Mechanical Data

  • Dimension : 1100 mm(D)647 mm(W)2010 mm(H)
  • Empty Cabinet Weight : 221 KgsDettaglio 42U-100Ah-12V Battery Cabinet-fig1 Dettaglio 42U-100Ah-12V Battery Cabinet-fig2

Battery Cabinet & Battery Requirement

  • Number of Lead-Acid Cells: 12V 100Ah x 32 Batteries
  • Number of Lead-Acid Cells: 12V 100Ah x 36 Batteries
  • Number of Lead-Acid Cells: 12V 100Ah x 40 Batteries
  • Lead-Acid Battery maximum size(mm): L W H = 343 173 224

Pre-installation Description

  • Battery cabinet:
    The marked “F” means front side of battery cabinet; the other marked “R” means rear side of battery cabinet.

  • Battery tray:
    The cabinet include 6 layers totally of battery trays from L1 (bottom) to L6 (up).Dettaglio 42U-100Ah-12V Battery Cabinet-fig4

How to link battery cabinet with UPS

Connection cable specification

  • For 250A circuit breaker in 1/0 AWG wireDettaglio 42U-100Ah-12V Battery Cabinet-fig5
  • For 400A circuit breaker in 1/0 AWG double wireDettaglio 42U-100Ah-12V Battery Cabinet-fig6
Battery Cabinet Link with UPS

Internal wiring

FOR 12V 100Ah x 40 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig7

FOR 12V 100Ah x 36 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig8

FOR 12V 100Ah x 32 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig9

Installing battery cabinet

  • Step1.
    Pull out the latch from door hinge then remove the front door.Dettaglio 42U-
100Ah-12V Battery Cabinet-fig10

  • Step 2.
    Unscrew the M4 screws (12 pcs) by cross screwdriver and then remove the side panels.Dettaglio 42U-100Ah-12V Battery Cabinet-fig11

  • Step 3.
    Unscrew the M6 screws (4 pcs) form each battery tray and remove all the battery trays from cabinet.Dettaglio 42U-100Ah-12V Battery Cabinet-
fig12

  • Step 4.
    Install the battery into the battery cabinet from L1 (bottom) and connect with battery. (See chapter 3.2.1 internal wiring “L1”)

FOR 12V 100Ah x 40 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig13

FOR 12V 100Ah x 36 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig14

FOR 12V 100Ah x 32 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig15

  • Step 5.
    Install the battery tray and using M6 screws to fix the battery tray.Dettaglio 42U-100Ah-12V Battery Cabinet-fig16

  • Step 6.
    Install the battery into the battery cabinet and connect with battery. (See chapter 3.2.1 internal wiring “L2”)

FOR 12V 100Ah x 40 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig17

FOR 12V 100Ah x 36 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig18

FOR 12V 100Ah x 32 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig19

  • Step 7.
    Install the battery tray and using M6 screws to fix the battery tray.Dettaglio 42U-100Ah-12V Battery Cabinet-fig20

  • Step 8.
    Install the battery into the battery cabinet and connect with battery. (See chapter 3.2.1 internal wiring “L3”)

FOR 12V 100Ah x 40 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig21

FOR 12V 100Ah x 36 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig22

FOR 12V 100Ah x 32 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig22

  • Step 9.
    Install the battery tray and using M6 screws to fix the battery tray.Dettaglio 42U-100Ah-12V Battery Cabinet-fig24

  • Step 10.
    Install the battery into the battery cabinet and connect with battery. (See chapter 3.2.1 internal wiring “L4”)

FOR 12V 100Ah x 40 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig25

FOR 12V 100Ah x 36 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig26

FOR 12V 100Ah x 32 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig27

  • Step 11.
    Install the battery tray and using M6 screws to fix the battery tray.Dettaglio 42U-100Ah-12V Battery Cabinet-fig28

  • Step 12.
    Install the battery into the battery cabinet and connect with battery. (See chapter 3.2.1 internal wiring “L5”)

FOR 12V 100Ah x 40 Batteries
Dettaglio 42U-100Ah-12V Battery Cabinet-fig29 FOR 12V 100Ah x 36 Batteries
Dettaglio 42U-100Ah-12V Battery Cabinet-fig30FOR 12V 100Ah x 32 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig31

  • Step 13.
    Install the battery tray and using M6 screws to fix the battery tray.Dettaglio 42U-100Ah-12V Battery Cabinet-fig32

  • Step 14.
    Unscrew the M4 screws (4 pcs) form cabinet top and remove the top cover.Dettaglio 42U-100Ah-12V Battery Cabinet-fig33

  • Step 15.
    Install the battery into the battery cabinet and connect with battery. (See chapter 3.2.1 internal wiring “L6”)

FOR 12V 100Ah x 40 Batteries
Dettaglio 42U-100Ah-12V Battery Cabinet-fig34

FOR 12V 100Ah x 36 Batteries

FOR 12V 100Ah x 32 BatteriesDettaglio 42U-100Ah-12V Battery Cabinet-
fig36

  • Step 16.
    Reinstall the top cover and using M4 screws to fix to the battery cabinet.

  • Step 17.
    Reinstall the side panels and using M4 screws to fix to the battery cabinet.Dettaglio 42U-100Ah-12V Battery Cabinet-fig38

  • Step 18.
    Reinstall the front door and reinsert the latch to the door hinge.Dettaglio
42U-100Ah-12V Battery Cabinet-fig39