Style SELECTIONS LWD20232SSSS Sample Coir Vinyl Plank Instruction Manual
- June 3, 2024
- Style SELECTIONS
Table of Contents
Style SELECTIONS LWD20232SSSS Sample Coir Vinyl Plank
SUBSTRATE PREPARATION
Flatness:
Check all substrates for flatness prior to installation. The maximum
acceptable tolerance is < 1/8-in. gap (2 x US quarters) over 6-ft. and ≤
1/16-in. gap (1 x US quarter) over 1-ft. Make any necessary adjustments to the
substrate before installation. Dormant cracks, saw cut joints and grout lines
< 1/8-in. wide or deep are acceptable – all others must be cleaned of all dirt
and debris, then filled using a suitable commercial-grade patching or repair
compound, following the product instructions.
Concrete Substrates & Concrete Moisture:
All concrete must be free of contaminates and structurally sound. If required,
smooth the surface using a suitable, moisture-resistant commercial-grade
leveling or patching compound, following the product instructions. Do not
install if hydrostatic pressure is visible, present or suspected. If a
chemical adhesive remover has been used, contact the technical department. For
all on and below grade concrete slabs, test the surface to confirm it is
absorbent (porous), following the ASTM F3191 Standard Practice for Field
Determination of Substrate Water Absorption (Porosity) for Substrates to
Receive Resilient Flooring. The water droplets placed on the substrate must be
absorbed for it to be considered absorbent. If required, the concrete can be
made porous by mechanical methods, such as diamond grinding, a DiamaBrush
buffer attachment, shot blasting or similar. If the substrate cannot be made
porous and will not have a topical moisture mitigation system installed,
install a ≥ 6-mil thick polyethylene (PE) sheet, which is available at most
home improvement stores. Use sheeting that is ≤ 10-ft. wide to prevent
wrinkles and folds. Sheeting must be installed over the entire area and extend
at least 2-in. up the walls. All seams must be overlapped and sealed according
to the product instructions.
Wood Substrates:
All wooden subfloors and substrates must be dry and in compliance with the
moisture content percent (MC-%) for your region. Regional values are freely
available by searching “moisture map of wood” images. Test using a non-
destructive electronic moisture meter, following the product instructions. The
subfloor must comply with local building codes, have at least 18-in. of well-
ventilated air space below and have a suitable vapor retarder to isolate the
subfloor from ground cover and outdoor conditions. Wood subfloors must have a
total thickness of at least 1-in. Sleepers must not make direct contact with
concrete or earth. If necessary, install an underlayment grade plywood with a
minimum thickness of 1/4-in. on the surface. The underlayment must be
installed in the opposite direction to the subfloor, following ASTM F1482
Standard Practice for Installation and Preparation of Panel Type Underlayments
to Receive Resilient Flooring.
Note: plywood is a water-sensitive subfloor that may become damaged or
deformed by topical liquids. To protect wood subfloors from topical water
exposure, follow the Wet Area Guidelines below:
Radiant Heating Substrates:
When installing floor covering over a substrate that contains a radiant
heating system, ensure the radiant heat does not directly contact the floor
covering and is set at the correct “in-service” temperature for 48-hours
prior, during and after the installation. The radiant heat may be gradually
increased or decreased to maintain the correct “in-service” site conditions.
Note: Ensure the temperature of the radiant heating system does not
exceed 85°F (29°C).
Additional Acoustic Underlayments:
Additional acoustic underlayments are not recommended or required. However,
should one be used, ensure a polycarbonate chair mat is used in all rolling
chair areas. Do not use additional acoustic underlayments in any commercial
areas.
Unsuitable Substrates:
These include but are not limited to: any floating or loose floor coverings,
hardwood installed directly over concrete, carpet, cushion vinyl, rubber,
cork, foam, asphalt tile, any additional acoustic underlayment, any substrate
with visible mold, mildew, or fungi and any substrate in wet areas, such as
inside showers and saunas. Do not install directly over any adhesive or
adhesive residue of any kind. Do not install directly over radiant heating
elements/pipes or in recreation vehicles, campers or boats.
Other Subfloors/Substrates:
Installing over existing resilient vinyl flooring is not recommended. However,
it may be possible over some materials, such as hardwood flooring, VCT, VAT,
quartz tile, solid vinyl tile, sheet vinyl or linoleum, as well as existing
hard surface flooring substrates, such as terrazzo, porcelain or ceramic tile.
Ensure existing flooring is a single layer and is clean, dry, sound, solid and
well adhered. All loose material must be removed and repaired or replaced. All
grout lines and wide seams greater than 1/4-in. in width and/or depth, as well
as any significant substrate imperfections, must be filled and troweled flush
with a suitable cementitious patch.
Note: Existing hardwood floor coverings will swell when exposed to
moisture – vinyl floor covering may restrict the movement of moisture in
hardwood, which may result in flooring failure, especially when installed on
or below grade. Some hardwood floor coverings may also discolor vinyl floor
covering, which is excluded from warranty coverage. Electing to install over
any existing floor covering releases the manufacturer from any responsibility
regarding the suitability and continued performance of the product, including
any resulting effect on the new floor covering.
Wet Area Guidelines
Some subfloors and substrates, such as plywood, may be sensitive to and damaged or deformed by topical liquids, such as water, pet urine and spills. While StainMaster Pet Protect Interlocking Flooring is a waterproof product, water-sensitive subfloors may require additional protection to prevent water exposure. When installing floor covering in wet areas, ensure that bathmats or similar are used where appropriate to decrease the amount of water that can collect on the surface. Any and all spills should be cleaned up immediately after discovering them and within 8 hours. Subfloor flatness is critical to preventing water migration through seams that may flex or peak due to foot traffic and subfloor deflection – be sure to check flatness and make all necessary adjustments prior to installing. The water-sensitive substrate must have a ≥ 6-mil thick polyethylene (PE) sheet (available at Lowe’s) installed over the entire area and extend at least 2-in. up the walls. All seams must be overlapped and taped according to the product instructions. In addition, the area must be separated from all other rooms using a suitable water-resistant t-molding. Following flooring installation, the plastic sheet must be trimmed flush with the surface of the subfloor. Prior to installing wall-base or molding, the required perimeter expansion gap must be filled with a 100% silicone caulk, including the wet area side of all t-moldings. Additionally, all door jambs, plumbing and vertical surfaces that won’t have wall-base or molding installed must be sealed with 100% silicone caulk. Once the entire perimeter has been filled or sealed, water-resistant wall-base, moldings or other accessories may be installed. Apply a bead of silicone caulk to the parts of the wall-base or moldings that will make contact with the surface of the flooring. Ensure all wall base and moldings are attached to the subfloor, wall or wall-base without compression, to allow movement and cleanup any remaining silicone immediately. Do not anchor wall-base or moldings into or through the floor covering.
INSTALLATION INSTRUCTIONS
Expansion Gap:
If the length or width of the installation area is ≤ 50-ft., an expansion gap
of at least 1/4-in. must be created around the entire perimeter. If the
overall length or width is between 50 – 85-ft., then the gap must be increased
to 1/2-in. around the entire perimeter. A maximum of 85-ft. in length or width
must not be exceeded. If required, use a suitable trim molding covering the
edges by 1/8-in. and allowing a 1/2-in. expansion gap. For three-season
rooms, a gap of at least 1/2-in. around the entire perimeter is required. In
addition, the area must be separated from all other rooms using a suitable
trim molding. The maximum of 30-ft. in length or width must not be exceeded.
Note: Areas with very heavy furniture ≥ 800-lb. (363-kg) must be isolated
from the rest of the installation with a compatible t-molding and have ≥
1/2-in. expansion gap.
General Installation Preparation:
It is recommended that all wall-base be removed before flooring installation.
Alternately, a quarter round molding that covers both the required expansion
gap and at least 1/8-in. of the floor covering (attached to the wall or
wallbase only) may be installed. Undercut all wooden door jambs and the first
inch of any remaining wall-base (which will be covered with molding) with an
Oscillating Multi-Tool or hand saw – the height must be the thickness of the
floor covering plus 1/64-in., which allows the floor covering to expand and
contract freely, out of sight, with temperature fluctuations. Steel door jambs
should be pattern-scribed, leaving the required expansion gap. Use a color-
coordinated 100% silicone to fill the void. Clean the entire area to be
installed using a HEPA-filtered vacuum. Before beginning, check and make sure
the lot numbers on the packaging match and mix the floor covering from several
boxes to ensure a random appearance. During the installation, inspect for
visible defects, including any damage, gloss, color or shade variations, dirt
and debris in the locking mechanism (remove using a soft brush), as installing
it assumes full responsibility. If you have any concerns, do not install and
immediately contact the technical department.
Layout:
Follow the design or drawings provided or agreed upon by the designer,
architect, or end-user. The end joint layout for all planks should be random –
make sure joints are not “stair stepped”. Failure to randomize end joints
could weaken the integrity of the joint system, which may lead to failure. All
planks must be at least 8-in. in length and all end seams must staggered by ≥
8-in. Tiles must be installed in a brick-bond pattern, offset by 1/2 or 1/3 of
the plank.
Cutting:
To cut the floor covering, measure and mark the surface with a pencil, then
carefully score the surface a few times on the mark using a sharp utility
knife along the side of a speed square. Snap the plank downwards and complete
by cutting the backing from underneath. For complicated cuts, such as door
jambs, it is recommended to use a jigsaw with a carbide blade following the
product safety instructions.
Installation:
Clean the entire area to be installed twice using a HEPA-filtered vacuum.
Determine the best wall to start installation on – typically this would be the
longest straight wall with a doorway (if present). Measure the width of the
room and, allowing for two expansion gaps, calculate the width of your last
row. If it is less than half the width of the floor covering, or if a balanced
design is required, than reduce the width of the first row accordingly. Use a
chalk-line to mark the outside edge of the first row on the substrate. If
needed, trim the first row (the side without the extended locking mechanism)
to fit, accounting for the expansion gap.
First Row (Slide):
At the left corner of the starting wall, position the first tile or plank
flush with the walls. Use the side and end without the extended locking
mechanism against the walls. Place wedge spacers between the floor covering
and wall to maintain the required expansion gap around the entire perimeter
(see figure 4). Before connecting the second piece, lay it flat on the
substrate, adjacent to the first row and lined up with the end of the previous
piece. Then, while keeping the joint perfectly in line, slide the second plank
into the first, locking the mechanism together (see figure 5). Complete the
first row using this method. If there is a doorway, measure, mark and cut the
flooring to make sure the cut edge will be located underneath the door jamb
and frame while maintaining the required expansion gap. A jigsaw should be
used for complicated cuts like these. Keeping the installation straight is
critical, so check the first row using a chalk line or similar and, as needed,
adjust and reinforce the row by adding more wedge spacers. The acceptable
straightness tolerance is within 1/16-in. for lengths over 20-ft. or 1/32 in.
for lengths under 20-ft. Complete the following rows starting with a cut
piece, such as a piece from a previous row. Install the side joints before the
end joints as instructed under “Side Joints” and “End Joints”.
Side Joints (Angle-Angle):
Starting at the left corner, place the side without the extended locking
mechanism into the side of the previously installed row at a ~ 25° angle. Make
sure the joint is seated properly, then slide the plank or tile into position.
The end joint must line up perfectly. Lay the tile or plank flat and complete
the end joint.
End Joints (Drop-Lock):
Always check the alignment of the end joint and adjust if necessary. Lock the
joint into place by lightly tap along the high side, starting from the “T”,
using a 2-lb. (~ 32-oz.) soft faced dead blow hammer or rubber mallet. Keep
the striking head flat with the floor covering and tap until perfectly flush.
If the locking mechanism does not line up properly, then check and adjust the
straightness as necessary.
Pro-Tips:
Do not hit the locking mechanism directly with any hammer, tapping block or
pull bar (except the last row) – doing so will damage the locking mechanism
and may result in peaking, gapping or broken joints. If required, use a ~
6-in. piece of scrap floor covering, seated in the locking mechanism, to
lightly tap and close any joints. If you need to install small cuts of floor
covering that are < 3-in. in length or width, place a thin bead of liquid
superglue on the previously installed locking mechanism just before
installing. This will ensure the pieces remain locked together during use. Do
not get the adhesive on the surface – coverage will be ~ 30 ft. per oz. After
the first five or six rows are completed, turn around and continue installing,
working on top of the installed material. This will allow the side joints to
be pulled together rather than pushed together, which will make the
installation even easier. If you need to disengage the end joints for any
reason, first unlock the side joints by lifting the outside edge of the row to
~ 25° and disconnect the entire row. Make sure all pieces are lying flat and
are properly engaged (tap to engage, if required), then simply slide them
apart. If they are angled or pulled upwards, the joint will break.
Completion:
If used, plastic sheeting must be trimmed flush with the surface of the floor
covering. If installed in a wet area, plastic sheeting must be trimmed flush
with the subfloor. When installing in wet areas, ensure the expansion gap and
all vertical surfaces are filled or sealed with a 100% silicone caulk and
ensure all wall-base and moldings are water-resistant, following to the Wet
Area Guidelines. Install all necessary wall-base and/or moldings and ensure
they are anchored to the substrate, wall or wall-base without compression, to
allow movement. Do not anchor wall-base or moldings into or through the floor
covering.
Protection
If required, protect the clean floor covering from other trades or heavy loads using ½-in. plywood or similar and tape all seams. For light traffic, use Ram board or similar and tape all seams. For furniture, use only polyurethane, silicon or felt glides (replaced > 3-times a year), keeping them clean and grit-free – all glides should be ≥ 1-in.2, especially on heavy furniture. Use protective polycarbonate chair mats designed for resilient flooring underneath rolling chairs or soft “W-type” wheels. Use non-rubber-backed entrance matting at all outdoor entrances, as this will improve air quality and reduce maintenance. Do not drag heavy or sharp objects directly across the surface – use hard surface “sliders” (available at Lowe’s). For areas that may be subjected to standing water on the surface, such as bathrooms with a bath or shower, the perimeter of the installation must be properly sealed using a 100% silicon caulk to prevent water from getting beneath the flooring. To avoid excessive fading or discoloration from direct sunlight exposure, use appropriate window treatments, an effective UV/IR film or Low-E glass windows. Take photographs and have any required documentation signed and filed following completion.
Questions, problems, missing parts? Before returning to your retailer, call our customer service department at 1-888-509-3438, 8:00 am – 5:00 pm, EST, Monday – Friday. You may also contact us anytime at customerservice@novalis- intl.com.