ES-L215110 Laser TV Screen
**Installation Guide
**
INSTALLATION GUIDE
Hisense Laser TV Screen
Before installing this product, read this guide carefully and make sure you
understand all of the content.
Structure diagram of the laser TV screen
Parameters for the laser TV screen
Name | Fresnel laser TV screen 100 inches |
---|---|
Size | 100″ |
Projected area | 2214 × 1245 mm |
Screen size | 2250 × 1280 × 30 mm |
Package size | 1665 × 430 × 255 mm |
- The above is only the specifications of some main products. If there is a small deviation in the size of the laser TV screen, it is a normal installation measurement error. Please feel free to use it.
Overall structure diagram of the laser TV screen
Tool preparation before installation
Hardware and Parts List
The appearance drawn in this manual is a schematic diagram. Please refer to
the purchased actual object. After opening the package, please carefully check
the parts list.
Please read this manual carefully before using it and keep it properly for reference.
Maintenance of laser TV screen
Use a dust-free soft cotton cloth dipped in absolute ethanol to gently wipe
the frame.
Warning
- Do not touch or wipe the screen with an ordinary towel.
- Do not expose the screen to dripping or splashing.
- Do not place the screen on an unstable cart, tripod, or desktop. Dropping may cause serious damage and injuries.
- Do not scratch or touch the screen with hard or sharp objects.
- Do not expose the screen to direct sunlight.
- Do not place the screen near inflammable, explosive, and other dangerous objects.
Screen assembly steps
( I ) Assemble the inner frame
First, find the white protective sheet (1) in the packing box, spread out the
sheet, and lay it on the clean ground for the following installation:
- Take out all the frames from the foam cotton and gently put them on the sheet separately. Check whether they are missing according to the parts list. Place the inner frame correctly according to the illustration below. Splice upper and lower inner frames (A1) and upper and lower inner frames (A2) with inner frame connectors (C). (Methods: Insert one end of the upper and lower inner frame (A 1) into the inner frame connectors (C), align it with the hole on the inner frame, and use a piece of inner frame corner screw (E) to fix the inner frame, and then connect it with another upper and lower outer frame (A2). Repeat this step to splice the other two sections of the frame), and the two left and right inner frames (B) are inserted into the inner frame connector (D), which are connected with the spliced long inner frame.
(II) Installation of screen surface
- Loosen the screws on the brackets at both ends of the paper tube with an M4 Allen screw wrench (Z2), remove the brackets on both sides, slowly remove the screen surface from the paper tube, and wear installation gloves to prevent the screen surface from being stained with sweat. Carefully unroll the screen surface and lay it on the sheet with the back of the screen facing upward (the side with the label in the back). Please refer to the following illustration for this step:
- There are 6 fiber rods in total, of which 4 are of the same length and are used for two long sides. Insert 4 fiber (J1) rods into the sleeves of the long sides, and the other 2 slightly longer fiber rods (J2) into the sleeves of the short sides.
- Slide the screen edges into the grooves of the pull rod (N) and pull rod (M) as shown in the illustration below.
- Center the inner frame on the back of the screen surface.
5. Ensure that the four sides of the screen are aligned with the outer edge
of the frame. The M4 × 45 pull nail screw (L) is screwed into the Pull pin nut
(K) in the pull rod through the hole in the inner frame hole. Install the four
corners first according to the installation sequence of 1-1 2-2 3-3 4-4 in the
illustration, first the long side and then the short side. Pre-tighten the
screws to ensure that the four sides of the screen are aligned and then
tighten the screws symmetrically. The frame screws can be tightened to the
side of the pull rod and close to the positioning line. If the screen surface
is not flat, adjust the tension of the pull screws until the screen surface is
flat.
(III) Install the outer frame After splicing the long side outer frames (Q1)
and (Q2) with the outer frame connecting screws (S), slightly lift the inner
frame to buckle the outer frame on, and splice the short outer frame (R) with
the outer frame connector (0).
(IV) Paste cushion block
Tear off the release film on one side of the cushion block and paste the
cushion block on the inner frame as shown in the illustration below. After the
screen is hung on the wall, tear off the release film on the other side to fix
the lower side of the screen to the wall
(V) Install wall mounting bracket
- According to the dimensions in the illustration below, after drilling on the wall with a cp8 drill, fix the wall hanging bracket to the wall by inserting the plastic expansion pipe (Z1) into the hole on the wall.
- Tear off the protective films on the four corners of the screen. The screen stands upright, and the Down label on the back of the screen is at the bottom. After the screen is hung on the wall, rotate the adjusting rod to adjust the height of the screen to achieve the best display effect.