FR NKISCHE Rigofill inspect System Infiltration Installation Guide
- June 13, 2024
- FR NKISCHE
Table of Contents
Rigofill inspect System Infiltration
Product Information
This installation manual provides instructions for the
installation of infiltration systems and watertight storage
systems. The manual is applicable to Rigofill inspect modules,
which are used above the maximum groundwater level in temperate
climate zones.
The manual also emphasizes the importance of following safety
provisions in the building industry.
Product Usage Instructions
2.1 Transport and Storage
Rigofill inspect modules are delivered packed in units of four
(half blocks in units of eight) each. It is recommended to unload
the packages using forklifts, cranes, or other lifting tools that
have the necessary technical equipment for lifting gear
operation.
When handling the modules, it is important to avoid dropping,
dumping, or hitting them against each other to prevent damage.
For temporary storage, ensure that the ground is level, solid,
and clean. Do not stack packages more than two high, with a maximum
of four modules per stack, to prevent accidents. In case of a storm
risk, secure the packages and avoid stacking them if possible.
Rigofill inspect modules can be stored outside, but the storage
period should not exceed one year. To protect the material from
direct sunlight, store it in the shade or cover it with
bright-colored, light-tight foil. When transporting the modules at
the construction site, use appropriate equipment or carry them by
hand.
Before installation, carefully check the components for any
defects. It is important to note that the impact strength of the
material decreases in sub-zero temperatures. Damaged modules must
not be installed.
Installation Manual
Rigofill® inspect
Infiltration systems and watertight storage systems
Drainage Systems www.fraenkische.com
2
Rigofill inspect Installation Manual
1 Contact
Contact persons Königsberg headquarters
Sales Director (Export)
Klaus Lichtscheidel +49 9525 88-8066 klaus.lichtscheidel@fraenkische.de
Back office
Dinah Wächter +49 9525 88-8155 dinah.waechter@fraenkische.de
Regional Sales Director (Export)
Markus Blatt +49 9525 88-8609 markus.blatt@fraenkische.de
Carolin Diem +49 9525 88-2229 carolin.diem@fraenkische.de
Julia Möller +49 9525 88-2394 julia.moeller@fraenkische.de
Technology
Pedro Simões +49 9525 88-8360 pedro.simoes@fraenkische.de
Fax +49 9525 88-2522
Viktoria Majewski +49 9525 88-2103 viktoria.majewski@fraenkische.de
Fabian Thiergärtner +49 9525 88-2197 fabian.thiergaertner@fraenkische.de
Jennifer Gernert +49 9525 88-2569 jennifer.gernert@fraenkische.de
Table of contents
Rigofill inspect Installation Manual
3
1 Technical advice
2
2 Rigofill® inspect storage/infiltration module 4
2.1 Transport and storage
4
2.2 Excavating pit and creating bearing
5
2.3 Laying geotextile
6
2.4 Installing Rigofill inspect
6
2.5 Mounting accessories
7
3 Installing inspection shafts
8
3.1 QuadroControl with connections to be opened on site
8
3.1.1 Shaft components
8
3.1.2 Combination of shaft components
9
3.1.3 Selecting connections to be opened
10
3.1.4 Arrangement variants
11
3.1.5 Cutting pipe connections DN 200
11
3.1.6 Cutting tunnel openings
12
3.1.7 Installation
12
3.2 QuadroControl with factory-prepared connections
14
3.3 Rigo Control shafts
14
3.3.1 Installing extension pipes
15
3.3.2 Installing shaft covers
15
4 Final installation steps
16
4.1 Creating geotextile wrapping
16
4.2 Lateral backfilling
16
4.3 Creating cover Rigofill inspect
17
4.4 Use of construction vehicles during installation
18
5 Waterproof systems
18
6 Safety instructions
19
NB Please read this installation manual carefully and follow our instructions.
This installation manual applies to the temperate climate zone infiltration
systems and watertight storage
systems with Rigofill inspect above the maximum groundwater level (e.g.
according to ATV-A 138)
The relevant safety provisions of the building industry apply.
4
Rigofill inspect Installation Manual
2 Rigofill® inspect storage/infiltration module
2.1 Transport and storage
Rigofill inspect modules are delivered packed in units of four (half blocks in
units of eight) each. Preferably unload the packages using forklifts, cranes
or other lifting tools. The excavators must have the technical equipment
required for lifting gear operation. For load handling activities, use the
tunnels of the lower modules either by inserting the fork, slinging with
belts, or using other suitable load handling equipment.
CAUTION Avoid dropping, dumping and hitting Rigofill inspect modules against
each other!
Level, solid and clean ground is particularly important for temporary storage.
ATTENTION Do not stack packages more than two high, four modules each, height
2.7 m, to prevent accidents. In case of storm risk, the packages should be
secured and preferably not stacked!
Rigofill inspect can be stored outside. The storage period outside should,
however, not exceed one year. Protect the material from direct sunlight. Store
in the shade or cover with bright-coloured, light-tight foil. Transport the
modules by hand or using appropriate equipment at the construction site.
Check the components for defects before installation. The impact strength of
the material decreases in sub-zero temperatures. Damaged modules must NOT be
installed!
Weight: full block 20 kg; half block 12 kg.
Rigofill inspect Installation Manual
5
2 Rigofill® inspect storage/infiltration module
2.2 Excavating pit and creating bearing
Excavate the pit according to design specifications. During excavation work,
the walls of the pit must be sloped or constructed such that they pose no
danger to the workers due to downsliding masses. Additionally, national
regulations must be observed. Measures must be taken to ensure that the
excavation pit is free from water during the entire execution time.
In order to install Rigofill inspect modules, a horizontal, level and stable
bearing is essential. To this end, create a levelling layer of approx. 10 cm,
preferably made of crushed stones or gravel (without fine fractions), on the
bottom of the excavation pit. The layer must be compacted carefully and
smoothed to achieve a level surface. The compression level Dpr should be
larger than or equal to 97 % (EV2 45 MN/m² or CBR 12 % top edge of the
bearing). If the soil has been included in the infiltration calculation, the
permeability of the compacted layer must at least correspond to the
permeability (kf value) of the backfill soil (soil groups GE, GW, SE, SW, SI).
ATTENTION The quality of the bedding is decisive for further installation and
strongly affects both bearing and setting properties of the
storage/infiltration systems, particularly in case of multiple-layer designs
and higher loads (soil and traffic loads).
6
Rigofill inspect Installation Manual
2 Rigofill® inspect storage/infiltration module
2.3 Laying geotextile
Wrap the entire storage/infiltration system in RigoFlor geotextile. Before
starting to lay the modules, spread out the geotextile on the planum. The
geotextile must have sufficient lateral excess length in order to eventually
wrap up the entire system.
Important characteristics of geotextile (e.g. RigoFlor) Thickness 2 mm
Puncture resistance: 2.0 kN Geotextile class 3 Characteristic opening width
0.08 mm kf value (at 20 kPa): 6 x 10-² m/s Water permeability acc. to EN ISO
11058: 80 l/sm² Mass per unit area 200 g/m² Resistance: Anticipated resistance
of up to 50 years
in all natural soil types with 4 pH 9 and soil temperature of 25 °C (B.4.2.2,
EN ISO 13438)
ATTENTION Ensure that the geotextile surface is completely closed leaving no
gaps even during backfilling. Edges should overlap at least 50 cm.
2.4 Installing Rigofill® inspect
Rigofill inspect modules must be arranged on the planum according to design
specifications. They must be placed in a row to form swale tunnels as
intended. Installation at sub-zero temperatures requires greater care (impact
stability, please refer to the section on transport and storage).
CAUTION
Modules are slippery when wet or frosty!
ATTENTION
Half blocks must be installed with the “FRÄNKISCHE” inscription in the lower
part of the tunnel.
Rigofill inspect Installation Manual
7
2 Rigofill® inspect storage/infiltration module
2.4 Installing Rigofill® inspect (continued)
Connectors help secure the modules in place. Secure modules using connectors
on the top surface of the module in the centre of each edge that is adjacent
to another module.
Single-layer connector for installation in the roof slab of semi-/single-layer systems
Multiple-layer connector for installation in multiple-layer systems between different layers, for connecting layers with each other
Determination of requirements:
Connector single-layer
multiple-layer
Application Requirement
for single-layer installation
requirement for single-row installation requirement for multiple-row installation
for multiple-layer installation
requirement for 2-layer installation requirement for 3-layer installation
1 pc(s). per module 2 pc(s). per module 1 pc(s). per module 1.3 pc(s). per module
2.5 Mounting accessories
Assembled end plate
End plate
Cover all external tunnel sides which do not connect to shafts with end
plates. If necessary, a DN/OD 110, DN/OD 160 or DN/OD 200 pipe connection can
be cut out.
Adapter end plate DN/OD 160 Adapter end plate DN/OD 200 Connection panel DN 250 KG
Adapter end plate / connection panel
DN/OD 160 and DN/OD 200 inlet pipes can be connected using adapter end plates.
The DN 250 KG connection panel allows the connection of the nominal diameter
DN/OD 250. For the adapter end plate, the connection opening to insert the KG
pipe is already factory-provided. The connection panel is also opened and
features a DN/OD 250 spigot to connect a KG coupling. Twin-wall pipes are
connected using adapters (Ü-KG to be ordered separately). Adapter end plates /
adapter panels are used for pipe connections without shaft only!
8
Rigofill inspect Installation Manual
3 Installing inspection shafts
The following types of shafts can be used with Rigofill systems:
1. QuadroControl with connections to be opened on site 2. QuadroControl with
factory-prepared connections (project shaft) 3. RigoControl (shaft outside the
modular block type structure)
Type and position of inspection shafts are determined according to design
specifications. The shafts must be connected to the corresponding inspection
tunnel.
3.1 Quadro®Control with connections to be opened on site
QuadroControl shafts are delivered in individual parts (shaft base, shaft top,
cone and extension pipe), which can be combined and adjusted on site as
required according to the following instructions. Additionally, please observe
the design specifications.
3.1.1 Shaft components
The individual components are colour-coded.
Quadro cone Connection element between Quadro top and extension pipe
Quadro top + ½ Quadro top Second or further layer of multiple-layer shafts.
Quadro base + ½ Quadro base Single-layer shafts or bottommost layer of
multiple-layer shafts.
3 Installing inspection shafts
3.1.2 Combination of shaft components
Quadro cone ½ Quadro base
QuadroControl ½-layer
Quadro cone
Rigofill inspect Installation Manual
9
Quadro cone
½ Quadro top
Quadro cone
Quadro top
Quadro top
Quadro base
Quadro base
Quadro base
QuadroControl 1-layer
QuadroControl 1 ½-layer
QuadroControl 3-layer
Type Quadro cone ½ Quadro top Quadro top ½ Quadro base Quadro base
Illustration
Height 250 mm 350 mm 660 mm 350 mm 660 mm
Identification Cone, effective height 15 cm Top, bottom open Top, bottom open Base, bottom closed Base, bottom closed
Colour coding
10 Rigofill inspect Installation Manual
3 Installing inspection shafts
3.1.3 Selecting connections to be opened
Each shaft base body has an inlet side and three tunnel sides. The inlet side
is used to connect pipes DN 200 for installation alongside the system. The
connection openings (220 x 220 mm) in the tunnel sides are meant to connect to
the intended swale tunnels.
Inlet
Extension pipe DO 600
Tunnel side facing the module
Ventilation
Inlet side
Tunnel connections to be opened
Inlet Inspection access
Inlet side:
Tunnel side:
If necessary, open the connection
All tunnel connections related to the
DN 200 at the intended height. To do so, planned inspection tunnels must be opened
use a suitable tool, e.g. a Ø 200 mm
in order to ensure optimum ventilation,
circular hole saw (suitable for plastic). water distribution and inspection.
ATTENTION
The tunnel openings and unused connections DN 200 facing the soil must NOT be
opened!
3 Installing inspection shafts
3.1.4 Arrangement variants
Rigofill inspect Installation Manual 11
Corner of the storage/infiltration system: one tunnel connection
Front-end of a single-row storage/infiltration system: Within the storage/infiltration system:
one tunnel connection
two tunnel connections
Side of the storage/infiltration system: one tunnel connection
Side of the storage/infiltration system: two tunnel connections
Legend:
Inlet side (if necessary) open
Tunnel side / inlet side closed
Side of the storage/infiltration system on a single-row system: two tunnel
connections
Tunnel side open
3.1.5 Cutting pipe connections DN 200
A drill with a circular hole saw Ø 200 mm suitable for plastic including a
pilot drill is required to establish pipe connections DN 200 on site.
ATTENTION Make sure that the drilling is carried out vertically and axially in
relation to the pipe connection.
CAUTION
After cutting the shaft wall has been completed, the drill must first be
switched off and brought to a complete halt. Then remove the hole saw from the
opening.
12 Rigofill inspect Installation Manual
3 Installing inspection shafts
3.1.6 Cutting tunnel openings
Use appropriate tools to create tunnel openings.
1
2
CAUTION
Wear protective equipment when creating tunnel openings.
Place the shaft base body onto a level surface. Please ensure that the side to be opened faces upwards.
The corners of the set-back surface must be provided with one drill hole each, Ø at least 12 mm (drill diameter must be larger than the width of the saw blade to be used).
3
4
5
Open the sides of the tunnel opening using appropriate cutting tools.
Remove resulting edges and irregularities on the cutting surfaces with a grater, file or another suitable tool.
Remove chips from the shaft body afterwards. Dispose of cuttings appropriately.
3.1.7 Installation
Installation of shaft elements
The prepared shaft base bodies must be installed at the intended position in
the layout.
The connections of the tunnel sides must be aligned with the respective
Rigofill inspection tunnel, see sub-section 3.1.4 Arrangement variants (page
11) and/or design specifications.
In case of multiple layer systems, the correct order must be ensured. Type
Quadro base and/or ½ Quadro base is intended for the bottommost layer, and
type Quadro top and/or ½ Quadro top for any additional layer. Before
installing the shaft cone, wrap the shaft in geotextile. After the cone has
been installed, cut an opening into the geotextile.
Rigofill inspect Installation Manual 13
3 Installing inspection shafts
3.1.7 Installation (continued)
Installing extension pipes
After wrapping in geotextile and lateral backfilling have been completed (see
following sections), extension pipes must be installed. Mount the extension
pipe onto the shaft cone. Make sure that the shafts and extension pipes are
installed upright and do not shift during compaction.
Temporary construction site cover
The extension pipe bodies are delivered ex works with temporary construction
site covers. Make sure that no dirt, e.g. backfill material, enters the shafts
during the construction period. Do NOT remove the respective temporary
construction site covers before installing shaft covers. Additionally protect
shaft openings against earth slides until final installation of shaft covers.
CAUTION
Shafts must NOT be accessed before installing the cover. If necessary, the
required load transfer to the native soil must be ensured using a wide steel
plate.
Shaft cover
Shaft cover DOM sealing ring Support ring Bearing without stationary loads*
Sediment trap, large
Extension pipe DO = 600
- to be supplied on site
Installing shaft covers Cut the DO 600 extension pipe such that it reaches the
support ring. The gap between the support ring and the shaft cover must be
sealed using a DOM sealing ring. Mount the sealing ring onto the last
corrugation of the extension pipe.
DOM sealing ring
Place a DO 600 sediment trap on the extension pipe. If the start shaft must
feature a gully gutter according to design specifications, a bucket handle (or
feed hopper) and a bucket according to DIN 4052-A4 must be installed.
Gully gutter
Bucket handle DOM sealing ring Support ring
Bearing without stationary loads Bucket*
Extension pipe DO = 600
Shaft covers, concrete support rings, gully gutter, bucket handle and bucket
are not included in the scope of delivery of FRÄNKISCHE Rohrwerke and must be
supplied on site. Install shaft covers according to DIN EN 124, CW 610,
installation according to design specifications.
Place a support ring h = 100 mm according to DIN 4034 under the shaft
cover/gully gutter on an appropriate bearing. Create the bearing from
compacted bearing layer material (EV2 module larger than or equal to 100
MN/m2) or in-situ concrete C 16/20. Avoid interlocking of the bearing with the
corrugations of the extension pipe (use casing aid!). Vertical loads may only
be transferred to the load-bearing underground.
Optionally: gully gutter * to be supplied on site
14 Rigofill inspect Installation Manual
3 Installing inspection shafts
3.2 Quadro®Control with factory-prepared connections (project shaft)
QuadroControl project shafts are delivered unassembled in individual parts
(shaft base body, cone and extension pipe), which are labelled according to
the installation position in the storage/infiltration system. Place the shaft
on the planum of the Rigofill storage/infiltration system. The connections on
the tunnel sides must be aligned with the respective Rigofill inspection
tunnel. In case of multiple-layer systems, the designated order of individual
shaft bodies must be ensured. Before installing the shaft cone, wrap the shaft
in geotextile. After the cone has been installed, cut an opening into the
geotextile.
QuadroControl (project shaft) connection DN 500
Assembly and installation
For the installation of extension pipes and shaft covers see sub-section 3.1.7
Installation (pages 1213).
3.3 Rigo®Control shafts
RigoControl
RigoControl shafts are placed outside the Rigofill layout. A separate bearing
must be created in the hand pit for the shafts. In doing so, a 25 cm deep
sedimentation chamber must be taken into account. Compact the bearing and
level it to reach the required height.
The connection to the Rigofill inspect modules is established using short
connecting pipes, adapters and adapter end plates (included in the scope of
delivery). Adapter end plates (and end plates, if applicable) must be
installed in the block first. Prior to installing the connecting pipes, create
the geotextile wrapping. Cut a cross-sectional opening into the geotextile in
the area of the pipe connection. Secure the resulting geotextile triangles
with an adapter.
ATTENTION
Ensure that the geotextile surface is completely closed leaving no gaps even
during backfilling!
Cross section for pipe connection
Rigofill inspect Installation Manual 15
3.3.1 Installing extension pipes
After wrapping in geotextile and lateral backfilling have been completed (see
following sections), extension pipes must be installed. Install the coupling
onto the RigoControl shaft. Afterwards, insert the extension pipe into the
coupling. Make sure that the shafts and extension pipes are installed upright
and do not shift during compaction.
The extension pipe bodies are delivered ex works with temporary construction
site covers. Make sure that no dirt, e.g. backfill material, enters the shafts
during the construction period. Do NOT remove the respective temporary
construction site covers before installing shaft covers. Additionally protect
shaft openings against earth slides until final installation of shaft covers.
3.3.2 Installing shaft covers
Class B or D cast iron shaft cover, with ventilation openings, CW 410
Concrete support ring DO 400, h = 100 mm Bearing Sediment trap DO 400
Extension pipe DO 400 Shaft cover on the shaft (e.g. inspection shaft) to be
supplied on site Class B or D gully gutter (cast iron), CW 410
Cast iron shaft covers
After the covering has been created (see following section), install the shaft
covers. Cut the DO 400 extension pipe such that it reaches the support ring.
According to the design specifications, a sediment trap DO 400, a dirt trap DO
400 or a filter set DO 400 must be placed onto the extension pipe.
Install shaft covers and/or gully gutters according to the design
specifications. Place a support ring h = 100 mm on an appropriate bearing
under the shaft cover/gully gutter. Create the bearing from compacted bearing
layer material or in-situ concrete C 16/20. Avoid interlocking of the bearing
with the corrugations of the extension pipe (use casing aid!). Vertical loads
may only be transferred to the load-bearing underground.
Concrete support ring DO 400, h = 100 mm Bearing Filter set DO 400 Extension
pipe DO 400
Gully gutter on the shaft (e.g. swale emergency overflow) to be supplied on
site
Class B 125 shaft cover, square
87 270 500
95 500
Square shaft cover for on-site application
Manually cut the extension pipe considering the installation depth of the
cover. Create the height of the backfill at the extension pipe considering a
bedding for the cover to be created, if applicable.
Do not remove the trough from the frame before later installing the cover,
since this might lead to subsequent problems with opening and closing. Make
sure that there are no foreign objects (dirt, etc.) between trough and frame
during installation. The seal glued into the frame limits the space between
frame and trough. Protect the screw heads and edges of the trough and frame
from concrete splashes if the trough shall be filled with concrete. An
installation manual is included with the product.
16 Rigofill inspect Installation Manual
4 Final installation steps
4.1 Creating geotextile wrapping
Rigofill inspect systems must completely be wrapped in geotextile (e.g.
RigoFlor). QuadroControl shafts are part of the cubage of the storage/
infiltration system and must be wrapped as well. At the edges, sufficient
overlapping shall be provided (at least 50 cm) to make sure no backfill
material enters the system. Produce sand-tight pipe inlets by crossshaped
cutting of the geotextile.
ATTENTION Ensure that the geotextile surface is completely closed leaving no
gaps even during backfilling!
4.2 Lateral backfilling
Connectors secure the individual Rigofill inspect modules and prevent the
storage/infiltration module from shifting during backfilling.
Use non-cohesive, non-frozen earthwork material with a maximum grain size of
32 mm for backfilling.
Distribute the backfill material evenly and compact it in layers of max. 30 cm
using a light or medium compacting machine (area vibrator or vibratory
rammer). In doing so, a compaction level Dpr of larger than or equal to 97 %
should be achieved. The modules must NOT be damaged. National guidelines for
earthworks (such as ZTV E-StB) must be adhered to.
Make sure that the overlapping geotextile is not pulled apart during
backfilling and compacting, and that the Rigofill inspect modules are not
damaged!
The permeability of the backfill must at least correspond to the permeability
of the backfill soil.
Rigofill inspect Installation Manual 17
4 Final installation steps
4.3 Creating the cover
SLW 60 / HGV 60
The storage/infiltration system must be covered according to design
specifications. Non-cohesive, compactable graded earthwork material with a
maximum grain size of 32 mm should be used for the cover, which is a mandatory
requirement under traffic areas! Frozen soil is not permissible! Additionally,
national guidelines for earthworks (such as ZTV E-StB) apply here as well.
Stability analysis
Storage/infiltration systems are subsoil structures and must have sufficient
loadcarrying capacity against impacting soil and traffic loads. The stability
must be proven according to Eurocode, taking into account partial safety
factors and/or limiting factors. With conventional installation parameters,
depths of cover of DC max. 4 m and soil depths of DS max. 6 m are possible for
infiltration systems. A project-specific stability analysis can be prepared by
FRÄNKISCHE. Under traffic areas, a minimum cover DC of 80 cm must be observed.
HGV 60; specific weight of soil 18 kN/m³; friction angle 28°; = 0.3; mean soil temperature 23 °C
ATTENTION
Note for HGW over structure soil: Rigofill inspect systems, which are used as
watertight storage systems with impermeable membranes, have been designed for
application above the highest groundwater level (HGW). Use in groundwater is
possible under corresponding technical conditions after consultation with
FRÄNKISCHE. Please contact us!
Standard installation under a traffic area SLW 60 / HGV 60
Traffic area
Superstructure according to relevant guidelines, e.g. RStO 12
Upper levelling layer
Planum EV2 45 MN/m2 CBR12 %
Rigofill inspect
Lower levelling layer 2) Subsoil
Bearing EV2 45 MN/m2 CBR12 % HGW
(highest groundwater level)
- Lower cover upon request! 2) At least the same permeability (kf) as the subsoil
35 cm 80 cm DC 4 m 1)
National guidelines, e.g. RStO 12, must always be observed for installation
under traffic areas. To build the planum for the subsequent road construction,
a cover must be provided, preferably a gravel sub-base with a thickness of at
least 35 cm. Other construction materials normally lead to greater depths of
cover.
Generally, at the surface of the cover (= planum), a uniform modulus of
deformation EV2 larger than or equal to 45 MN/m² or CBR larger than or equal
to 12 % must be achieved.
Soil layers must always be provided and compacted in layers of no more that 30
cm. The compaction level Dpr should be larger than or equal to 97 %.
Compacting must be carried out by means of light or medium area vibrators
only!
DS 6 m 1)
approx. 10 cm
CAUTION
Compacting by means of vibratory rollers and explosion rammers is not
permissible!
18 Rigofill inspect Installation Manual
4 Final installation steps
4.4 Use of construction vehicles during installation
Use of vehicles when applying the first cover layer The first cover layer can
be applied, for example, using a wheel loader or a front-type mobile
excavator. For a wheel loader or mobile excavator with a maximum total weight
of 15 tons (chain, 4 wheels, twin-tyres), a compacted cover of at least 30 cm
must be placed over the storage/infiltration system. Possible formation of
ruts must be taken into account! Avoid steering manoeuvres at this
construction stage.
Use of construction vehicles Driving over the cover with heavy construction
vehicles with a wheel load of up to 50 kN (e.g. HGV 30) is possible if the
thickness of the compacted cover is no less than 60 cm. Possible formation of
ruts must be taken into account! When dumping the earthwork material, the
wheel load of 50 kN must not be exceeded; if necessary, load distribution
plates must be used.
CAUTION It is not allowed to use construction vehicles directly on the
modules!
5 Note for waterproof systems
When using Rigofill inspect for stormwater storage, the system can be wrapped
in impermeable plastic foil (KDB). Besides this installation manual, also
observe the manufacturer’s specifications when installing the impermeable
plastic foil (KDB). In addition to the static verification, uplift
verification is required in case of groundwater. Dewatering measures are to be
checked and, if necessary, provided during construction in order to prevent
upwards floating of watertight systems if these are not yet sufficiently
covered. Follow the steps described in this manual to install the modules.
Install and weld the impermeable membrane and execute the impermeability test
of individual weld seams according to the instructions of the
manufacturer/installer.
Applications Stormwater retention Stormwater harvesting (tank) Fire water
storage Combined applications
Rigofill inspect Installation Manual 19
6 Safety instructions
ATTENTION
Staff responsible for installation, assembly, operation, maintenance and
repair must have appropriate qualifications required for this kind of work.
The builder is responsible for organising in detail authority, responsibility
and supervision of staff.
The operational safety of the system components supplied is only guaranteed in
case of proper installation and correct use. Technical threshold values must
not be exceeded.
Observe the accident prevention regulations and relevant standards and
directives for installation, fitting, operation, maintenance and repair!
This includes (in extracts): Accident prevention regulations
– Construction work BGV C22 (Bauarbeiten BGV C22) – Technical wastewater
systems GUV-V C5 (Abwassertechnische Anlagen GUV-V C5) Safety regulations for
working in enclosed spaces of technical wastewater systems GUV-R 126
(Sicherheitsregeln für Arbeiten in umschlossenen Räumen von
abwassertechnischen Anlagen GUV-R 126) Handling biological working materials
in technical wastewater systems GUV-R 145 (Umgang mit biologischen
Arbeitsstoffen in abwassertechnischen Anlagen GUV-R 145) Directives for
working in tanks and narrow spaces BGR 117 (Richtlinien für Arbeiten in
Behältern und engen Räumen BGR 117) Standards – Excavations and trenches
Slopes, planking and strutting, breadths of working spaces DIN 4124 –
Construction and testing of drains and sewers DIN EN 1610 Tool for safety and
health protection in technical wastewater systems
WARNING
Hazards from gases and vapours such as risk of suffocation, risk of poisoning and risk of explosion Risk of falling Risk of drowning Germ pollution and wastewater with sewage High physical and psychological stress during work in deep, narrow and dark spaces And others
DANGER
Non-compliance with the operating manual may result in considerable property damage, injury or death.
CAUTION
The system is part of an entire network. During installation, maintenance,
service and repair work on one component, always consider the entire system.
Avoid work during rain.
Changes or modifications to the system may only be carried out in agreement
with the manufacturer. For safety reasons, use original spare parts and
accessories approved by the manufacturer. The use of other parts voids the
liability for any consequences arising therefrom.
General information on using our products and systems:
Information about or assessments of the use and installation of our products
and systems are exclusively provided on the basis of the information
submitted. We do not assume any liability for damage caused by incomplete
information. If the actual situation deviates from the planned situation or if
a new situation occurs or if different or new installation techniques are
applied, these must be agreed upon with FRÄNKISCHE, since these situations or
techniques may lead to different conclusions. Notwithstanding the above, the
customer is solely responsible for verifying the suitability of our products
and systems for the intended purpose. In addition, we do not assume any
liability or responsibility for system characteristics and system
functionalities when third-party products or accessories are used in
combination with FRÄNKISCHE systems. We only assume liability if original
FRÄNKISCHE products are used. For use in other countries than Germany,
country-specific standards and regulations must also be observed.
All information provided in this publication is generally up to date at the
time of printing. Moreover, this publication was prepared with the greatest
possible care. However, we cannot rule out printing errors or translation
mistakes. Furthermore, we reserve the right to change products, specifications
and other information, or changes may be necessary due to legal, material or
other technical requirements, which no longer could be considered for this
publication. For this reason, we are unable to accept any liability if this is
based solely on the information contained in this publication. Instrumental in
connection with information about products or services is always the purchase
order, the concrete product purchased and the related documentation or the
information provided by our specialist staff in the specific case.
FRÄNKISCHE Rohrwerke Gebr. Kirchner GmbH & Co. KG | Hellinger Str. 1 | 97486
Königsberg / Germany Phone +49 9525 88-2200 | Fax +49 9525 88-92200 |
marketing@fraenkische.de | www.fraenkische.com
EN.90067/2.12.22 | Subject to change without notice | Cat. no. 5000-1723-00X |
10/2022 [DE.90043/4.10.22]
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>