CHROMALOX CHS-1485 Horizontal Electric Steam Boiler Instruction Manual
- June 17, 2024
- Chromalox
Table of Contents
Installation, Operation
and
RENEWAL PARTS IDENTIFICATION
SERVICE REFERENCE
DIVISION 4| SECTION CHS
SALES REFERENCE (Supersedes PQ404-5) PQ404-6
161-048642-001
DATE OCTOBER, 1983
Horizontal Electric Steam Boiler
Model Number CHS 0 – 150 PSI
Boiler Serial No . . . . . . . . . . . . . . . . . . . Power Circuit Voltage .
. . . . . . .. . . . . . . . . . . . .. . . . . . . . .
Model No. . . . . . . . . . . . . . . . . . . . . . . . No. of Power Circuits
. . . . . . .. . . Amps. . . . . . . . . . . . . . .
Electrical Capacity . . . . . . . . . . . . . . . . . Control Circuit Voltage
. . . . . . . . . . . . . . . . . . . . . . . . . . . .
National Board No . . . . . . . . . . . . . . . . Total Amps . . . . . . . .
. . .. Phase . . . . . . . . . . Cy . . . . . . .
IMPORTANT – This data file contains the National Board Registration Certificate approving your generator. It must be kept near the generator at all times.
CHS-360 Steam Boiler
**Specifications — 480 Volt Boilers***
Model Number
| B.H.P. Rating| kW| Contactors| Fuse Size| Delta kW| Power CC Nominal Size (Amps)| Size of 90˚C Wire (M.C.M)| Amps per Circuit| Elements (kW)| Standard Control System|
Output Lbs. per Hr. at 212˚F
---|---|---|---|---|---|---|---|---|---|---|---
CHS-150*|
15.3
| 150| 5| 50A| 60A| 30| 1| 300| 4/0| 181| 2
1| 60
30| 2 P’TROLS|
452
CHS-180*|
18.4
| 180| 6| 50A| 60A| 30| 1| 300| 250| 217| 3| 30|
543
CHS-210*|
21.4
| 210| 7| 50A| 60A| 30| 1| 600| 600 | 253| 3
1| 60
30|
633
CHS-240*|
24.5
| 240| 8| 50A| 60A| 30| 1| 600| 400 | 290| 4| 60|
723
CHS-270*|
27.6
| 270| 9| 50A| 60A| 30| 1| 600| 600| 326| 4
1| 60
30| 3 P’TROLS|
814
CHS-300*|
30.6
| 300| 10| 50A| 60A| 30| 1| 600| 600| 362| 5| 60|
904
CHS-360|
36.7
| 360| 12| 50A| 60A| 30| 2| 300| 250| 217| 2
3| 90
60| SEQUENCER|
1085
CHS-420|
42.9
| 420| 14| 50A| 60A| 30| 2| 600| 350| 254| 4
1| 90
60|
1266
CHS-495|
50.5
| 495| 11| 60A| 100A| 45| 2| 600| 500| 297| 3
1| 135
90|
1492
CHS-540|
55.1
| 540| 12| 60A| 100A| 45| 2| 600| 600| 324| 4| 135|
1628
CHS-630|
64.3
| 630| 14| 60A| 100A| 45| 2| 600| 700| 378| 4
1| 135
90|
1889
CHS-720|
73.5
| 720| 16| 60A| 100A| 45| 3| 600| 400| 324| 5
1| 135
45|
2170
CHS-810|
82.7
| 810| 18| 60A| 100A| 45| 3| 600| 600| 324| 6| 135|
2441
CHS-945|
96.4
| 945| 21| 60A| 100A| 45| 3| 600| 700| 378| 7| 135|
2848
CHS-1080|
110.0
| 1080| 24| 60A| 100A| 45| 4| 600| 500| 324| 8| 135|
3255
CHS-1215|
124.0
| 1215| 27| 60A| 100A| 45| 4| 600| 700| 378| 9| 135|
3662
CHS-1350|
138.0
| 1350| 30| 60A| 100A| 45| 5| 600| 600| 324| 10| 135|
4069
CHS-1485|
152.0
| 1485| 3| 60A| 100A| 45| 5| 600| 700| 378| 11| 135|
4476
CHS-1620|
165.0
| 1620| 36| 60A| 100A| 45| 6| 600| 600| 324| 12| 135|
4883
*150 kW Thru 300 kW Boilers available in 280V and 240V. Check Factory
INSTALLATION
CAUTION: To avoid electrical shock hazard, boilers must be suitably
grounded to earth.
NOTE: Chromalox boilers are pre-tested before shipment; no internal piping or wiring is necessary. WARNING: Substitution of components or modification of wiring without prior consent of Chromalox, Inc. voids warranty.
1. Locate unit on level floor or platform. NOTE: A minimum distance of 60 inches from wall, other equipment, etc. must be allowed for removal of the elements.
2. Complete all piping to boiler. Connect water line to tagged fitting on the motor and pump assembly, if used, or to tagged fitting on water control feeder.
3. When any type of feed other than a pump feed is used – the existing water supply must be 10 pounds greater than the boiler operating pressure to assure water supply maintains proper water level in boiler. Otherwise, lack of water can cause heater failure. Keep feed water line valves open at all times.
4. All water feed systems are connected to supplied water inlet check valve.
5. Connect steam line (with Globe valve) to boiler steam outlet. Valve should be placed as close as possible to boiler outlet.
6. To insure maximum efficiency of supplied kw, all piping from outlet should be insulated.
7. Drain and relief valve piping should be in accordance with state and local codes.
© 2010 Chromalox, Inc.
Figure 1
- High Pressure Control
- Pressure Gauge
- Manual Reset Pressure Control
- Electric Control Box
- Wall
- Blow Down Drain Valve (L)
- Return Inlet (J)
- Heating Elements
- Step Sequencer (Optional)
Figure 2
Figure 3
- Safety Valve (G)
- Steam Outlet (F)
- Wall
- Blow Down Drain Valve (L)
- Check Valve Water Inlet (K)
- Water Level Control
*CHS- thru 1620 have 2 control boxes (See Figure 2). Add 13″ to “B” dimension.
Model Number
| A| B| C| D| E| **F*| G| H| I| J| K**|
L
---|---|---|---|---|---|---|---|---|---|---|---|---
CHS-150 thru CHS-300|
57”
| 45”| 32”| 40”| 68”| 3” NPT| 1”| 25”| 31”| 2” NPT| 1” NPT|
1” NPT
CHS-360 thru CHS-420|
57”
| 45”| 32”| 40”| 68”| 4”| 1”| 25”| 31”| 2” NPT| 1” NPT|
1” NPT
CHS-495 thru CHS-630|
57”
| 45”| 32”| 47”| 86”| 4”| 1”| 34”| 40”| 2” NPT| 1” NPT|
1” NPT
CHS-720 thru CHS-810|
76”
| 58”| 45”| 47”| 94”| 6”| 1-1/2”| 38”| 44”| 2” NPT| 1” NPT|
1” NPT
CHS-945 thru CHS-1080|
76”
| 68”| 45”| 47”| 94”| 6”| 1-1/2”| 38”| 44”| 2” NPT| 1” NPT|
1” NPT
CHS-1215 thru CHS-1620|
86”
| 76”| 56”| 50”| 98”| 6”| 1-1/2”| 40”| 46”| 2” NPT| 1-1/2” NPT|
1” NPT
*4″ and 6″ are flanged.
Typical Plumbing Installation of a Steam Boiler with Condensate Return System
STEAM
WATER
CONDENSATE
VAPOR
-
Vacuum Breaker
-
Safety Valve
-
Globe Valve
-
Insulated Steam Lines
(Pitch Down 5˚) -
Water/Steam Separator
-
Gate Valve
-
Heat Exchanger
-
(Typical Load)
-
Trap
-
Check Valve
-
Drain
-
Boiler
-
Auxiliary Inlet
-
Cold Water
(for Initial Fill) -
Pitch Down 5˚
-
Condensate Return
-
Vent
-
Return
-
Cold Water Make-Up
-
Strainer
-
Centrifugal Turbine Pump
SPECIAL INSTRUCTIONS FOR CUSTOMERS SUPPLYING THEIR OWN CONDENSATE OR PUMP
SYSTEMS.
1. Check the voltage of the motor before making the wiring connection. Some Chromalox boilers are supplied with dual voltage systems. The motor should always match the voltage of the control circuit.
2. The motor circuit should be wired into the pump control as shown in wiring diagram.
3. A heavy-duty vacuum breaker is required when condensate system is used. (part number ES-89369)
Width – 6-1/2
Figure 4 – Motor and Pump Assembly
-
1/2” Water Line
-
1/2” Solenoid
-
1” Discharge
-
to Boiler
-
1/2” Strainer
-
15-1/4” for CHS-150
16-3/8” for CHS-180 to 300 -
1” Condensate Return
-
1” Vent
-
1/2” Water Line
-
Strainers
-
“W” Dimension – Overall Width
-
Motor and Pump
-
1” Drain
-
1” Outlet to Boiler
Model Number
| Max. PSI| Tank Cap. (Gal.)| L| H|
W
---|---|---|---|---|---
CHS-150 thru CHS-300
| 125| 33| 33-1/4| 41-1/2| 21
CHS-360 thru CHS-420| 150| 40| 40| 41-1/2|
21
Figure 5 – Condensate Return System
WIRING
1. Wiring to boiler should be as per appropriate wiring diagram supplied with boiler and in accordance with Local and National Electrical Codes.
2. SAFETY SWITCHES – Purchaser should use a safety switch between his main power source and the boiler. The safety switch should use circuit breakers or fuses and be in accordance with NEC and local codes.
Serious thought should be given to the advisability of using a shunt trip safety switch of the circuit breaker type as an additional safety precaution. It is possible to utilize the spare contacts in the low water cutoff to energize the shunt mechanism on the safety switch. This is an additional safety feature that prevents a dangerous situation should a contactor or relay stick. Activation of the shunt trip device will completely disconnect the boiler from the power supply. (See Figure 7).
3. Since boiler heating elements are susceptible to lightning damage, plants not having lightning arresters that have above-ground electrical cable supply sources should install lightning arresters in the proper size to meet the boiler kw load.
- To Aux. L.W. C.O.
- Hi-Limit Pressuretrol
- Operating Pressuretrols
- Common
- To L2 on Terminal Strip
*Standard on CHS-150 to CHS-300 units in lieu of step sequencer and operating pressuretrol shown in Figure 8
**Figure 6 – Pressuretrol Control System***
-
To Main Switch
-
L.W.C.O. & Pump Control
-
To L2
-
Supply Voltage
-
Shunt Trip Device
(Supplied by Others) -
To Field Wiring Input Terminal
-
To Motor Starter
-
To Aux. L.W.C.O.
Figure 7 – Safety Switch (Field Installed)
SEE FIGURE 6 FOR DETAILED DIAGRAM OF
BOILERS SUPPLIED WITHOUT SEQUENCER.
NOTES
(1) Connect alarm light or bell from A to L2 if alarm is used.
(2) Not included if control circuit fed from optional trans-former or if
pressuretrol control system is used. (See Figure 6)
(3) Each single line component represents a three phase component. (See
Figure 9)
(4) When pressuretrols are used contactor common goes to L2 on the
terminal block. (See Figure 6)
- 120-VOLT CONTROL VOLTAGE MAY BE SUPPLIED FROM OPTIONAL TRANSFORMER
- OPT’L. TRANSFORMER
- FUSES
- FIELD WIRING INPUT TERMINALS 480V, 3ø
- RELAY TRANSFORMER
- TO SUPPLY
- TO MOTOR
- POWER CCT
- PILOT LIGHT
- POWER CIRCUIT RELAY
- FUSE BLOCKS
- COMMON
- CONTACTORS
- MOTOR
- STEP SEQUENCER OPT’L ON 150 – 300KW
- RECYCLE LOAD CONTACT
- OPERATING PRESSURETROL
- HI-LIMIT PRESSURETROL
- TANK GROUND
- PROBE
- AUX. LW.C.O.
- LW.C.O. & PUMP CONTROL
- MAIN SWITCH
- FUSE
- CONTROL CCT
- FLEW WIRING
- MOTOR STARTER
- CONTACTOR COILS
- HEATING ELEMENTS (WIRED IN DELTA)
- SEE FIGURE 9 FOR DETAILED DIAGRAM
Figure 8 – Typical Wiring Diagram
Figure 9 – Power Circuit Detail
- To Power Circuit Relay
- Power Circuit Terminal Block
- To Other Heater Groups
- Typical 3 Phase Heater Group
- Step Sequencer
Electronic Resistance Sensing Amplifier for Auxiliary Low Water Cutoff
Figure 10 – Auxiliary Low Water Cutoff
- 120 Volt Control Voltage
- Hi Limit Control
- Low Water Probe
PRE-OPERATION CHECK
Figure 11 – Automatic Reset Low Water Cutoff Junction Box
- Pump
- Low Water Cut-Off Terminals
- Alarm Circuit Terminals
- Pump Circuit Terminals
- Line
- Pump Switch
- Adjusting Screws
- Cut-Off and Alarm Switch
NOTES
1. Motor, Solenoid Valve and Dotted Control Wiring are included if Motor
and Pump package is supplied. Solenoid Valve only is supplied with 99117 Water
feed.
2. 1/3 HP Motor is controlled directly without use of Motor Starter.
After proper wiring and piping of boiler system is complete, testing of controls can start. Before testing controls, it is recommended that all contactor fusing be removed. This is to prevent possible element failure under test conditions.
CAUTION: Be sure all electrical connections are tight before energizing boiler. Reset all manual reset controls by pushing reset buttons on: (1) high limit control located on top of boiler and (2) McDonnell-Miller located on side of boiler.
A. McDONNELL & MILLER LOW WATER CUTOFF CONTROL OPERATION AND TESTING
1. Be sure all valves from incoming water supply are fully open. Turn boiler switch to “ON” position, pump or solenoid valve will energize, allowing boiler to fill with water. Proper water level is automatically reached with level control supplied. Pump or solenoid feed will shut off at proper water level. Contactor(s) will energize, supplying power voltage to elements.
2. Checking operation of pump switch. (Figure 11) With water level visible in sight glass, partially open drain valve at bottom of boiler. If automatic blowdown supplied, push manual blowdown switch until valve open light is on, hold for few seconds. Water level will fall, allowing float to trip pump switch to “ON” position. Close drain valve or release manual blowdown switch. Pump motor or solenoid valve will energize and water level will resume to normal level in sight glass.
3. Checking low water cutout switch operation, open drain valve completely. If automatic blowdown supplied, push in and hold manual blowdown switch until water level falls enough to trip cutout switch. Close drain valve or release manual blowdown switch. If low water cutout is automatic reset, pump or solenoid will return water level to normal. If low water cutout is manual reset, then manual reset button on McDonnell & Miller low water cutoff control must be pushed to complete circuit. Turn off boiler. Reinstall contactor fuses.
Wiring Diagram – McDonnell & Miller Low Water Cutoff and Pump Control
- Pump
- Line
- For pump motors 1/2 h.p. Single Phase or less, or D.C. 1/4 h.p. or less, wire as main line switch.
B. ADJUSTING OPERATING PRESSURE CONTROLS
1. Chromalox boilers are supplied with operating and high limit pressure controls. One is used for controlling the operating pressure of the boiler while the other is used as a high limit control. To determine the difference in the controls, the high limit has a manual reset lever on top of the case. Also, there is no differential scale present.
2. On all controls, the pressure adjusting screw on the top of the case sets the desired pressure. Turning the screw counterclockwise reduces the pressure setting (see Figure 12). High limit control should be set at 10 psig above the operating pressure of the boiler.
3. The differential adjusting screw on the operating control is set in the same manner as the pressure adjusting screw. This scale setting, plus the main scale setting, equals cutout pressure of the operating control. (Scale A thru F equals 3 psi per letter. L9l B only) L404A Differential is indicated on Scale Plate.
Figure 12 – Pressure Control
- Differential Adjusting Screw
- Pressure Adjusting Screw
- Mercury Switch
- Index Mark
- Pointer
- Leveling Indicator
- Diaphragm Assembly
- Operating Lever
- Pressure Setting Indicator
- Differential Setting Indicator
To check operation of the controls, close steam outlet valve and adjust operating pressure control to a low pressure setting. Also, set high limit control at 10 psig above operating pressure control.
Turn on boiler and allow pressure to build up. When pressure gauge reading approaches set point of pressure control, the switch will trip and shut off boiler. Turn boiler main switch to “OFF”.
To reset pressure control, bleed off enough pressure in the boiler by opening steam outlet drain, or blowdown valve to allow the operating control to reset.
4. HIGH LIMIT PRESSURE CONTROL OPERATION. The high limit is tested in
the same manner but with the operating control set above the pressure setting
of the high limit. (Figure 13)
CAUTION: THIS IS FOR TEST PURPOSES ONLY!
When the high limit trips turn off boiler and reset high limit to proper
setting, the manual reset level must be pushed to resume operation upon
startup.
Wiring Diagram – McDonnell & Miller Low Water Cutoff and Pump Control
- Pressure Adjusting Screw
- Manual Reset Lever
- Mercury Switch
- Index Mark
- Pointer
- Leveling Indicator
- Diaphragm Assembly
- Operating Lever
- Pressure Setting Indicator
- Scaleplate
OPERATION
RECOMMENDED START-UP PROCEDURES
1. Close globe valve on outlet side of boiler. (Customer Supplied)
2. Turn on boiler and allow pressure to build up to operating pressure.
3. Only open globe valve by quarter turns at first, introducing smaller
amounts of steam into process. Avoid opening globe valve all at once. This
will eliminate the possibility of evacuating the boiler of water caused by the
suddenly increased boiling of the water in the vessel as the pressure is
reduced. On boilers where constant pressure is not maintained, globe valve
should be kept partially closed. This will maintain a constant head on the
boiler and stabilize any fluctuation in boiler water level.
NOTE: For best boiler performance, a steam valve 1/4″ smaller than size
of safety valve should be plumbed as close as practicable to steam outlet.
MANUAL BLOWDOWN INSTRUCTIONS
Blowdown is an essential part of boiler operation. It is the best preventive maintenance you can give your boiler and will add years of life to the unit. Make sure a blowdown schedule is established and followed regularly.
In extremely hard water areas blowdown is necessary once a day. In soft water areas, once each week. If there is a particular problem which applies to your own local water condition other than mineral content, take this into consideration in determining which schedule is to be followed.
1. At the end of the working day, while boiler is still operating, turn switch to the OFF position and close water supply valve. De-energize wall mounted safety switch.
2. If blowing-down into a receptacle, allow pressure to decrease to 15-20 psi before opening blowdown valve.
3. It is preferable to connect the blowdown valve directly into a drainage system. If this is done, the boiler can be discharged at operating pressure.
4. When discharge is complete and boiler is drained –
a. close the blowdown valve;
b. open water supply valve;
c. put boiler switch to the “ON” position; and, (d) close wall mounted safety
switch.
5. When refilling is complete turn off the boiler switch unless further operation is desirable.
6. If you have been supplied with a Manual Reset Low Water control as required in some states, the reset button on the control must be pushed before boiler will begin developing pressure. (Do not push reset until boiler has filled with water.) The use of chemical boiler cleaning compounds in these boilers voids all warranties unless approved by manufacturer. Some compounds will damage copper-sheathed heating elements, thereby shortening their life.
AUTOMATIC BLOWDOWN INSTRUCTIONS
(IF FURNISHED) (See Figures 14 and 15)
The Automatic Blowdown is a device which automatically starts up your boiler in the morning; shuts it down at night and blows down (partially drains) the main boiler drain and the low water cut-off column for a predetermined time interval each working day.
The heart of the unit is an electrically operated straight through type ball valve. It is specially designed to handle dirty, corrosive fluids and particles without requiring cleaning or the use of a strainer.
Both the valve and the boiler are controlled by an electric control unit which indicates with pilot lights when the drain valve is in the opened or closed position and when the boiler is ON or OFF. In addition to the automatic control function, the unit has a push button which momentarily de-energizes the boiler and opens the drain valve regardless of the time of day.
Figure 14 – Automatic Blowdown Control Cabinet
- Timer
The unit may also be used to blow down boilers which run continuously, day and night.
INITIAL TESTING – Set the switch marked “Boiler Normal/24-hour duty” located on the panel box to the “Boiler Normal” position.
On the large timer set the “ON” tab to 8 AM and the “OFF” tab to 8 PM. Set the small, time delay relay to “0”.
Turn the larger timer by hand until the “ON” tab passes the “TIME NOW” indicator so that the “TIME NOW” arrow indicates 10AM.
Energize the main feed to the “line terminals” of the unit. The “boiler normal” pilot light as well as the “drain valve closed” light should glow.
Hold down the “drain” button for about six seconds. The “boiler normal” light should go out immediately as well as the “drain valve closed” light. It takes about 4 seconds for the drain valve to open fully at which time the “drain valve open” light should light. As soon as the “drain” button is released, the valve begins to close. When it reaches the closed position, the “drain valve closed” light and the “boiler normal” light should light up again.
Pilot Lights and Switches
Figure 15 – Display View of Automatic Blowdown Control Cabinet
- Boiler Normal
- Valve Open
- Valve Closed
- Toggle Switch
- Manual Drain Push Button
- Valve Actuator
- Motor Drain Ball Valve
Now turn the wheel on the large timer until the “off” tab passes the “time now” arrow. The “boiler normal” light should go out and the valve should begin to open. Once the “valve open” light goes on, the valve should remain open for a few seconds and then automatically close. The “drain valve closed” light should light and the “boiler normal” light should remain off.
NORMAL OPERATION – Set the “Boiler Normal/24-hour duty” switch located on the inside of the control panel to “boiler normal” if the boiler is to be shut down each night. Set it to “24-hour duty” if the boiler is to remain on continuously 24 hours per day (except during blowdown).
Set the tabs on the large timer for the ON and OFF times desired for the boiler, screw in the small black day-skip tabs if the boiler is to remain off for the weekend, etc.
If the boiler is on 24-hour duty set the OFF tab for the time that is desired for blowdown. The ON tab can be ignored, but must remain on timer.
The small time delay relay controls the time that the drain valve remains open. Counterclockwise decreases, clockwise increases blowdown time. Time must be adjusted by trial.
Figure 16 – Typical Wiring for Automatic Blowdown System
- PILOT LIGHT (RED JEWEL)
- WIRE CONN.
- BOILER CIRCUIT
- TO VALVE ACTUATOR
- FUSE 15A/250VAC
- CONNECTOR
- TOGGLE SWITCH
- SWITCH
- TIMER
- JUMPER
- VALVE RELAY “B”
- TIME DELAY
- TIME DELAY ADJUCT.
- BOILER RELAY “R”
OPTIONAL EQUIPMENT FOR CHROMALOX STEAM BOILERS
AUXILIARY LOW WATER CUT-OFF
(See page 4 for Wiring Diagram)
Operation
Operation of this control is accomplished by sensing a minute AC current flowing between submerged contact probe in the boiler shell.
When this minute AC current is conducted through an external circuit resistance up to 100,000 ohms or less, a signal of sufficient magnitude is present to trigger the SCR and, in turn, energize the control relay.
As the water level in the boiler drops below the level of the probe. the AC circuit is broken and the control relay is de-energized. The control will not energize until sufficient water is present in the boiler.
Specifications
Input supply ………………..120 vac/50-60 hz
Delectable Range…………100.000 ohms
Probe Voltage………………24 vac
Probe Current………………10 milliamps
Control Relay …………….Single pole double throw
CAUTION: Control will not work with de-ionized or demineralized water.
PROPORTIONING PRESSURE CONTROL (See Figure 17)
Typical Operation
Pressure variations cause the bellows to expand or contract. Linkage between the bellows and the potentiometer wiper causes the wiper to move across the windings on the potentiometer. This varies the resistance between R and B, and between R and W, causing an imbalance in the circuit connected to the controller.
A proportioning pressure control is used to regulate a motor driven or solid state sequencer. The controller potentiometer, the feedback potentiometer in the motor and a balancing relay in the motor form an electric bridge circuit. As long as the pressure of the controlled medium remains at the set point of the controller, the circuit is balanced; i.e., equal currents flow through both sides of the balancing relay and the relay contacts are open. When the circuit is balanced, the motor does not run.
If the pressure of the controlled medium rises, the wiper in the controller moves toward W. This unbalances the circuit, so a larger current flows through one side of the balancing relay. The “close” contacts in the relay make, causing the motor to drive toward its closed position. As the motor runs, the wiper on the feedback potentiometer moves in a direction balance, the balancing relay contacts open and the motor stops.
Similarly, if the pressure of the controlled medium falls, the wiper on the controller potentiometer moves toward B, and the “open” contacts in the balancing relay make. The motor drives toward its open position until circuit balance is achieved.
The slightest change in the pressure of the controlled medium will cause a change in the number of elements energized to compensate for it, thus keeping the pressure constant. This process is called modulation.
PROPORTIONAL PRESSURE CONTROL ONLY SUPPLIED WITH SEQUENCER
Main Setting – Turn the adjustment screw until the indicator is opposite the low point of the desired throttling range. That is, if the pressure is to be held to a minimum of 50 psi, set the indicator at 50 psi. The pressure will then be maintained between 50 psi and a higher pressure equal to the 50 psi plus the throttling range.
THROTTLING RANGE SETTING L918
After setting the indicator for the minimum pressure, turn the throttling range adjustment screw until the throttling range indicator points to the desired throttling range on the scale. This scale is graduated from “min” to “F”. The value of each division varies with the scale range of the instrument.
Pressure Value Each
Scale Rating **Division on Scale**
0-15 psi 2.2 psi
5-150 psi 3.6 psi
Pressure scale rating will vary depending on pressure control supplied.
CHECKOUT
After the controller has been installed, wired, and set, it should be tested with the system in operation. First allow the system to stabilize. Then observe the operation of the controller while raising and lowering its set point. Pressure should increase when the set point is raised and decrease when the set point is lowered. Use accurate pressure testing equipment when checking out the controller. Do not rely on inexpensive gauges. The controllers are carefully calibrated at the factory.
If the motor or actuator runs in the proper direction when the set point is adjusted, it can be assumed that the controller is operating properly. If it runs in the wrong direction, reverse the B and W wires. Observe the action of the motor to see if it stabilizes. If the motor is moving constantly, widen the proportioning range a little at a time, until the system is stable.
Figure 17
(L91B) Proportioning Pressure Control Used with Sequencer Control
- Adjusting Screw
- Differential Adjusting Screw
IF A CONTROLLER SEEMS
TO OPERATE IMPROPERLY (See Figure 18)
If the controller is suspected of operating improperly, it may be further checked as follows.
1. Leave the controller installed where it is, but disconnect all power to the controlled motor.
2. Loosen the cover screw below the main scaleplate and remove the cover.
3. Disconnect the wires from the controller.
4. Connect an ohmmeter between controller terminals 8 and W to measure the resistance of the potentiometer in the controller. The ohmmeter should read about 135 ohms on an L91B.
5. Connect the ohmmeter between controller terminals W and R and raise the set point of the controller above the actual pressure being measured. The ohmmeter should read the full value of the potentiometer measured in step 4 (135 ohms for an L91B).
6. Slowly lower the set point of the controller while observing the ohmmeter reading. The resistance should drop to zero at some set point below the actual pressure.
7. An approximation of the proportioning range can be made by observing the change in set point required for a resistance change from zero to full value.
8. When the controller is operating properly, reconnect the wires, replace the cover. tighten the cover screw, and reset the controller to the desired value.
9. Reconnect power to the controlled motor.
Figure 18
- Main Scale Setting Indicator
- Main Scale Adjusting Screw
- Proportioning Range Adjusting Screw
- Setpoint
- Ohmmeter
- Increases to 15 Ohms
Note: Terminals are not labeled, but screw-heads are color-coded red (R), white (W) and blue (B).
BOILER SEQUENCER (5 STEP)
RECYCLE FEATURE (See Figure 19)
The step control is designed to drop out all contactors when control circuit is interrupted. On resumption of power, the camshaft rotates to the counter- clockwise (ccw) limit, opening all the load switches. The recycle relay then energizes, pulling in the load contact, and finally the camshaft rotates clockwise (cw) to the position called for by the pressure controller energizing, in sequence, the required load stages.
Figure 19 – Five Step Sequencer
TESTING OPERATION OF SEQUENCER (See Figure 20)
1. With boiler off, remove wiring from pressure control on sequencer low voltage terminal board.
2. Turn on boiler to supply the voltage to sequencer. Short terminal R and B for counter-clockwise rotation and terminal R and W for clockwise rotation.
3. If sequencer operates under this test procedure, but when rewired to pressure controller, does not function, check pressure control. Note that wiring is W-B and B-W-R-R between sequencer and pressure control.
Figure 20
Typical Wiring Diagram for 5 Step Motor Driven Sequencer
- CONTROLLER
- PRESURE DECREASE
- STAGE 1
- STAGE 2
- STAGE 3
- STAGE 4
- STAGE 5
- ON-OFF SWITCH
- FEEDBACK POTENTIOMETER
- (LOAD SWITCH BREAK)
- (R TO B CCW CYCLE)
- (LOAD SWITCH MAKE)
- DELAY TIMER
3WITCHES SHOWN WITH DEVICE DE-ENERGIZED.
REFER TO SPECIFICATIONS FOR NUMBER OF SWITCHES.
DIRECTION OF MOTOR ROTATION IS AS VIEWED FROM THE MOTOR OR POTENTIOMETER END.
C — 0.1 MFD CAPACITORS
1L — CW LIMIT SWITCH
2L — CCW LIMIT SWITCH
1M — CW MOTOR WINDING
2M — CCW MOTOR WINDING
R — 150 OHM RESISTORS
1R — RECYCLE RELAY
2R — BALANCE RELAY
SEQUENCE REVERSER (See Figure 21)
GENERAL:
Sequence Reverser is an automatic switching device which is interposed on an electric boiler between the proportional sequence controller and the heating element contactors. The device is periodically actuated to alter the operating sequence of each of the heating elements, thereby increasing the overall reliability of the boiler.
DETAILS:
The Sequence Reverser consists of an eight-day timer set up for four days on and four days off which energizes and de-energizes double throw relays which are wired to reverse the “firing” order of the heating element contactors with each operation of the timer.
The Sequence Reverser accomplishes its tasks and shows the relative use of each of ten beat stages during the first four days of the cycle. This is how the work load would be distributed on a boiler without Sequence Reverser. It can be seen the early stages are ON most of the time and the later stages are OFF most of the time, since they are used only during heat load peaks. (This analysis assumes hours of use directly affecting component life. Frequency of on/off operations has been ignored because of the limited in-rush associated with beating elements and because of the relative independence of contactor life on number of operations in the resistive load situations.)
It is clear, without sequence reversing, the early stages would tend to fail long before the later stages. The sequence reverser essentially equalizes the relative usages of heating stages. It can be seen, without the sequence reverser the first heat stage is used approximately twice as much as it is with the sequence reverser. This means the boiler will be likely to have its first element failure in half the time without
Figure 21 – Five Step Sequence Reverser
sequence reverser as compared to the boiler with sequence reverser. In addition. boilers without sequence reverser will have many failures spread over a long time while boilers with sequence reversing will require element changes at roughly the same time. (See wiring diagram on Page 4).
Solid State Progressive Sequencer (See Figure 22)
The solid state progressive sequencer provides accurate electronic control of multi-stage loads of the type used in Chromalox steam boilers. It features progressive sequencing (first on-first off) which equalizes the operating time of each load. This control gives visual indication of each energized stage by means of integral solid state light emitting diodes. In the event of power interruption all heating elements are immediately de-energized for safety. When power resumes, the control will re-stage the loads one at a time. Refer to the diagram for visual description of progressive sequencing.
PROGRESSIVE SEQUENCING
The solid state sequencer operates on 120 V AC/60 Hz and each output is relay switched with a load rating of 125 VA at 120 VAC.
Figure 22 – Solid State Sequencer
MAINTENANCE
CAUTION: Hazard of electric shock. Disconnect all power before working on boiler.
Chromalox Electric Steam Boilers are designed for years of trouble-free performance. To establish a good preventative maintenance program, we suggest the building maintenance man or engineer familiarize himself with these simple rules:
1. The use of specific boiler cleaning compounds cannot be recommended. We do recommend that a reputable firm of water treatment engineers be consulted regarding conditioning boiler water. Proper selection must be made of a compound to prevent damage to copper sheath heating elements.
2. The sight glass should be checked daily to ensure the boiler has adequate water.
3. A monthly inspection should be made of the internal wiring. All electrical connections should be checked for lightness.
4. A check for water or steam leaks should also be made and any loose fittings immediately tightened.
5. If boiler is equipped with a Solid State Auxiliary Low Water Cutoff, every four months the probe should be checked for deposits and cleaned, if necessary. This is accomplished by removing the inspection plate, removing the probe (with a standard sparkplug wrench) cleaning and replacing.
Note: The system will not operate if the boiler is using distilled, demineralized or deionized water.
At the same time, one of the bottom heating elements should be removed. If scale has begun to form, all elements should be cleaned and boiler drained and flushed.
6. IMPORTANT: The Manufacturers’ Data Report enclosed within the instruction sheet is very important and must be put in a safe place. You may be called upon to produce it by a State agency.
INSTRUCTIONS FOR ELEMENT REPLACEMENT
CAUTION: Before installing your new elements, be sure the McDonnell- Miller low-water cut-off is operating perfectly and the float chamber and lower equalizer column are completely clear of sludge or other foreign matter. (See Figure 23)
Failure to do this may cause the immediate burnout of the new elements.
All elements are thoroughly checked before shipment. The manufacturer cannot be responsible for burnouts caused by a faulty low-water cut-off.
Figure 23
- 1″ Steam Equalizing Pipe
- Pump and low water control
- Normal Boiler Water Line
- Cut-off Level is arrow mark
- Blowdown Valve
- 1″ Water equalizing pipe
The lower equalizer column can best be examined by breaking the unions on either side and then visually and manually examining the piping with your fingers or probes to see if it is clear and clean.
READ COMPLETELY BEFORE STARTING WORK
1. Disconnect boiler from electric power supply at main safety switch or fuse panel. Then turn boiler switch to “off” position.
2. On automatic feed units, close valve on incoming water line. Drain boiler completely of water.
3. Open boiler door to expose heating element.
4. Disconnect wire (electric) leads connecting element to main power system of boiler. Again note wire connections to facilitate reassembly. Proceed to remove (6) 5/16-18 bolts from flange.
5. Thoroughly clean boiler flange of all foreign material. Be certain no part of old gasket remains on boiler flange.
6. Apply “Slic-Tite” Gasket Compound (or equal) to both surfaces of new gasket supplied with replacement element. Proceed to install element flange assembly with gasket between boiler flange and clement flange. In doing this, be careful to align flange holes so wire connection terminals on element assembly are in line with previously disconnected wire leads to facilitate easy connections.
7. When all (6) flange bolts are tight, connect all wires to terminals.
Make certain wires are clean and bright to assure good electrical contact and
nuts on screws are firmly secured.
CAUTION: Bolts should be lightened 10 a torque of 22 ftlbs.
8. Open water valve so water supply can reach boiler feed mechanism.
9. Put main safety switch to “on” position.
10. Turn boiler switch to “on” position.
11. As boiler automatically refills, observe the new flange assembly for possible leaks. If water is noticed, the bolts must be retightened. Before doing this, turn the boiler off at the main fuse safety switch.
12. As boiler is heated to working pressure, check flange assembly again
for leaks.
CAUTION – Avoid use of chemical cleaning compounds. Follow maintenance
instructions.
RENEWAL PARTS IDENTIFICATION
-
MOTOR DRIVEN SEQUENCER
-
MANUAL RESET HIGH LIMIT PRESSURE CONTROL
-
STEAM OUTLET
-
PRESSURE GAGE
-
SAFETY VALVE
(two provided above CHS-495) -
AUXILIARY LOW WATER CUTOFF (not shown)
-
McDONNELL AND MILLER #157 LOW WATER CUTOFF/PUMP
-
WATER LEVEL SIGHT GLASS
-
FIBROUS GLASS INSULATION
-
INSPECTION PORT
-
BOILER SHELL, CARBON STEEL
-
CHECK VALVE/ WATER INLET
-
INSPECTION PORT
-
2-1″ NPT DRAIN SLOWDOWN GATE VALVES
-
WELDED BASE
-
AUXILIARY INLET
-
VENTILATING LOUVERS
-
CHROMALOX ELECTRIC RESISTANCE HEATING ELEMENTS
-
CONTROL CABINET OF HEAVY GAGE STEEL CONSTRUCTION HINGED W/CAPTIVE FASTENER
-
MANUAL “ON-OFF” SWITCH
-
CONTROL CIRCUIT PILOT LIGHT
-
CONTACTORS
-
FUSING
(not shown) -
PROPORTIONAL PRESSURE, CONTROL (WITH MOTOR DRIVEN OR SOLID STATE SEQUENCER) RANGE 5-150 PSI WITH MECHANICAL STOP AT 135 PSI ALTERNATES 0-15 AND 0-50 PSI.
-
Bellows Base Clamp Assembly
-
Bellows Assembly with Gasket
-
Bellows Base Clamp and Bellows Assembly
Low Water Cutoff and Water Feed Controls
Description|
Part Number
Complete Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-013
Complete Assembly (Manual Reset) . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-026
Complete Head Mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-027
Complete Head Mechanism (Manual Reset) . . . . . . . . . . . . . . . . . .|
300-118538-028
Float and Rod . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . |
300-118538-029
Head Gasket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-030
3 Wire Cut-Off and Alarm Switch . . . . . . . . . . . . . . . . . . . . . . . . . . .|
292-118665-003
3 Wire Cut-off and Alarm Switch (Manual Reset) . . . . . . . . . . . . . .|
292-118665-004
2 Wire Pump Switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
292-118665-002
Junction Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-031
Bellows Base Clamp & Bellows Assembly . . . . . . . . . . . . . . . . . . . .|
300-118538-032
Bellows Base Clamp & Bellows Assembly (Manual Reset) . . . . . . .|
300-118538-033
Bellows Base Gasket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-034
Bellows Base Clamp Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-035
Bellows Base Clamp Assembly (Manual Reset) . . . . . . . . . . . . . . . .|
300-118538-036
Bellows Assembly w/Gasket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-037
B-W Auxiliary Low Water Cut-off . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-038
Heating Elements and Gaskets
Description|
Part Number
30kW, 3 ph, 240V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
155-118524-040
30kW, 3 ph, 480V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
155-118524-021
45kW, 3 ph, 480V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
155-118524-041
45kW, 3 ph, 240V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
155-118524-042
60kW, 3 ph, 240V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
155-118524-026
60kW, 3 ph, 480V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
155-118524-022
90kW, 3 ph, 480V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
155-118524-023
135kW, 3 ph, 480V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
155-118524-043
Element Gasket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
132-146012-002
Hand Hole Gasket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
132-118533-004
Contactors and Contactor Parts
Description|
Part Number
Contactor (50 amp, 115V, 60 cy.) . . . . . . . . . . . . . . . . . . . . . . . . . . .|
072-118525-001
Contactor (50 amp, 240V, 60 cy.) . . . . . . . . . . . . . . . . . . . . . . . . . . .|
072-118525-002
Contactor (60 amp, 115V) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
072-118525-003
Contactor (75 amp, 115V, 60 cy.) . . . . . . . . . . . . . . . . . . . . . . . . . . .|
072-118525-005
Contactor (75 amp, 208/240V, 60 cy.) . . . . . . . . . . . . . . . . . . . . . . .|
072-118525-006
Relay PR 7AY, 115V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
072-118525-008
Relay PR 7AY, 230V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
072-118525-009
Terminal Blocks and Fuses
Description
|
Part Number
Control Circuit Fuse and Block . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
129-118527-001
Fuse Block, Class “J” 100 amp . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
129-118527-003
Power Circuit Fuse, Class “J” 60 amp. . . . . . . . . . . . . . . . . . . . . . . .|
128-118530-003
Power Circuit Fuse, Class “J” 100 amp. . . . . . . . . . . . . . . . . . . . . . .|
128-118530-004
Valves and Gauges
Description|
Part Number
Pressure Gauge 3-1/2, 160# . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
344-118529-024
Gauge Glass Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
347-118537-002
Sight Glass . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
374-118537-009
Safety Valve – 30#, 1” . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
344-118529-006
Safety Valve – 125#, 1” . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
344-118529-020
Safety Valve – 150#, 1” . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
344-118529-025
Check Valve – 1” Spring Type . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
276-118536-003
Safety Valve – 15#, 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
344-118529-008
AUTOMATIC FEED PUMP CONTROLLER
-
Junction Panel
-
3 Wire Switch
-
2 Wire Switch
-
Sylphon Bellow Assembly
(See picture) -
Bellows Base Gasket
-
Head Gasket
-
Float and Rod
Condensate Return Systems
Description|
Part Number
Condensate Return System (Comp.) 1/2 H.P.
115V or 230V, 60 cy. (CHS-150) . . . . . . . . . . . . . . . . . . . . . . . .
. .|
226-118656-002
Condensate Return System (Comp.) 3/4 H.P.
115V or 230V, 60 cy. (CHS-180 to CHS-300) . . . . . . . . . . . . . . . .
(For Boilers CHS-360 through CHS-1350 check factory)|
226-118656-009
Pressure Controls and Sequencers
Description
|
Part Number
Pressure Control Complete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
344-118529-010
Pressure Control Complete (Manual Reset) . . . . . . . . . . . . . . . . . . .|
344-118529-011
Mercury Tube (Two Wire) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
292-118665-001
Pressure Control Type L91B, 0-150 . . . . . . . . . . . . . . . . . . . . . . . . .|
344-118529-015
5 Step Proportional Sequencer . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-005
10 Step Proportional Sequencer . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-008
Pressure COntrol Type L91B, 0-15 . . . . . . . . . . . . . . . . . . . . . . . . . .|
334-118529-016
Parts for Condensate Systems – Hot Water Motors & Pumps
Description|
Part Number
Impeller for Pump (192 or 3/4 H.P). . . . . . . . . . . . . . . . . . . . . . . . .|
266-118671-001
Parts for Condensate Return Systems
Description|
Part Number
Pumps and Motor, 1/2 H.P., 115 Volts or
230 Volts, 1 ph. (CHS-150) . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . .|
226-118656-005
Pump and Motor 3/4 H.P., 115 Volts or
230 Volts, 1 ph. (CHS-180 to 300) . . . . . . . . . . . . . . . . . . . . . .|
226-118656-006
Float Valve – 33 Gallon Tank (CHS-150 to 300 . . . . . . . . . . . . . . . .|
226-118662-006
Seal for Pump (CHS-150 to 300) . . . . . . . . . . . . . . . . . . . . . . . .
. . .
(For Boilers CHS-360 through CHS-1350 check factory)|
251-118657-002
Vacuum Breaker . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .|
300-118538-039
Limited Warranty:
Please refer to the Chromalox limited warranty applicable to this product at
http://www.chromalox.com/customer-service/policies/termsofsale.aspx.
2150 N. RULON WHITE BLVD., OGDEN, UT 84404
Phone: 1-800-368-2493
www.chromalox.com
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>