Kit content

  • Steering adapter (pre-assembled) (x2)
  • Outer joint (pre-assembled) (x2)
  • Thread tap) Mounting hardware (as in the picture) (x1)

Disclaimer

  • Racing part with NO warranty, not for use on public roads
  • Manufacturer disclaims all liability for direct, indirect, incidental or consequential damages, including damage or loss of equipment, cost of purchase or replacement of goods, accident or injuries, or claims of the purchaser that result from the use of the part

Tools / equipment required for installation

  • 10mm hex key
  • 17mm / 19mm / 22mm / 24mm / 27mm / 36mm wrenches or sockets
  • Torque wrench
  • Wire brush / abrasives for paint removal / cleaning of the parts
  •  Hydraulic press for outer joint removal / installation
  • Angle grinder for original outer joint removal (E30 M3 Dorman / E46 non-M / E46 M3 aluminum control arms)
  • Loctite (blue)

Torque rates for the bolts / screws / nuts

  • M10x1 tie rod nyloc nuts: 40Nm
  • M12x1.5 tie rod nyloc nuts: 45Nm
  • M12 nyloc nuts / hex bolt: 100Nm
  •  M14x1.5 nyloc nuts: 120Nm
  • M14x1.5 castle nuts: 85-125Nm (depending on pin hole alignment)
  • Outer joint retainer nuts / inserts: 100Nm

Important notes:

  • Fits only 32mm / 33mm / 41mm / 48.5mm outer joint control arms
  • Control arm end may need to be ground down with aftermarket Big Brake Kits and / or rotors to allow sufficient clearance
  • Tie rod thread may need to be cut down with E30 / E36 M3 3.2 spindles to allow sufficient clearance
  • Tie rod length may need to be shortened for a couple of millimeters with aftermarket tie rod inner / outer ends to allow sufficient toe-in adjustment
  • Steering rack reducers may need to be used depending of wheel specs/offset

wheel fitment chart

MRT Engineering MRT-20003 Roll Center 8

Installation

  1. Remove control arm and unfasten tie rod from the spindle / knuckle, unfasten sway bar from the control arm on E30 / E36 applications.
  2. Install new outer joints

E30 / E36 control arms:

  • Use hydraulic press to press out the original outer joint on the control arm
  •  Clean the bore with wire brush or abrasive
  • Measure and confirm that outer joint diameter match control arm bore size, maximum recommended interference fit 0.4mm
  • Use hydraulic press to install the new outer joint from bottom side as original joint NOTE: Install 48.5mm eccentric outer joints thin side out as in the pictureMRT Engineering MRT-20003 Roll Center 1
  • Insert and tighten outer joint lock nut using a soft tool and a hammer

E46 non-M control arms:

  • Cut out the retaining lip of the outer joint on the bottom side of the control arm and press out the outer joint
  • Clean the bore and flatten the surfaceMRT Engineering MRT-20003 Roll Center 2
  • Measure and confirm that outer joint diameter match control arm bore size, maximum recommended interference fit 0.4mm
  • Use hydraulic press to install the new outer joint from bottom side as original joint NOTE: Install 48.5mm eccentric outer joints thin side out as in the picture
  • Insert and tighten outer joint lock nut using a soft tool and a hammer

E30 M3 Dorman / E46 M3 control arms:

  • Cut out the retaining lip of the outer joint on the bottom side of the control arm and press out the outer joint

  • Clean the bore and flatten the surface
    NOTE: Open up the oval bore on the top side of the control arm to allow adequate articulation for the outer joint

  • Chamfer the edge of the bore and tap it with the thread tool included in the kitMRT Engineering MRT-20003 Roll Center 3

  • Assemble the outer joint dry and confirm that the bearing retainer will index with the bearing and tightens it

  •  Make final installation using Loctite on both bearing and the bearing retainer, secure the bearing retainer with a safety wire

Install tie rod into the steering adapter

  • With E30 / E36 small taper tie rod ends press the tie rod taper adapter flush with the steering adapter surface, with E46 big taper tie rods this adapter is not required
  • With E30 / E36 M3 3.2 spindles check tie rod thread to spindle clearance, shorten the thread if neededMRT Engineering MRT-20003 Roll Center 4
  • Install tie rod into the steering adapter, place the washer convex side up and tighten up the nyloc nut (M10x1 40Nm, M12x1.5 45Nm)

Clean up and flatten the spindle/knuckle mounting surfaces

NOTE: Paint will cause fasteners to loosen up and may lead to failure!

MRT Engineering MRT-20003 Roll Center 5

Install the pre-assembled steering adapter into the spindle/knuckle as in

the pictures

  • Insert spacer between the spindle / knuckle and the steering adapter (tie rod end)
    • E30 non-M: none
    • E36 non-M: 7.5mm
    • E36 M3 3.0: 4.5mm
    • E36 M3 3.2: 1mm
    • E46 non-M: 6mm
    • E46 M3: 7.5mm
  • Tighten up the nyloc nuts (M12 100Nm, M14x1.5 120Nm)MRT Engineering MRT-20003 Roll Center 6

Install spindle/knuckle back into the control arm

  • Install castle nut beneath the outer joint and tighten it up (85-125Nm, see where pin hole aligns the best)
  • Insert and secure the pin

MRT Engineering MRT-20003 Roll Center 7

  • Re-install control arm into the chassis and mount the sway bar
  • Re-align front toe geometry
  • After alignment check and measure whether steering rack stops are required
  • In simplest form steering rack stop is a sleeve made out of Delrin / plastic / soft material which slides on top of the steering rack shaft and stops against the steering rack oil seal. Approximate length for the sleeve is 15 – 30mm (general rule)
  • Remember to check and inspect all fasteners after first 100km and occasionally after every 500km until the fasteners have set properly. Repeat inspection before and after every trackday

If you have any questions, feedback or other comments regarding the kit please reach us via email / WhatsApp or social media direct message:

If you have problems / issues with the kit, please state where you have bought the kit, original Order No. and / or exact model of the kit you have / you supposed to have to ensure we can give you an accurate response All spare parts are available on our webshop and dealerships around the world:
https://mrtengineering.fi/collections/spare-parts
https://mrtengineering.fi/pages/dealers

MRT Engineering Oy, FI31033454 Kuukuja 12 33420 Ylöjärvi, Finland
info@mrtengineering.fi
+358 45 783 636 66

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals