center Sharjah UAE
Tel.: +44 121 782 2662 Fax: +44 121 782 2680
Tel.: +1 585 426-0990 Fax: +1 585 426-4025
Tel.: +603 55692322 Fax: +603 55691322
Tel.: +971 6 5572205 Fax: +971 6 5572230
E-mail: info@lutz-jesco.co.uk E-mail: mail@jescoamerica.com E-mail: info@lutz- jescoasia.com E-mail: info@jescome.com Website: www.lutz-jesco.co.uk Website: www.lutzjescoamerica.com Website: www.lutz-jescoasia.com Website: www.jescome.com
References
- Berechnungs-Assistent MEMDOS SMART LD- Dosierpumpen Chlorgas Dosierung Desinfektion Wasser Behandlung - Lutz-Jesco GmbH -
- manufacturer pumps | electric drum pumps, drum pump electric
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>