LABOUNTY UPX250 Universal Processors Instruction Manual

July 9, 2024
LABOUNTY

LABOUNTY logo

UPX
UNIVERSAL PROCESSORS
SAFETY, OPERATION & MAINTENANCE
514821 User Manual 4/2024 Ver. 8
LABOUNTY UPX250 Universal Processors

PREFACE

This manual contains information for the safe operation and maintenance of the LaBounty UPX Universal Processor.
Read the entire manual before the initial start-up of the attachment. It is important to know the correct operating procedures of the attachment and all safety precautions to prevent the possibility of property damage and personal injury.
The LaBounty attachment has been designed and manufactured with high quality materials and care in workmanship.
The instructions in this manual have been prepared to ensure that, when followed properly, the attachment will provide efficient and reliable service. Continuing product development and improvement may have caused changes in the attachment that are not reflected in this manual. If a question arises regarding the operation or maintenance of the attachment, contact a LaBounty dealer for the most current information available.
IMPORTANT
This operator’s manual must accompany the attachment at all times and be readily available to the operator.
MANUAL REPLACEMENT
Should this manual become damaged, lost or additional copies are required, immediately contact any authorized LaBounty dealer. You may also download a PDF copy at the LaBounty website.
REGISTRATION FORM
The Warranty Registration Form must be filled out by the dealer or customer and returned to LaBounty indicating the date the machine went into service.
POSSIBLE VARIATIONS
LaBounty cannot anticipate every possible circumstance that might involve a potential hazard, as the owner’s requirements and equipment may vary. Therefore, the warnings in this publication and on the product may not be allinclusive
and you must ensure that the procedure, application, work method and operating technique is safe for you, and others, before operation.
PUBLIC NOTICE
LaBounty reserves the right to make changes and improvements to it’s products and technical literature at any time, without public notice or obligation. LaBounty also reserves the right to discontinue manufacturing any product at it’s
discretion, at any time.
WARRANTY
All work or repairs to be considered for warranty reimbursement must be authorized by the LaBounty Service Department before work is started. Any alterations, modifications or repairs performed before authorization by the LaBounty Service Department will render all warranty reimbursement consideration null and void without exception.
Improper operation or improperly performed maintenance may render any warranty null and void.

SAFETY

| The Safety Alert Symbol alerts you to potential personal
injury hazards. Obey all safety messages that follow to avoid possible injury or death.
---|---
Warning-icon.pngDANGER| Indicates an imminently hazardous situation which will result in death or serious injury.
Warning-icon.pngWARNING| Indicates a potentially hazardous situation which could result in death or serious injury.
Warning-icon.pngCAUTION| Indicates hazards that could result in damage to the equipment or personal injury.
Warning-icon.pngNOTICE| Indicates important procedures.

Your safety and the safety of others is a direct result of how you operate and maintain your equipment. Read and understand this manual and other safety information provided with the base machine and be sure that you understand all controls and operating instructions before attempting to operate this equipment.
Failure to follow the safety precautions can result in personal injury, death or property damage.
Carefully read all safety messages in this manual and on your equipment safety signs. Keep safety signs in good condition. Replace missing or damaged safety signs.
Because LaBounty cannot foresee all hazardous circumstances, the precautions listed in this manual and on the equipment are not all-inclusive. If a procedure, method, tool or part is not specifically recommended by LaBounty, determine whether it is safe for you and others, and that the equipment will not be damaged or made unsafe as a result of your decision to implement it.
The basic rules are summarized in this section of the manual. They also appear throughout the manual along with additional specific rules for safety and operation.

GENERAL

  • If the attachment is not functioning properly, shut down the machine, follow proper Lock-out / Tag-out procedures and follow proper repair procedures.

  • Remove and replace any damaged or worn parts with parts recommended by LaBounty. Use of parts that are not factory approved may cause damage or unnecessary downtime and may void the warranty.

  • NEVER operate equipment without the original safety guards in place.

  • DO NOT process material with the attachment over the operator’s cab. Doing so will result in severe personal injury or death from falling debris.

  • DO NOT attempt to process brittle materials, such as axles and railroad rail. DO NOT process any material in a position that may propel it toward the operator, other workers, buildings or equipment.

  • Clear all persons and equipment from the area of operation and machine movement. NEVER move loads over people or equipment. When viewing the operation of the attachment, maintain a safe distance of at least 75 feet (23 meters).

  • NEVER approach power lines with any part of the machine. Keep clear at a minimum of 15 feet (5 meters).

  • DO NOT close the attachment on a structure and reverse the excavator in an attempt to pull down material.

  • Use of this tool on certain materials could generate dust potentially containing a variety of hazardous substances, such as, asbestos, silica or lead.
    Inhalation of dust containing these, or other hazardous substances could result in serious injury, cancer or death. Protect yourself and those around you. Research and understand the materials you are processing. Follow safety procedures and comply with all applicable national, state or provisional health and safety regulations relating to them. If appropriate, arrange for the safe disposal of the materials by a qualified person.

  • Disassembly of any pin-connected attachment can be hazardous. NEVER remove any pin unless the attachment is on the ground and blocked up. Serious injury or death could result. Metal chips or debris may fly when a connecting pin is struck. Use a brass drift when striking pins and always wear protective clothing and proper eye protection. Pins may fly when struck with force to drive them in or out. Always keep people clear when removing or installing pins.

  • Do not operate this, or any other equipment, under the influence of drugs or alcohol.

  • DO NOT modify LaBounty equipment without factory authorization. This equipment is designed to do a specific job and alterations could result in injury.

  • ALWAYS lower the boom to the ground before leaving the cab. If it is necessary to work on an attachment off the ground, securely support the machine and attachment. DO NOT support the machine on cinder blocks, hollow tiles or props that may crumble under continuous load. DO NOT rely on a cylinder to hold the attachment in the air. If a control is moved or hydraulic pressure is otherwise released, the attachment may drop. DO NOT work under a machine that is supported only by a jack.

  • DO NOT weld on any structural member unless specifically authorized by LaBounty. Unauthorized welding will void the warranty, may cause structural failure and could result in personal injury.

  • Keep clear of potential pinch points, including the moving upper jaw, cylinder connections, bucket linkages and other moving parts.

  • Before operating the attachment, read and observe all safety instructions in the Operation & Maintenance manual. If you are unfamiliar with any operation or maintenance procedure, seek instruction before proceeding.

  • Inspect the attachment daily. Do not operate a poorly maintained or damaged attachment.

  • Never operate a machine if an unsafe condition exists. Attach a “Do Not Operate” tag to the machine.

BASE MACHINE

  • Ensure that the cab is equipped with the proper safety guards for LaBounty applications. The cab MUST be equipped with an approved Falling Object Protection Structure (FOPS) and cab guarding. The FOPS must meet the requirements of SAE standard J1356. A transparent, shatter-resistant shield covering the front of the cab, is also required. Contact your base machine equipment dealer or manufacturer for more information on the availability of FOPS and cab guarding. Lack of proper FOPS and guards may result in injury or death.

  • Avoid tipping. The attachment will alter the lift capacities of the base machine. DO NOT overload the excavator or serious injury could result. Lift capacities will vary if the base machine is not on level ground. Lifting incorrectly can cause severe injury or machine damage. Use the recommended excavator counterweight. Use short slings and lift the load only as high as necessary.

  • DO NOT allow riders on the machine. Riders are subject to serious injuries, such as being struck by foreign objects or being thrown off the machine.
    Riders also distract and obstruct the operator, resulting in the machine being operated in an unsafe manner. NEVER use the attachment as a work platform or personnel carrier.

  • Check ground conditions before operating. Avoid unstable or slippery areas and position the base machine on firm, level ground. If level ground is not possible, position the base machine to use the attachment to the front or back of the carrier. Avoid working over the side of the base machine.

SAFELY OPERATE EQUIPMENT

  • Establish a training program for all operators to ensure safe operation.
  • Do not operate the tool or attachment unless thoroughly trained or under the supervision of a qualified operator or instructor.
  • Know and obey all OSHA regulations, local laws, and other professional guidelines for your operation.
  • Know your work site safety rules. When in doubt on any safety issue, contact your supervisor or safety coordinator.
  • Assess risks to yourself and others around you before operating the tool or attachment. Start in a work area without bystanders and assess the risks to bystanders including, but not limited to, the risk of serious injury or death caused by the tool or accessories dropped from an elevated height.
  • Do not operate the equipment from anywhere other than the correct operator’s position.
  • Do not alter or remove any safety feature from the excavator or attachment.
  • Stay alert, watch what you are doing and use common sense when operating the tool. Do not operate the tool or attachment if you are tired or under the influence of drugs, alcohol or medication. A moment of inattention while operating the tool may result in serious injury.

HYDRAULIC

  • Do not operate at temperatures above 120°F or below -10 ° F (-23° C).
  • Use only clean hydraulic oil, filling equipment, and lubricants.
  • Hydraulic oil becomes hot during operation. DO NOT come in contact with hot hydraulic oil as it could cause severe burns. Wear adequate protective clothing and safety equipment.
  • DO NOT tamper with hydraulic lines or components while they are pressurized. Escaping fluid under pressure can penetrate the skin, causing serious injury. Keep hands and body away from pinholes and nozzles which eject fluids under high pressure. Use a piece of cardboard to search for leaks. If ANY fluid is injected into the skin, seek immediate medical assistance.

PPE

  • ALWAYS wear close-fitting clothing and safety equipment appropriate to the job. Safety equipment should be worn at all times when viewing, operating or maintaining the attachment. Safety equipment includes eye protection, hard hat, steel toe shoes, gloves, hearing protection and respirator.

DECALS

LABOUNTY UPX250 Universal Processors - DECALS

TERMS

LABOUNTY UPX250 Universal Processors - TERMSLABOUNTY UPX250 Universal Processors -
TERMS2

INSTALLATION

LABOUNTY UPX250 Universal Processors - approved

Warning-icon.png WARNING
use only approved rigging hardware rated for loads greater than the weight of uPX. Hooking Points are for moving the attachment only. Do not lift other objects or use uPX in a cable-hung application.

  1. Locate flat, hard ground (e.g., concrete floor) for installation. Lift and place the attachment on the ground as shown. Use blocking if necessary.

  2. Remove the Transport Lock Pin.
    Note : insert the Transport Lock Pin when transporting uPX.

  3. Remove the bucket (third member attachment) or the excavator stick (second member attachment). Follow the manufacturer’s recommended procedure.
    Note : Plug hydraulic hoses to prevent contamination.

THIRD MEMBER INSTALLATION

  1. Bring the excavator into position, carefully lining up the stick tip with the UPX mounting bracket. Pin the stick tip to the UPX mounting bracket using the pin provided.

  2. Carefully extend the bucket cylinder to move the bucket linkage. Position the link into the mounting bracket linkage connection.
    Note: it may be necessary to use a lifting device (overhead hoist, forklift, etc.) to position the link.

  3. Pin the linkage connection using the pin provided.

SECOND MEMBER
INSTALLATION

  1. Pin the excavator boom and attachment boom pivot together using the same pin that was used for pinning on the stick.
  2. Clear all personnel and instruct the operator to slowly lift the attachment so there will be enough clearance to pin the excavator cylinder to the cylinder connection on the mounting bracket.
  3. Extend the cylinder rod and connect the cylinder connection. Install the pin provided with the mounting bracket.
    Note : it may be necessary to use a lifting device (overhead hoist, forklift,etc.) to position the cylinder.

THIRD MEMBER-TO- SECOND MEMBER ADAPTER BRACKET (OPTIONAL)
The third member to second member adapter bracket option allows the Universal Processor to be mounted as a third member, then quickly mount as a second member on another, smaller carrier.
Note: Not all combinations of carriers will work. use of carriers must be approved by the LaBounty Applications Department.

THIRD MEMBER INSTALLATION

  1. Locate flat, hard ground (e.g., concrete floor) for installation. Lift and place the attachment on the ground as shown.
    Use blocking if necessary.

  2. Remove the bucket. Follow the manufacturer’s recommended procedure.
    Note: Plug hydraulic hoses to prevent contamination.

  3. Use an overhead crane with a lifting strap through the stick cylinder connection, to lower the adapter bracket into place so the stick connection pin can be installed. Use the existing third member bracket pin.
    Note: ensure the crane and the lifting strap are rated to safely lift the adapter.

  4. Apply a thin coating of grease to the inside and outside diameters of the linkage connection sleeves. Slide the sleeves into the bores on each side of the adapter bracket.

  5. Lower the bracket so the linkage connection bores line. If the bores line up closely, it may be possible to install the pin at this time.

  6. The inside diameter of the linkage connection sleeves are off-center from the outside diameter. This allows the bores on the adapter bracket to be aligned with the bores on the third member bracket by rotating the sleeves. This can be done by pounding against the notches in the head of the sleeve.

  7. Once aligned, the linkage connection pin may be installed. Install the collars to secure the pins.

SECOND MEMBER INSTALLATION
See “Second Member Installation” on page 10

LABOUNTY UPX250 Universal Processors - SECOND MEMBER
INSTALLATION

HYDRAULIC INSTALLATION

Note: refer to “uPX Hydraulic Schematic” on page 33.

Warning-icon.pngWARNING

Do not connect hydraulic lines while they are pressurized.
Escaping fluid under pressure can penetrate the skin, causing serious injury.

Hydraulic Circuit Requirements

Model Jaw Cycle Circuit (Max) Rotation Circuit (Max) Connection
UPX 250 40-70 GPM (151-265 LPM)
4000-5500 PSI (275-380 Bar) 8-10 GPM (30-38 LPM)
2000-2500 PSI (140-170 Bar) Cylinder – 1” Code 62 Flange Rotation – .5” Flat

Face O-Ring
UPX 350| 50-110 GPM (189-416 LPM
4500-5500 PSI (310-380 Bar)| 8-10 GPM (30-38 LPM)
2000-2500 PSI (140-170 Bar)| Cylinder – 1.25” Code 62 Flange Rotation – .5” Flat Face O-Ring
UPX 450| 70-110 GPM (265-416 LPM)
4000-5500 PSI (275-380 Bar)| 8-10 GPM (30-38 LPM)
2000-2500 PSI (140-170 Bar)| Cylinder – 1.25” Code 62 Flange Rotation – .5” Flat Face O-Ring
UPX 750| 80-140 GPM (303-530 LPM)
4500-5500 PSI (310-380 Bar)| 8-11 GPM (30-42 LPM
2000-2500 PSI (140-170 Bar)| Cylinder – 1.5” Code 62 Flange Rotation – .5” Flat Face O-Ring
UPX 950| 120-180 GPM (450-680 LPM)
4500-5500 PSI (310-380 Bar)| 8-10 GPM (30-38 LPM)
2000-2500 PSI (140-170 Bar)| Cylinder – 1.5” Code 62 Flange Rotation – .5” Flat Face O-Ring
UPX 1800| 185-250 GPM (700-945 LPM)
4000-5500 PSI (275-380 Bar)| 8-12 GPM (30-35 LPM
2000-2500 PSI (140-170 Bar)| Cylinder – 2” Code 62 Flange Rotation – .5” Flat Face O-Ring

  1. Connect the hydraulic hoses to the connections located on each side of the upper head.
    Note : Remember to cap all hydraulic hoses and fittings immediately to prevent contamination of the oil.

  2. After installing the hydraulic circuit on the base machine, install additional hydraulic lines up the boom
    • One 1/2 inch (13 mm) diameter case drain line
    Note : These lines will terminate at the end of the boom.

  3. Install jump lines from these hydraulic lines to the attachment bulkhead or manifold fittings.
    Note: Check to make sure all bolts and nuts are properly installed and torqued.

  4. Check for any hydraulic oil leaks or interference.
    Note : Hydraulics will need to be bled before putting into service (see “Bleed the Hydraulic Cylinders” on page 15).LABOUNTY UPX250 Universal
Processors - ROTATION CIRCUIT

OPERATION

BEFORE YOU START

Know Your Safety Program

  • Read and understand this manual and the base machine manual.
  • Know the employer’s safety rules. Consult your foreman for instructions and safety equipment.
  • Learn the traffic rules at the work site. Know the hand signals used on the job and who is responsible for signaling. Take signals from only ONe person.
  • Wear personal protection equipment (PPE) at all times. This includes eye protection, hard had, steel toe shoes, leather gloves and hearing protection that conforms to standards ANSI Z87.1 (Eye and Face Protection), ANSI Z89.1 (Head Protection), ANSI Z41.1 (Foot Protection) and ANSI S12.6 (S3.19) (Hearing Protection).

Know Your Equipment

  • Learn and test the function of all controls. If malfunctions are found, shut the machine down and report the malfunction for repair.
  •  Be familiar with safety devices, indicators, warning devices and caution instructions. They will alert you to conditions that are hazardous.
  • Know the clearances in the work area.

Daily Safety Checks

  • Ensure all decals are installed and legible. Contact LaBounty for replacements as required.

  • Have a DAiLY safety dialog with all workers. Inform them of any abnormal work that is planned. Remind them of the safe working distance.

  • Clear the area. ALWAYS look out for others. In any work area, people constitute a serious safety hazard.
    Before operating, walk around the machine to ensure no workers are next to, under or on it. Warn nearby workers that you are starting up. DO NOT start up until they are out of danger. Review Job Safety Analysis (JSA) with all personnel in the immediate proximity to the work being done.

  • Check the location of cables, gas lines and water mains before operation. Ensure work site footing has sufficient strength to support the machine. When working close to an excavation, position machine with the propel motors at the rear.

  • Keep bystanders clear, especially before moving the boom, swinging the upper structure, or traveling.
    ALWAYS be alert for bystanders in or near the operating area.

SAFETY DEVICES

  • Seat belts
  •  Safety decals
  • Flags and flares
  • Signs and other markings
  • Falling Objects

Protection Structures (FOPS) and Cab Guards

  • Canopies
  • Shields and guards
  • Barricades
  • Warning lights
  • Visual or audible warning devices

Warning-icon.pngDANGER

  • Clear all persons and equipment from the area of operation and machine movement. NEVER move loads over people or equipment. When viewing the operation of the attachment, maintain a safe distance of at least 75 feet (23 meters).
  • Maintain at least 15 feet (5 meters) between the attachment and any nearby power lines.

Warning-icon.pngWARNING

  • KNOW the capacity of the excavator and it’s attachments. DO NOT overload or serious injury could result. The attachment may have altered the machine’s lift capabilities.
  • NEVEr leave the attachment suspended or pass it over people, occupied vehicles or buildings.
  • ALWAYS lower the attachment to the ground and turn the base machine off when leaving the machine unattended.
  • DO NOT close the jaws on a structure and reverse the excavator in an attempt to pull down material. This is dangerous and will damage the excavator and the attachment.

Warning-icon.pngCAUTION

  • This attachment is for processing materials. DO NOT use for unapproved purposes.

  • DO NOT continuously process oversized materials by forcing them into the jaw. This will shorten the life of the attachment.

  • If attachment stalls, scale back the amount of material being processed at one time. Overloading can cause overheating or damage to the hydraulic system.

  • Cycle the cylinder completely when processing.
    Fully cycling will allow hydraulic fluid to circulate and prevents overheating.

  • When working in confined spaces, keep watch on exposed parts to avoid damage.

  • Avoid collision of the boom or jaws, especially when working with limited visibility or inside buildings.
    Know the height and reach of the attachment during operation, transport and when swinging the excavator.
    Watch out for overhead obstacles.

  • DO NOT alter factory preset hydraulics. This may void the warranty.

  • DO NOT use attachment as a jack hammer or wrecking ball.

  • DO NOT operate a poorly maintained or damaged attachment.

  • The attachment is not a dozer. DO NOT position iton the ground and travel forward.

  • Lifting lugs are to be used for shipping and installation.
    Do not use them in cable-hung applications.

ATTACHMENT CONTROLS

Warning-icon.pngWARNING
Learn the control for each movement of the attachment before attempting to operate.
THIRD MEMBER CONTROL
Note: When installed as a third member, use the excavator auxiliary control to open and close the UPX jaws.

LABOUNTY UPX250 Universal Processors - CONTROL

SECOND MEMBER CONTROL

LABOUNTY UPX250 Universal Processors - MEMBER

BLEED THE HYDRAULIC CYLINDERS

Air must be bled out of the cylinders prior to operation. Air in the system leads to cavitation, oxidation of the oil and excessive heat. These conditions promote hydraulic oil break-down, contamination, noise, sluggish operation, reduced component life and potential cylinder damage.

  1. Start with the attachment cylinders fully retracted. Shut off the excavator and operate the jaw controls in order to relieve any existing hydraulic pressure to the attachment cylinders.
  2. Position the attachment so the cylinders are as horizontal as possible. Set the excavator at idle speed.
  3. Slowly open the jaws until a noticeable change in tone of the excavator is heard, indicating full cylinders. Release the controls and do not continue to apply full operating pressure to the cylinders.
  4. Slowly close the jaws until the rods are extended approximately 1/4 stroke.
  5. Retract the cylinder rods all the way.
  6. Repeat steps 3 and 4. Extend the rod 1/4 stroke more each time, until you reach full stroke.
  7. Slowly cycle back and forth, at least five times, to full stroke. Be careful not to apply full operating pressure to the cylinders at this time.
  8. Check the base machine hydraulic fluid level.
  9. Slowly extend and retract the excavator cylinder to it’s limits. Check for interference between the attachment and the excavator boom or stick. Check the hydraulic lines that connect to the attachment . Ensure they are not rubbing
    or getting damaged in any way. Contact your dealer immediately if interference occurs.

OPERATING TIPS

  • Start processing smaller materials and work up to larger materials. This will help you to learn the limitations of the machine and will allow the machine to warm up properly.

  • When handling materials, keep the load as close to the base machine as safely possible. This will provide the greatest machine stability.

  • Avoid handling long, heavy materials off center. Excessive weight held out to one side can force the attachment to rotate or “back-drive”. Back-driving puts increased strain on the rotation system and, if done continually, can lead to
    rotation component problems. The rotator is for positioning only.

  • When processing oversized concrete, make partial bites to start the breakage and then back off before making the next partial bite. This will allow the broken material to fall away between bites.

  • When shearing large steel members, such as I-beams or tubing, try doing it in two cuts rather than one. Pierce the material about halfway through with the first cut, and then finish it off with the second cut.

  • The shear jaws are best capable of processing light, thinner gauge materials immediately after performing blade maintenance. When processing larger materials, the condition of the blades are not as critical. See “Blade Maintenance” on page 16.

  • Sort your scrap to get the highest capacity from the attachment.

  • Understand that the attachment does have limits. Sometimes it may be necessary to downsize very large material by another method before the attachment can process it effectively.

  • Keep the attachment properly maintained. Jaws with excessive blade gaps or dull teeth are much less effective.
    Lack of maintenance can lead to greater problems and potential downtime.

CHANGING JAWS

Warning-icon.pngWARNING
removal of the attachment pins can be hazardous. Never release the weight of the jaw unless it is secured.
Warning-icon.pngWARNING
Avoid all potential pinching points when exchanging jaws.
UPX 250-950

  1. Park the excavator on solid, level ground.

  2. Remove the front cylinder pins and retract the cylinders.

  3. Screw in the stop bar and tack weld into place.

  4. Place the jaws in the LA Bounty Jaw Stand, or other blocking.
    Note : Secure the jaws to prevent them from tipping or falling.

  5. Slide the pivot group pin to the stop bar.

  6. Slowly raise UPX to separate from the jaws.

  7. Insert UPX into another set of jaws.

  8. Insert the main pivot group pin and front cylinder pins. Remove the stop bar.LABOUNTY UPX250 Universal Processors - Separate UPX from Jaws

UPX 1800

  1. Park the excavator on solid, level ground.

  2. Remove the front cylinder pins and retract the cylinders.

  3.  Place the jaws in the La Bounty Jaw Stand, or other blocking.
    Note : Secure the jaws to prevent them from tipping or falling.

  4. Remove the bolts holding the main pivot group pin in place, as shown in Figure 21.

  5. Slowly raise UPX to separate from the jaws.

  6. Insert UPX into another set of jaws.

  7. Insert and secure the main pivot group pin.

  8. Insert and secure the front cylinder pins.LABOUNTY UPX250 Universal Processors - UPX 1800

MAINTENANCE

8-HOUR INSPECTION CHECKLIST
Inspect all safety devices

____ Safety decals are in place an legible (see “Decals” on page 7).
____ Cab protection is in good condition.
____ Excavator warning systems are working.
Visually inspect for damage
____ Check for physical damage to the attachment, jaws, hoses and fittings.
____ Check rotation connections for wear, leaks or failure (see “Hydraulic Inspection” on page 20).
____ Check for damage to the Swift-Lock Teeth (see “Teeth Maintenance” on page 20).
Lubricate all points
____ Lubricate attachment and jaws (see “” on page 21).
____ Lubricate the turntable bearing, if equipped (see “Turntable Bearing Lubrication” on page 23).
____ Lubricate the planetary gearbox, if equipped (see “Planetary Gearbox Lubrication” on page 23).
Inspect bolts and hydraulic fittings
____ Inspect bolts and fittings on attachment and jaws (see “Inspect / Torque Bolts” on page 24).
Inspect connecting pins and retaining hardware
____ Stick connection / boom pivot pin.
____ Link connection / cylinder connection pin.
____ Front and rear cylinder pins.
____ Main pivot group pin.
Inspect pivot group & jaw blades
____ Check main pivot group for play (see “Main Pivot Group Maintenance” on page 25).
____ Inspect blade gap & shear jaw guide blade gap (see “Blade Maintenance” on page 25).
Inspected By:__ Date:
80-HOUR INSPECTION CHECKLIST
Build-up, hard-surfacing & Blade rotation
____ Build-up jaws & check wear plates. Replace if necessary (see “Build Up & Wear Plates” on page 30).
____ Rotate blades (see “Blade Maintenance” on page 25).
____ Inspect the cylinder gap (see “Check the Cylinder Gap” on page 28).
____ Inspect the slide puck and adjust if necessary (See “Slide Puck Adjustment” on page 29).
Inspected By:__ Date:

2,000-HOUR INSPECTION CHECKLIST
Reseal Attachment
____ Replace cylinder seals.
____ Replace swivel manifold seals, if equipped.
Inspected By:__ Date:

HYDRAULIC INSPECTION

Warning-icon.pngCAUTION
Wear personal protection equipment at all times. This includes eye protection, hard hat, steel toe shoes, leather gloves and hearing protection.

  1. Locate flat, hard ground and place the attachment on the ground.
  2. Check the hydraulic oil reservoir and ensure it is filled.
  3. Visually inspect all hydraulic hoses for leaks or damage.

Warning-icon.pngWARNING
Trapped hydraulic pressure may be present after the base machine is shut off. Extreme caution must be taken when removing hydraulic hoses or injury or death could result.

TEETH MAINTENANCE
When the jaw teeth are worn or cracking, performance is decreased and the teeth need to be replaced.

Warning-icon.pngCAUTION
Wear personal protection equipment at all times. This includes eye protection, hard hat, steel toe shoes, leather gloves and hearing protection.
Warning-icon.pngWARNING
Jaw Teeth are very heavy. DO NOT remove a tooth if the tooth is not supported. The tooth may fall and cause injury.

Swift Lock Teeth

  1. Locate flat, hard ground and place the attachment on the ground.
    Note: Work only on the jaw closest to the ground, with the tooth facing up.

  2. Remove the retainer ring using a grinder.
    Note: The retainer rings are welded into place.

  3. Use a soft metal drift and a mallet to drive out the tooth pin.

  4. Remove the tooth from the receptacle.
    Note: Do not lose the retainer ring.

  5. Weld the retainer ring in its place and insert a new Swift-Lock tooth.

  6. Insert the tooth pin.
    Note: insert the tooth pin so that the pin groove will line up and seat in the retainer ring.LABOUNTY UPX250 Universal Processors -
retainer

Weld-In Teeth

  1. Locate flat, hard ground and place the attachment on the ground.
  2. Preheat the area around the tooth receptacle to 250° to 300° F.
  3. Using carbon-air arc gouging, remove the weld material holding the tooth in place.
  4. Remove the tooth. Fill and sand gouges, then clean the tooth receptacle.
  5. Fit the new tooth into place.
  6. Weld the tooth into place.
  7. Cover the weld with a heat blanket and allow it to cool slowly.

LUBRICATION
Use premium grease, No. 2EP. Grease fittings are indicated on the attachment by yellow “GREASE” decals. Each grease fitting requires .3 oz (8 g) of grease. This is about 6 shots of grease from an average grease gun.

LABOUNTY UPX250 Universal Processors - LUBRICATIONLABOUNTY UPX250 Universal Processors - BACK OF
JAW

TURNTABLE BEARING LUBRICATION

Warning-icon.pngWARNING

Stand clear of uPX during rotation.
The turntable bearing has 1 to 4 grease fittings, depending on model type. Use lithium Grade 2 extreme pressure grease.
Note: For operation below 0° F, use grade 0 grease.

  1. Grease a fitting with 4 shots (.2 oz) of grease.
  2.  Stand clear and rotate the attachment 360°.
  3. Grease the same fitting with 4 more shots (.2 oz) of grease, or until grease starts to escape from the bearing seals.
  4. Perform steps 1 through 3 for every grease fitting.LABOUNTY UPX250 Universal Processors - LUBRICATION5

PLANETARY GEARBOX LUBRICATION
Some models use a planetary gearbox to rotate the attachment. The gearbox oil must be changed regularly, based on the Planetary Gearbox Oil Change Schedule.

Planetary Gearbox Oil Change Schedule

FIRST 50 Hours| 250 Hours / 6 Months| 500 Hours / 1 Year| 1000 Hours / 2 Years
SAE 80W – 90| Inspect Oil / Fill if needed| Synthetic ISO 150 @ 104°F| Synthetic ISO 150 @ 104°F

  1. Access the gearbox.

  2. Remove the oil fill plug.

  3. Remove the oil drain plug. Drain oil into a container larger than 2 quarts.
    Note : The plugs are magnetic and will collect metal filings. Discard the filings.

  4. Install the oil drain plug.

  5. Fill the gearbox with oil, as specified in the parts manual.

  6. Install oil fill plug.LABOUNTY UPX250 Universal Processors - OIL FILL PLUG

INSPECT / TORQUE BOLTS
Inspect all bolts for damage. Check the torque of all bolts and replace any bolt that is damaged or has been re-torqued more than once. Always use replacement bolts of the same size and class as the one removed. Unless otherwise specified, use class 10.9 metric hex head cap screws, class 10.9 metric flat head cap screws and class 12.9 metric socket head cap screws. When installing new bolts, ensure that the bolt is clean and dry.
Note : Some bolts have unique torque specifications. Refer to the parts manual.
Warning-icon.pngWARNING
Never use an inferior class fastener. Fastener failure can cause damage, injury or death.

General Fastener Torque Table

Size| Class 10.9| Class 12.9
M10| 41 Ft. Lbs. (55 Nm)| 49 Ft. Lbs. (67 Nm)
M12| 71 Ft. Lbs. (96 Nm)| 85 Ft. Lbs. (116 Nm)
M14| 112 Ft. Lbs. (152 Nm)| 136 Ft. Lbs. (185 Nm)
M16| 173 Ft. Lbs. (235 Nm)| 207 Ft. Lbs. (281 Nm)
M20| 335 Ft. Lbs. (454 Nm)| 403 Ft. Lbs. (547 Nm)
M24| 579 Ft. Lbs. (785 Nm)| 693 Ft. Lbs. (939 Nm)
M30| 1164 Ft. Lbs. (1579 Nm)| 1391 Ft. Lbs. (1887 Nm)
Hydraulic Flange Fastener Torque Table

Flange| Flange Code| Bolt Size| Torque
0.75”| 61| M10 x 1.50| 42 Ft. Lbs. (57 Nm)
1.00”| 61| M10 x 1.50| 42 Ft. Lbs. (57 Nm)
1.00”| 62| M12 x 1.75| 70 Ft. Lbs. (95 Nm)
1.25”| 61| M12 x 1.75| 70 Ft. Lbs. (95 Nm)
1.25”| 62| M12 x 1.75| 70 Ft. Lbs. (95 Nm)
1.25”| 62| M14 x 2.00| 112 Ft. Lbs. (152 Nm)
1.50”| 61| M12 x 1.75| 70 Ft. Lbs. (95 Nm)
1.50”| 62| M16 x 2.00| 224 Ft. Lbs. (304 Nm)
2.00”| 61| M12 x 1.75| 70 Ft. Lbs. (95 Nm)
2.00”| 62| M20 x 2.25| 435 Ft. Lbs. (590 Nm)
| Turntable & Rotation Head Fastener Torque Table
---|---
Size| Class| Torque
Metric| M10| 12.9| 64 Ft. Lbs. (87 Nm)
M12| 10.9| 92 Ft. Lbs. (125 Nm)
M16| 10.9| 224 Ft. Lbs. (304 Nm)
M20| 10.9| 435 Ft. Lbs. (590 Nm)
M24| 10.9| 752 Ft. Lbs. (1020 Nm)
M30| 10.9| 1511 Ft. Lbs. (2049 Nm)
Standard| 0.38”| Gr. 8| 44 Ft. Lbs. (60 Nm)
0.50”| Gr. 8| 154 Ft. Lbs. (209 Nm)
0.75”| Gr. 8| 380 Ft. Lbs. (515 Nm)
1.00”| L9| 900 Ft. Lbs. (1220 Nm)
1.50”| ZN-L9| 2600 Ft. Lbs. (3525 Nm)

Warning-icon.pngNOTICE
replace rotation bolts after 1500 hrs / 2 years. You may need to rotate uPX to access bolts.

MAIN PIVOT GROUP MAINTENANCE

  1. Check for play in the main pivot group BeFOre performing maintenance on jaw blades.
  2. Fully open the UPX jaws.
  3. Lower UPX so the lower jaw is on the ground. Turn off the base machine.
  4. Using a pry-bar between the upper and lower jaw, attempt to move the jaws.
  5. Measure the movement using a dial indicator. If movement is detected, contact your LaBounty Dealer or LaBounty Customer Service.

BLADE MAINTENANCE

Warning-icon.pngCAUTION
Wear leather work gloves at all times during blade maintenance.

Cracker and Pulverizer Jaws

  1. Remove the blade.

  2.  Grind all rough edges from each blade and clean the blade seat.

  3. Rotate the blade.
    Note : each blade has four edges, as shown in Figure 33 & Figure 34. each time you rotate the blade, you use a different edge. Replace blades when all edges are rounded to .25” radius.

  4. Reinstall each blade.
    Warning-icon.pngDANGER
    Stay at least 75 ft. (23 m) when moving.

  5. Cycle the jaws closed. Measure the gap between the upper and lower blade using a feeler gauge. If the gap is larger
    than .060”, shim the blade.

Shimming the Blades

  1. Measure the blade gap.
  2. Shim each blade so that the blade gap is approximately .005” – .010”. Fit the shims between the blade and the blade seat.
    Note : Do not shim out a blade more than .125”. Doing so may cause structural damage and will void the warranty.

LABOUNTY UPX250 Universal Processors - BLADE SEAT

Shear Jaws

  1. Loosen the bolts holding the lower primary and secondary blades in place. Ensure the blades are loose before removing each blade, one at a time.
    Warning-icon.png WARNING
    Never strike a UPX blade with a hardened steel tool. The blade may chip and cause severe injury.
    Note: if the blades are not loose, try the following;
    • Lightly tap on the blade with a soft-faced mallet.
    • insert a soft metal punch into one of the bolt holes and lightly tap against the back of the blade.LABOUNTY UPX250 Universal Processors - NOSE PLATE
PINS

  2. Remove the piercing tip, than the upper primary and secondary blades.

  3. Remove the guide blade..

  4. Place a soft metal punch through the two outer most holes in the nose plate. Drive the pins that hold the cross blade in place. Remove the cross blade.

  5. Grind the rough edges from the blades and clean the blade seats.

  6.  Rotate the blades.
    Note : Each blade has four edges, as shown below. Each time you rotate the blade, you use a different edge.
    replace blades when all edges are rounded to .25” radius.

  7. Reinstall each blade.
    Shimming the Guide Blade
    The guide blade supports the upper jaw. The gap must be checked daily.
    Warning-icon.png DANGER
    Stay at least 75 ft. (23 m) when moving.

  8. Cycle the tool until the side of the piercing tip begins to bypass the guide blade.

  9. Measure the blade gap in multiple spots. If the gap is larger than .020”, add shims, supplied by LaBounty, between the guide blade and blade seat until the gap is .010” – .020”.
    Note : When all of the provided shims have been used, rotate the guide blade, end over end, and shim. Once all provided shims have been used again, replace the guide blade.

Shimming the Primary and Secondary Blades

Warning-icon.pngDANGER
Stay at least 75 ft. (23 m) when moving.

  1. Cycle the jaws closed. Measure the gap between the upper and lower blades using a feeler gauge. If the gap is larger than .015”, shim the blade.
  2. Shim each blade so that the blade gap is approximately .005” – .010”.
    Fit the shims between the blade and the blade seat.
    Note : Do not shim out a blade more than .125”. Doing so may cause structural damage and will void the warranty.

CHECK THE CYLINDER GAP
Note: Measuring the cylinder gap is necessary for UPX 450 and 950 only.

  1. Fully open the shear jaws.
  2. Measure the gap between the rod eye shoulder and the head face, as shown.

LABOUNTY UPX250 Universal Processors - Measuring the Cylinder
Gap

If the cylinder gap exceeds the value in the “Maximum Cylinder Gap” table, contact the LaBounty Service Department at 218-834-6901.

Maximum Cylinder Gap Table

Model| Maximum Cylinder Gap
UPX 350| 0.40 inches (10 mm)
UPX 450| 0.25 inches (6.4 mm)
UPX 750| 0.52 inches (13 mm)
UPX 950| 0.52 inches (13 mm)
UPX 1800| 0.56 inches (14 mm)

SLIDE PUCK ADJUSTMENT
The slide puck keeps the upper jaw in line and should be inspected and adjusted every 80 hours.

Warning-icon.pngDANGER
Do not cycle or move the attachment while removing the slide puck. This will result in severe injury.
Warning-icon.pngWARNING
Keep clear when the attachment is in motion. Avoid pinch points, such as the upper jaw or cylinder. Severe injury could result.

  1. Remove the lock plate screw and the lock plate.
  2. Using a crescent wrench, adjust the slide puck until it begins to touch the upper jaw.
  3. Reinstall the lock plate.
  4. Grease the slide puck using the grease fittings.

LABOUNTY UPX250 Universal Processors - fittings Slide Puck Adjustment
Figure 43

BUILD UP & WEAR PLATES
As the jaws become worn from use, the worn areas will need to be built up to prolong the life of the attachment. Some jaws have wear plates that protect commonly worn surfaces and reduces the need to build up and hard-surface.

Warning-icon.pngCAUTION
Wear safety equipment when welding. This includes eye protection, hard hat, steel toe shoes, gloves, hearing protection and respirator protection. Do all work in a well ventilated area.

Checking and Replacing Wear Plates

Wear bars are welded into the jaw and must be replaced after they have worn down to 1/4 their original thickness.
Using the UPX parts manual, ensure you have ordered the proper wear plate kits.

Installing Wear Bars

  1. Preheat the area around the wear bar to 250° to 300° F.

  2. Remove the worn wear bar.

  3. Fit the new wear bar into the receptacle. Heat the bar locally and bend it into place.
    Note: Wear bars are pre-cut to length and must be formed to the jaw in the field.

  4. Weld the wear bar into place.

  5. Cover the weld with a heat blanket and allow it to cool slowly.LABOUNTY UPX250 Universal Processors - Wear Plates2

SWIFT-LOCK TEETH BUILD UP

  1. Obtain the proper Swift-Lock tooth template. Refer to the parts manual for template part numbers.

  2. Throughly clean the area to be build up. Grind off any existing hard-surface material.

  3. Preheat the area to 200° F (93.3° C) to remove moisture.

  4. Preheat the area to be build up to 300° – 400° F (149° – 204° C).
    Note : Do not exceed 450° F (232° C).

  5. Use the tooth template to determine how much buildup is required.

  6. Using AWS E7018 welding rod, make hard surface beads.

  7. Relieve stress and remove slag after each pass by peening vigorously with an air operated slag peener.

  8. Repeat steps 6 and 7 until the tooth profile matches the build up template.

  9. Grind edges square to match the template.

  10. Using AWS E7018, place underlayment passes.

  11. Apply a bead of Amalloy 814H rod on top of each of the underlayment beads.
    Note: Do NOT apply Amalloy 814H to the base metal.

  12. Relieve stress after each pass by peening vigorously with an air operated slag peener.

  13. Taper the end of each hard-surface bead by grinding.
    Note: Do NOT undercut the weld.

  14. When grinding is complete, peen the area until it is shiny or until the peener cannot dent the weld.
    Note : About 5-10 minutes.

  15. Cover the welded area with a heat blanket and allow to cool slowly.

HYDRAULIC MAINTENANCE

Speed Valve
The speed valve allows the jaws to shift into high speed when the jaws are closing. Two valve spool screws control this speed change, the Main Spool Adjustment Screw and the Pilot Valve Adjustment Screw. Access the adjustments through the side access panel.
Testing the Speed Valve
Close the jaws and observe the movement. If the speed valve is working properly, the jaw closing speed will increase after 1-2 inches of movement.
Adjusting the Speed Valve
If the jaw movement doesn’t shift to high speed when closing, adjust the pilot valve adjustment screw clockwise until the jaws shift speed.LABOUNTY UPX250
Universal Processors - MAIN SPOOL

CONTROL VALVE SCHEMATICS AND DESCRIPTIONS
Crossover Relief Flow

Work Ports (A&B)
SAE #8 O-Ring Boss Ports for 5/8 OD
Tube, 7/8-14UNF-2B
gauge Ports (gA & gB)
SAE #4 O-Ring Boss Ports for 1/4 OD
Tube, 3/8-24UNF-2B

Crossover Relief Flow Control Valve
Work Ports (A & B)
SAE #8 O-Ring Boss Ports
gauge Ports (g1 & g2)
SAE #4 O-Ring Boss Ports
Drain Ports (D & T)
SAE #4 O-Ring Boss Ports

Motion Control Valve
Work Ports (A & B)
SAE #10 O-Ring Boss Ports
gauge Ports (g1 & g2)
SAE #4 O-Ring Boss Ports
Drain Ports (D & T)
SAE #6 O-Ring Boss Ports

UPX HYDRAULIC SCHEMATIC

LABOUNTY UPX250 Universal Processors - SCHEMATIC

EC DECLARATION OF COMFORMITY
We: LaBounty
1538 Highway 2, Two Harbors, MN 55616, USA
hereby declare that the machine specied hereunder.

  1. Category: Universal Processing Attachable
  2. bane La Bounty
  3. Type: UPX250, UPX350, UPX450, UPX750, UPX950. UPX1800
  4.  Septal number of equipment:
    SN: UPK
    Have been manufactured ia conformity with, Directive/Standards| NO| Detalls
    ---|---|---
    Machinery Directive| 121002010
    2006/42/EC:| applies to interchangeable Machinery. ‘interchangeable means a device which, after the putting into service of Machinery Sar acer EN we Oa aery OF Backer y tne operator mew in orders to change is function or a new function.
  5. Special provision for compellation of technical file the person Sited under No.6 is responsible. 
  6. Representative in the Union Patrick Verviers Doubles 17-19 rule Jules Bretonneau Bp 3406 41034 Blols Cedex, France.
    Done ab LaBounty, 1538 Highway 2, Two Harbors, Minnesots, USA 55616
    DateName and Signature :Michael W. kaczrowskl
    Position Oppressions Manager

Ukca declaration of conformity

We: LaBounty
1538 Highway 2, Two Harbors, MN 55616, USA
hereby declare that the machine specied hereunder.

  1. Category: Excavator Mounted Demolition Tool
  2. Make  LaBounty
  3. Type:UPX250, UPX350, UPX450, UPX750, UPX950. UPX1800
  4.  Septal number of equipment:
    SN: UPK
    Has been manufactured ia conformity with, Directive/Standards| NO| Detalls
    ---|---|---
    Directive| 121002010
    S.l.2012/1597|
  5. Special provision for compellation of technical file the person Sited under No.6 is responsible.
  6. Representative in the Union Patrick Verviers Doubles 17-19 rule Jules Bretonneau Bp 3406 41034 Blols Cedex, France.
    Done ab LaBounty, 1538 Highway 2, Two Harbors, Minnesots, USA 55616
    Date
    Name and Signature :Michael W. kaczrowskl  Position Oppressions Manager

LABOUNTY logo

Additional copies of this manual are available by contacting your dealer or the LaBounty parts department, and
requesting a CE Operation & Maintenance manual. You must include the attachment model number and serial number.
LaBounty | 1538 Hwy 2 |
Two Harbors, MN 55616 | 1-800-522-5059

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals