AEG AS-BBH1 High Voltage Battery Installation Guide
- July 17, 2024
- AEG
Table of Contents
- AEG AS-BBH1 High Voltage Battery
- Product Usage Instructions
- PRELIMINARY REMARKS
- Product Identification
- SAFETY
- Installation safety
- Maintenance safety
- PRODUCT OVERVIEW
- Product appearance
- Technical data
- Operating data
- INSTALLATION
- LED INDICATOR DESCRIPTION
- TROUBLESHOOTING GUIDELINE
- References
- Read User Manual Online (PDF format)
- Download This Manual (PDF format)
AEG AS-BBH1 High Voltage Battery
Specifications
- Product Name: AEG HIGH VOLTAGE BATTERY
- Model: AS-BBH1-10000/HV, AS-BBH1-15000/HV
- Nominal Energy: 10 kWh / 15 kWh
- Capacity: 40 Ah
- Nominal Voltage: 268.8VDC
- Usable Energy: 9 kWh
- Charge/Discharge Current (Nominal): 20A/20A
- Protective Class: Class I
- IP Rating: IP54
- Operating Temperature: -10°C to +50°C
Product Usage Instructions
Safety
Ensure that you follow all safety guidelines provided in the manual to
prevent any potential hazards during installation and operation.
Installation
Follow these teps for the installation of the AEG High Voltage Battery
- Use the recommended installation tools and materials.
- Refer to wire specifications for proper connections.
- Unbox the battery carefully.
- Select a suitable installation site following the guidelines.
- Complete both mechanical and electrical installation as per instructions.
LED Indicator Description
Understand the LED indicator lights to monitor the status of the battery
during operation.
Troubleshooting Guideline
Refer to the troubleshooting section in case of any issues with the battery
performance. Follow the guidelines provided to diagnose and resolve common
problems.
FAQ
-
Q: Can the AEG High Voltage Battery be installed by non-professionals?
- A: No, the AEG High Voltage Battery should only be installed by qualified professional companies to ensure proper setup and safety.
-
Q: What should I do if I encounter an emergency situation during battery operation?
- A: Refer to the “Response to emergency situations” section in the manual for guidance on handling emergency scenarios.
-
Q: What is the warranty period for the AEG High Voltage Battery?
- A: Please refer to the warranty information provided by AEG for details on the warranty period and coverage.
AEG HIGH VOLTAGE BATTERY
INSTALLATION MANUAL
VERSION: PD202407 V1-24
AEG HIGH VOLTAGE BATTERY SERIES: AS-BBH1
AS-BBH1-10000/HV
AS-BBH1-15000/HV
AEG HIGH VOLTAGE BATTERY (10 KWH / 15 KWH) INSTALLATION MANUAL
AEG HIGH VOLTAGE BATTERY
INSTALLATION MANUAL
Thank you for choosing the reliability of AEG high voltage batteries.
- This installation manual is intended for dealers and installers involved in the planning, installation and commissioning of photovoltaic systems deploying AEG high voltage batteries. These instructions provide you with valuable information to ensure that your battery runs smoothly over its whole lifecycle.
- AEG high voltage batteries are tested and approved by acknowledged independent certification authorities and can only be installed by qualified professional companies.
- Please observe the standards and regulations applying to photovoltaic systems in the relevant countries, as well as the rules of the employers’ liability insurance associations for accident protection. Failure to comply with these can result in major injuries and damage.
- The information provided in this manual is accurate at the time of publication; however, Solar Solutions reserves the right to make changes to product design and technical specification updates at any time without prior notice. Illustrations in this manual are meant
- to help explain system configuration concepts and installation instructions. The illustrated items may differ from the actual items at the installation location.
- Keep this guide in a safe place for further reference as it contains important information for product care, maintenance and disposal.
PRELIMINARY REMARKS
Icons
This section describes relevant warning symbols recurring in the installation
and operation manual of AEG high voltage batteries. Icons highlight relevant
information for the physical and property safety of the user. Compliance to
the provided instructions is essential to prevent physical injury and product
damage. Below is a list of the icons used in this manual:
Table 1: Icon meaning
Product Identification
High Voltage Battery
Each High Voltage Battery can be identified by means of the following
information:
Serial Number
Each battery is identified by a unique serial number univocally coupled with a
barcode, to be found on the housing.
Product Label
The product label of the battery pack is placed on
the housing. It provides information about the main parameters of the device
such as: Product Name
Code (PNC), Battery Type, Capacity, Nominal Voltage and Nominal Energy,
Charge, and further operation parameters.
PRODUCT NAME CODE: AS-BBH1-10000/HV| Solar Solutions BV Finlandlaan 1
2391PV Hazerswoude-Dorp The Netherlands
www.aeg-solar.com info@aeg- solar.com
AEG is a registered trademark used under license from
AB Electrolux (pub). Product assembled in P.R.C.
---|---
Li-ion Battery Pack| Rechargeable Li-ion
Capacity: 40 Ah| Nominal voltage: 268.8VDC
Nominal energy: 10kWh| Usable energy: 9 kWh
Charge/discharge current (nominal): 20A/20A
Operating temperature range: -10~50°C
Protective Class: Class I
IP54| | IFpR/41/136/[2P84S]M/-10+50/NA
| | |
Label example
Explanation of icons on product label
Explanation of icons on battery label
Please refer to the specific product datasheet on www.aeg- solar.com for the latest technical data.
SAFETY
General safety
- All AEG high voltage batteries are tested according to international safety regulations.
- AEG high voltage batteries should be installed, maintained, connected and operated by qualified technicians in compliance with all local and national applicable standards, codes and regulations issued by the relevant power suppliers, companies and authorities. Installers bear the risk of all injury that might occur during installation including, without
- limitation, the risk of electric shock. Check and follow all safety precautions specified even for the other components of the system. Keep children away from the installation site and during transportation, installation and maintenance of the electrical equipment.
Handling safety
- Please observe the following indications when handling the AEG high voltage battery.
- Look for any visible damage to the package or the product itself. Double-check the order information and the product nameplate to ensure the products are of the ordered type.
- Check that the package contents are not damaged and that all items listed are present (see 4.5 „Unboxing and package content“). Should you find any issues, contact the shipping company and or your supplier as soon as possible before attempting product installation.
Take note of the indications displayed on the product packaging. Specifically
Packaging icon meaning
-
Please make sure that the high voltage battery and its components are properly packed and sealed to ensure safe transportation. Ensure that the battery pack is stored in a dry, clean place and not exposed to water or dust.
-
The battery pack is heavy. Handle it carefully in order to avoid injuries. At least two people are required to move and install the battery pack.
To ensure handling, installation and maintenance safety, and to avoid personal injuries, please adopt mechanical protective measures such as wearing protective shoes and work clothes. -
****To avoid electric shock, remove metallic rings, watchbands, ear, nose or lip rings or other metallic devices during installation, connection and maintenance of the high voltage battery.
Handling the battery pack
- ****Handle the battery pack carefully as it may leak corrosive electrolyte.
- To avoid the risk of explosion of the battery pack, make sure to observe the following:
- Do not make the battery pack undergo strong impacts. Do not crush or puncture the battery pack.
- Do not dispose of the battery pack in a fire.
- To avoid fire risks to the battery pack, please make sure to observe the following:
- Do not expose the battery pack to temperatures that exceed 60°C.
- Do not place the battery pack near a heat source, such as a fireplace.
- Do not expose the battery pack to direct sunlight.
- Do not allow the battery connectors to touch conductive objects such as wires.
- To avoid the risk of the electric shock from the battery pack, please make sure to observe the following handling instructions:
- Do not disassemble the battery pack.
- Do not touch the battery pack with wet hands.
- Do not expose the battery pack to moisture or liquids. Keep the battery pack away from children and animals.
- To avoid damaging the battery pack, please make sure to also observe the following handling instructions:
- Do not allow the battery pack to come in contact with liquids.
- Do not expose the battery pack to high pressures or strong forces.
- Do not place any objects on top of the battery pack. Do not pull or drag the battery pack, nor step on it.
Installation safety
Installing solar photovoltaic systems and batteries requires specialized skills and knowledge and can only be performed by qualified technicians (see 2.1 General safety). All electric installations need to comply with the national and local laws and standards.
-
Use the AEG high voltage battery pack only for the intended purpose in combination with the suitable AEG hybrid inverter.
-
For installation, choose a location out of the reach of children or public access. Keep the battery pack away from the reach of children.
-
Ensure you are completely familiar with the indications provided the instructions manual before attempting installation.
-
****Do not use the battery pack if it is defective, if it appears to be cracked, broken or otherwise damaged, or if it fails to operate.
-
Handling or changing components without following the instructions in this manual may cause personal injury, cause product damage, and ultimately void the warranty.
-
****Do not attempt to open, disassemble, repair, or modify the battery pack. The battery pack can only be repaired by AEG service personnel.
-
Use only installation equipment suitable for a solar electric installation.
-
Only use original parts and components.
Handle with care to avoid damages to the battery pack and its components during transportation. -
****Installers and operators should carefully follow the instructions in this manual when handling the high voltage battery and avoid hazardous actions that might result in life-threatening situations.
-
It is important to ensure proper grounding according to local requirements.
-
****Do not install the battery pack on or close to flammable or explosive materials.
-
Do not insert any foreign objects into any part of the battery pack
-
Do not use cleaning solvents to clean the battery pack.
Grid-tied operation safety
Only qualified electricians are allowed to operate the high voltage battery
under the permission of local energy authorities.
- All electrical connections must meet the electrical standards of the country/region in which the installation is located.
- Ensure reliable installation and electrical connection before operation.
- Make sure that the battery polarity is connected correctly.
- Do not open the high voltage battery cover.
Maintenance safety
- Only qualified professionals are allowed to carry out maintenance, inspection and refitting of the AEG high voltage battery. If your AEG high voltage battery requires maintenance, please contact your supplier.
- Ensure that unauthorized people do not access the maintenance area during maintenance operations.
- ****Before attempting maintenance, disconnect first 10min all power supplies from the grid to the energy storage system. Disconnect the breakers. Wait at least 5 minutes until the internal parts of the system are discharged.
- ****Please follow the electrostatic protection norms, and take correct protective measures as there are electrostatic sensitive circuits and devices in the system. Appropriate protective measures are meant to prevent damages to the product and personal injury.
- ****Only use original parts and components. Do not refit the energy storage system unless authorized.
- ****Do not get near to / touch any metal conductive part of the grid or of the high voltage battery, otherwise electric shock, physical injury, death or fire may occur. Always pay attention to warning icons and instructions signaling the possibility of electric shock.
- Do not use cleaning solvents to clean the battery pack.
Response to emergency situations
The battery pack is designed to prevent hazards resulting from failures.
However, Solar Solutions cannot guarantee for its absolute safety.
- ****If the battery pack leaks electrolyte, avoid contact with the leaking liquid or gas. Electrolyte is corrosive and contact with it may cause skin irritation and chemical burns. situations resulting from exposure to electrolyte, please take the suggested take promptly:
- Inhalation : evacuate the contaminated area, and immediately seek medical attention.
- Eye contact : rinse the eyes with flowing water for 15 minutes, and immediately seek medical attention.
- Skin contact : wash the affected area thoroughly with soap and water, and seek immediately medical attention.
- Ingestion : induce vomiting, and seek immediately medical attention
- Fire: in case of fire, always have an ABC or carbon dioxide extinguisher at hand.
- The battery pack may catch fire if heated above 150°C. If a fire breaks out when the battery pack is installed, proceed with the following actions
- Extinguish the fire before the battery pack catches fire.
- If it is impossible to extinguish the fire but you still have time, move the battery pack to a safe area before it catches fire.
- If the battery pack has caught fire, do not try to extinguish the fire. Evacuate people immediately.
- If the battery catches fire, it will produce noxious and poisonous gases. Do not get close to it.
- Wet battery : if the battery pack is wet or submerged in water, do not try to get close to it. Contact your installer/ dealer for technical assistance.
- Damaged battery: damaged batteries are dangerous and must be handled with extreme caution. They are not fit for use and may pose a danger to people or property.
- If the battery pack seems to be damaged, pack it in its original container, and then return it to your installer or distributor.
- ****Damaged batteries may leak electrolyte or produce flammable gas. If you suspect such damage, immediately contact your installer/ dealer for advice and information.
PRODUCT OVERVIEW
General remarks
The AEG high voltage battery AS-BBH1-xxx-/HV (xxx= 10000 or 15000) is a
lithium battery product with BMS (Battery Management System) developed for use
with photovoltaic installations.
Characterized by high energy density and reliability, the battery pack‘s safety is granted among others by relevant protection functions such as under- voltage, over-voltage, over-current, over-temperature, under-temperature protection. The battery pack further supports CAN communication and features a WiFi connection module The number of battery units can be expanded (with the use of a Control Box AEG AS-BAC1-4W/HV).
The AEG high voltage battery can be deployed in back-up power systems, micro- grids and home energy storage systems.
Product appearance
High voltage battery
Item| Description| Size|
---|---|---|---
| | AS-BBH1-10000/HV| AS-BBH1-15000/HV
1| Width| 654 mm
2| Depth| 227 mm
3| Height| 971 mm| 1205 mm
4| Weight| 105 kg| 143 kg
---|---|---|---
Wiring port
The wiring port can be seen in detail after opening the cover plate.
Item. | Description |
---|---|
1 | CAN 1 port, 2 pcs, for external communication (inverter) |
2 | CAN 2 port, 2 pcs, for external communication (BMS) |
3 | Battery + / positive battery pole |
4 | Battery – / negative battery pole |
CAN communication interface (CAN1 & CAN2)
Below is the scheme of the CAN communication interface.
CAN1 port (for inverter communication)
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
---|---|---|---|---|---|---|---|
— | — | — | CAN1H | CAN1L | — | — | — |
CAN2 port (for battery communication)
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
---|---|---|---|---|---|---|---|
485A | 485B | GND | CAN1H | CAN1L | +12V | CAN2H | CAN2L |
Technical data
Technical data of battery module
Electrical characteristics
Model: AS-BBH1-xxx/HV xxx=| 10000| 15000
Battery type| | LFP
Total energy capacity| [kWh]| 10| 15
Usable energy capacity| [kWh]| 9| 13.5
Battery capacity| [Ah]| 40| 40
Voltage range / usable..v.r.| [V]| 235.2~294| 336~420
Nominal voltage| [V]| 268.8| 384
Charge voltage| [V]| 294| 420
Disharge cut-off voltage| [V]| 235.2| 360
Charge/Discharge Current (Nominal)| [A]| 20/20
---|---|---
Charge/Discharge Current (Max)| [A]| 40/40
Max. continuous discharge current| [A]| 50
DOD| | 90%
Cycle life at 25°C (under standard charge conditions, charge 0.2°C, discharge
0.2°C| | ≥6000
DC disconnect| | Contactor Fuse
Number of expandable battery units| [pcs]| max. 10
Warranties
- For the latest warranties please refer to:
- https://aeg-solar.com/service/downloads/
Operating data
BMS (Battery Management System)
Power consumption (work) | [mA] | ≤100 |
---|---|---|
Power consumption (sleep) | [mA] | ≤0.1 |
Communication | CAN | |
Monitoring parameters | System voltage, system current, cell voltage, cell |
temperature
Operating conditions
Installation Location | Indoor conditioned | |
---|---|---|
Operating Temperature | [°C] | -10~50 |
Operating Temperature (Recommended) | [°C] | 15~30 |
Storage Temperature | [°C] | -30 ~60 |
Humidity | [%] | 5~95 |
Altitude | [m] | Max. 2000 |
Cooling | Natural convection |
Reliability and certification
Certificates (cell) | UL1642 |
---|---|
Certificates (battery module) | IEC62619 / UL1973 / UL9540A |
Transportation | UN38.3 |
Ingress rating | IP54 |
INSTALLATION
Installation tools and materials
Please ensure you have the following items at hand before beginning the
installation of the AEG high voltage battery:
Use properly insulated tools to prevent accidental electric shock or short circuits.
The below installation material should be arranged by the installer for the installation of the battery pack
- Charging cables
- Network cable
- DC breaker
Wire specifications
In order to standardize the wiring specifications of
the AEG high voltage battery AS-BBH1-xxx/HV (xxx= 10000 and 15000) please make
sure to follow the below requirements for the connecting wires:
Battery cable | Communication cable |
---|
Recommended:
8 AWG / 10mm² conductor with double insulation
| Recommended: standard communication cable with shielding function
Unboxing
- Due to its weight, the AEG high voltage battery needs to be handled by two or more people.
- Before installing the product, please carry out a first check of the package and the package content as described in 2.2 „Handling safety“.
- Below is a sketch of the packing box of the AEG high voltage battery.
Step 1 : Open the packing box, take out the wall bracket and remove the EPE plate .
Item. | Description |
---|---|
1 | EPE plate |
2 | Wall bracket |
3 | AEG high voltage battery |
Step 2 : Pull out the battery pack and stand it upright. Check if the
battery pack is damaged.
Step 3: All the other items are contained in a box in one corner of the
carton. Take them out and check if any item is missing. Keep the carton for
future storage or transportation.
Battery pack package content
The package content of the AEG battery pack includes the following items. If
any item is missing, please contact your AEG distributor.
Item | Name | Qty. |
---|---|---|
1 | Battery pack AS-BBH1-10000/HV or AS-BBH1-15000/HV (according to your | |
order) | 1 | |
2 | PE wire | 1 |
3 | Allen wrench (M2.5) | 1 |
4 | M4 socket head combination screws | 4 |
5 | M6 Phillips head three combination screw | 10 |
6 | M8 expansion screw combination | 8 |
7 | Wall bracket | 1 |
8 | CAN communication wire | 1 |
9 | User manual | 1 |
Choosing the installation site
Note: For specific requirements such as the narrowest maintenance
channel, escape route, etc., please refer to the applicable standards of the
country/ region where the project is located.
Please make sure that the installation location meets the following requirements
- The installation site should be well ventilated and sheltered from direct sunlight, rain and snow;
- The building is designed to withstand earthquakes
- The location should not be in proximity of the sea, to avoid salt water and humidity.
- Ensure there are no corrosive gases at the installation site, including ammonia and acid vapor.
- Ensure there are no flammable or explosive materials at the installation site or nearby.
- The floor of the installation site must be dry and flat. Under no circumstance there should be water on the ground in proximity of the energy storage system. Ensure that the ground level is levelled and can fully carry the weight of the high voltage battery.
- The installation site should be clean.
- Ensure enough clear space to provide space for installation, maintenance, and safe escape.
Note: If the ambient temperature is out side of the operating range, the battery pack will go in self-protection mode and stop operating. The optimal temperature range for the battery pack to operate is between 15°C and 30°C degrees. Frequent exposure to harsh temperatures may deteriorate the performance and lifetime of the battery pack. For this reason, it is recommended that temperature and humidity stay at a constant level.
The AEG high voltage battery should be installed against a wall.
Mechanical and electrical installation
Step 1 – Unboxing: Unbox the AEG high voltage battery, put it upright and
check for any damage before proceeding to installation (see 2.2 „Handling
safety“ and 4.4 „Unboxing“).
Step 2-Drilling, Fixing : install the AEG high voltage battery against
the wall. Eight holes should be drilled on the wall in order to fix the racks
of the battery module. Please see below picture for details:
AS-BBH1-10000/HV
Item | Distance (mm) |
---|---|
1 | 562 |
2 | 116 |
3 | 298 |
4 | 116 |
5 | 60 |
AS-BBH1-15000/HV
Item | Distance (mm) |
---|---|
1 | 796 |
2 | 116 |
3 | 298 |
4 | 116 |
5 | 60 |
Step 3 -WiFi installation (if applicable): Insert the WiFi module according to the system configuration: single battery unit or battery units connected in parallel, for details see below:
Single battery unit
The Wi-Fi module should be connected to the CAN2 port of battery with Wi-Fi
cable. Please see the below figure for details.
Item | Remark |
---|---|
1 | WiFi installation position |
Battery units connected in parallel
You only need to install 1 Wi-Fi module on the Control Box AEG AS-BAC1-4W/HV.
Please see the below figure for details.
Item | Remark |
---|---|
1 | WiFi installation position |
Remarks: You can find the user manual of the WiFi module in the WiFi packing box. In pure off-grid case when the first installation is completed, if there is no PV power, long press the battery main switch to start the system.
Step 4 – Connecting the inverter: Connect the inverter and battery module with the communication and battery cable. Turn on the breaker placed on the right side of the AEG high voltage battery. Please refer to the below figure for details.
Item. | Description |
---|---|
1 | Details |
2 | CAN1 |
3 | Black start |
4 | Breaker |
CAN1 is connected to inverter for communication. The AEG high voltage battery can only operate after receiving the inverter’s communication instructions. After the system is powered on, you need to select the battery communication protocol on the inverter, so that the system can run normally.
In pure off-grid case when the first installation is completed, if there is no PV power, long press the battery black start switch to start the system.
Step 5 – Electrical connection of the battery pack
For connection of a single battery pack
Item. | Description |
---|---|
1 | Battery pack |
2 | Breaker |
3 | Inverter |
--- | --- |
For connection of multiple battery packs in parallel:
Item. | Description |
---|---|
1,2,3,4 | Battery pack |
5 | HV Pack Control Box |
6 | Breaker |
7 | Inverter |
Remarks: Technically it is possible to setup battery packs up to 4 units but it is possible to upgrade it till 10 units. Please contact www.solarsolutions.ag
Step 6- DOD setting of the inverter To make sure the battery working smoothly, we recommend the DOD set-ting of inverter as follows.
On-grid DOD: 80%
Off-grid DOD: 70%
LED INDICATOR DESCRIPTION
Item | Colour | Description |
---|---|---|
1 | Red | Battery is on black start mode. To active battery black start mode, |
please press the black start button and hold for 10 seconds. Battery can power
the inverter and active the communication with inverter if there is no power
grid or solar panels.
2| Purple| Battery has lost communication with inverter for over 5 minutes
3| Yellow| Battery is on protection model. The battery reached to the 3rd
level protection alarm such as over voltage, under voltage, over temperature,
low temperature.
4| White| Battery is on working model. If there are more than one battery in
parallel connection, it means this battery is the master battery on working
model.
5| Green| Battery is on working model as a slave battery in parallel
connection.
TROUBLESHOOTING GUIDELINE
Led indicator | Possible root cause | How to target the root cause | Solution |
---|---|---|---|
Led is purple |
- Compatible inverter firmware is not the latest revision.
- Battery firmware is not the latest reversion.
- Installer didn’t choose AEG battery correctly on inverter app or LCD/LED.
- Communication cable is loose or not correct.
- Inverter hardware fault.
- Battery hardware fault
| Please check the inverter APP or LCD/ LED for firmware reversion.
Please check the AEG smart energy cloud for firmware reversion.
Please check if the selection of battery is correct or not.
Please check the communication cable status
Please change another inverter to try If you checked all the items above and still can’t target the reason, please contact with AEG or change the
battery.
| Update inverter firmware.
Update battery’s firmware.
Reselect AEG battery on inverter.
Replug or change the cable. Contact Inverter supplier.
Contact AEG for further action.
N/A(Battery can’t be charged or discharged)|
- Inverter setting incorrect such as disable the charging or discharging, and time setting, etc.
- Inverter can’t read AEG battery type correctly.
- Inverter hardware fault.
- Battery hardware fault.
| Check the inverter setting.
Please check the battery type of product and product name shown in inverter side.
Please change another inverter to try. Please change another battery to try.
| Change the inverter setting.
Contact with Inverter manufacture or AEG for further action.
Contact with Inverter manufacture. Contact with AEG for further action
Led is off or yellow|
- Off-grid installation, battery can’t be charged for over 2 weeks due to no production of PV system(raining season snow season, or PV system fault).
- Customer didn’t turn off the battery for over 2 weeks in the scenario such as:
- Installation is not finished.
- System failure, not running.
- The battery was stocked for over 2 years without charging.
| Check the battery voltage through the reserved service port. If the 15K HV voltage is less than 300V, 10K HV voltage is less than 210V, 6K HV voltage is less than 120V, please turn off the battery and contact with AEG. Check the battery voltage through the reserved service port. If the 15K HV voltage is less than 300V, 10K HV voltage is less than 210V, 6K HV voltage is less than 120V, please turn off the battery and contact with AEG. Check the battery voltage through the reserved service port. If the 15K HV voltage is less than 300V, 10K HV voltage is less than 210V, 6K HV voltage is less than 120V, please turn off the battery and contact with AEG.| Contact with AEG for further action.
Contact with AEG for further action.
Contact with AEG for further action.
---|---|---|---
N/A| 1) Battery firmware is not updated to latest.| Please check the AEG smart
energy cloud for battery firmware reversion.| Updating the battery firmware to
the latest.
Master battery is white, but not all slaver battery are green|
- Battery communication cable is loose or not correct.
- Battery power cable is loose, or not correct connected.
- Communication terminal resistor is not dialed or not dialed correctly.
- Battery firmware is not the latest.
| Check the communication cable status.
Check the battery power cable.
Check the parallel box for the resistor dailling.
Please check the AEG smart energy cloud for battery firmware reversion.
| Replug or change the communication cable. Fasten the power cable.
Dail the terminal resistor according to manual or SOP.
Upgrade the firmware to the latest.
N/A|
- The Wifi network is not compatible.
- Connecting fail.
- System establish failed due to S/N invalid.
| Check the ender user network type.
APP will remind.
APP will remind.
| Please choose only 2.4G WiFi mode.
Please read the SOP of WiFi setting up.
Contact with AEG for further
action.
N/A|
-
- Battery reach to 1st level alarm such as battery over voltage.
-
- Battery reach to 2nd level alarm such as battery over voltage.
| Please check the AEG smart energy cloud for battery alarm information.
Please check the AEG smart energy cloud for battery alarm information.
| Please ignore it, this alarm message is only used for inverter strategy. The power of charging/ discharging will be reduced.
Please ignore it, this alarm is for inverter strategy.
Yellow| 1) Battery reach to 3rd level alarm such as battery over voltage.| 1)
Please check the inverter LCD/LED or APP for the battery alarm information.
2)Please check the AEG smart energy cloud for battery alarm information.|
Battery will shut down, please contact with AEG for further action.
---|---|---|---
NOTE
Damage to the battery system due to under voltages
- Charge the over-discharged system within 7 days when the temperature is above 25oC.
- Charge the over-discharged system within 15 days when the temperature is below 25oC.
- If the battery system doesn’t start up, please contact Solar Solutions AG after-sales service within 48 hours. Otherwise battery could get permanently damaged.
PRODUCT END OF LIFE
Please return any electrical equipment that you no longer use to the
collection points provided for their disposal. Information concerning where
the equipment can be disposed of can be obtained from your local authorities.
The battery pack is suitable for recycling through a professional battery recycling company
The wheelie bin symbol on the AEG product labels means that the equipment shall be disposed of as special waste in accordance to the local regulations.
DISCLAIMER OF LIABILITY
The use of this manual and the conditions or methods of installation,
operation, use and maintenance of this product are beyond Solar Solutions’s
control. Solar Solutions expressly disclaims liability for loss, damage, or
expenses arising out of or in any way connected with such installation,
operation, use or maintenance.
Solar Solutions will not be responsible for consequences caused by any of the following events
- Damage caused by transportation.
- Storage conditions do not meet the requirements specified in the manual, resulting in product damage.
- Incorrect storage, installation, and use of the product.
- Product installation and operation performed by unqualified personnel.
- Failure to comply with the operation instructions and safety precautions set forth in this manual.
- Product installation or operation in extreme environments that are not covered in this manual.
- Product installation or operation in environments not specified in the related international standards
- Exceeding the operation range of the parameters listed in the product‘s technical specifications.
- Unauthorized product disassembly and modification, or modification of the product‘s software.
- Product damage caused by abnormal natural events (force majeure, such as lightning strikes, earthquakes, fires, storms, etc.)
- Warranty expiration without extension of the warranty period.
- No responsibility is assumed by Solar Solutions for any infringement of patents or other rights of third parties which may result from the use of this product. No license is granted by implication or otherwise under any patent or patent rights.
CONTACT
- Solar Solutions BV
- Finlandlaan 1
- 2391PV Hazerswoude-Dorp, The Netherlands www.aeg-solar.com
- Mail: service@solarsolutions.ag
- AEG is a registered trademark used under license from AB Electrolux (publ).
- Solar Solutions Products BV
- Finlandlaan 1 2391PV Hazerswoude-Dorp The Netherlands service@solarsolutions.ag | www.aeg-solar.com
- AEG is a registered trademark used under license from AB Electrolux (publ).
References
Read User Manual Online (PDF format)